Host Mark Levine (212-335-2723 x.201 or [email protected]) of NYC property management firm EBMG talks with Robert Castellano, Vice President of VDA (212-868-9090 x.128 or [email protected]) on upcoming changes to the NYC requirements on elevator testing, beginning on January 1, 2022.
Email the show! [email protected]
Effective January 1, 2022 several changes to the NYC Building Code and the Elevator and Escalator Safety Code will impact the way elevators will be inspected and tested in the City of New York. Most notably, the NYC Department of Buildings will no longer subcontract “Periodic Inspections” to what were previously known as “PVT Agencies”, but rather the performance of these yearly vertical transportation inspections will become the responsibility of the building owner.
The following additions and/or changes to the NYC Building Code, Article 304 - Elevators and Conveying Systems are being adopted:
Category 1 & 5 Inspections
The completed reports, with all applicable signatures, shall be filed within 21 days after the date of the test. Exception: Reports are not required to be submitted to the department for private residence wheelchair lifts and private residence dumbwaiter devices. However, the owner shall maintain an inspection and test log to be available to the department upon request.
All defects as found in such category test report shall be corrected within 90 days after the date of test. An Affirmation of Correction shall be filed within 14 days of the date of correction.
Periodic Inspections
Periodic inspections shall be performed between January 1st and December 31st of each year at a minimum of three months from the date of any Category 1 testing or previous periodic inspection. Initial periodic inspections on new installations must be performed in the calendar year following the final acceptance test. For private residence elevators, the periodic inspection and Category 1 and/or 5 testing may be performed on the same date. Filing of Periodic Inspections in DOB NOW must be completed within fourteen (14) days of the date of Inspection.
All defects as noted in such periodic inspection report must be corrected within 90 days after the date of inspection. The department may grant an extension of 45 days upon submission of an application by the owner demonstrating a practical difficulty in complying within the 90-day timeframe. In no case shall more than two such extensions be granted for a specific defect. An Affirmation of Correction shall be filed within 14 days after the date of correction.
By Mark Levine (EBMG)4.4
2222 ratings
Host Mark Levine (212-335-2723 x.201 or [email protected]) of NYC property management firm EBMG talks with Robert Castellano, Vice President of VDA (212-868-9090 x.128 or [email protected]) on upcoming changes to the NYC requirements on elevator testing, beginning on January 1, 2022.
Email the show! [email protected]
Effective January 1, 2022 several changes to the NYC Building Code and the Elevator and Escalator Safety Code will impact the way elevators will be inspected and tested in the City of New York. Most notably, the NYC Department of Buildings will no longer subcontract “Periodic Inspections” to what were previously known as “PVT Agencies”, but rather the performance of these yearly vertical transportation inspections will become the responsibility of the building owner.
The following additions and/or changes to the NYC Building Code, Article 304 - Elevators and Conveying Systems are being adopted:
Category 1 & 5 Inspections
The completed reports, with all applicable signatures, shall be filed within 21 days after the date of the test. Exception: Reports are not required to be submitted to the department for private residence wheelchair lifts and private residence dumbwaiter devices. However, the owner shall maintain an inspection and test log to be available to the department upon request.
All defects as found in such category test report shall be corrected within 90 days after the date of test. An Affirmation of Correction shall be filed within 14 days of the date of correction.
Periodic Inspections
Periodic inspections shall be performed between January 1st and December 31st of each year at a minimum of three months from the date of any Category 1 testing or previous periodic inspection. Initial periodic inspections on new installations must be performed in the calendar year following the final acceptance test. For private residence elevators, the periodic inspection and Category 1 and/or 5 testing may be performed on the same date. Filing of Periodic Inspections in DOB NOW must be completed within fourteen (14) days of the date of Inspection.
All defects as noted in such periodic inspection report must be corrected within 90 days after the date of inspection. The department may grant an extension of 45 days upon submission of an application by the owner demonstrating a practical difficulty in complying within the 90-day timeframe. In no case shall more than two such extensions be granted for a specific defect. An Affirmation of Correction shall be filed within 14 days after the date of correction.