9/4/25 SCCRTC P7a - Measure D Active Transportation Expenditures and Financing Options


Listen Later

9/4/25 SCCRTC P7a - Measure D Active Transportation Expenditures and Financing

Options Summary

Overview

  • Measure D active transportation projects are progressing faster than pay-as-you-go funding allows, necessitating new financing options.
  • Over $150 million in state and federal funds have been leveraged for the coastal rail trail.
  • Recent project completions include segment 7 to the Santa Cruz Wharf and new funding for segment 12.
  • Cost estimates have increased due to material and escalation costs, creating a significant funding gap.
  • Three financing scenarios were presented, with borrowing needs ranging from $12.5 million to $55 million.
  • The commission will revisit recommendations and programming in November.

Project Delivery Pace and Funding Needs for Coastal Rail Trail

  • Provided update on coastal rail trail project funding needs.
  • Measure D active transportation funds enable earlier project delivery but require financing options.
  • Local Measure D funds leveraged over $150 million in state and federal funds for the 32-mile trail.
  • Current discussion is informational; further recommendations expected in November.

Project Updates, Segment Status, and Recent Funding Awards

  • RTC refines project cost estimates with sponsors for next five-year plan update.
  • Coastal Rail Trail aims for full public access; segment 7 completed to Santa Cruz Wharf.
  • SB1 grant awarded for Highway 1 State Park, Freedom Auxiliary Lane, and segment 12; construction funded.
  • Segments 8-9 led by City of Santa Cruz; segments 10-11 led by County of Santa Cruz; segment 5 under construction, completion expected summer 2026.
  • Segments 17-19 received $4.8M pre-construction funding; construction funding not yet identified.

Cost Estimates, Funding Gaps, and Value Engineering

  • Project cost estimates for segments 8 and 11 updated in August 2025.
  • Funding gap increased due to higher material unit costs, escalation, and schedule shifts.
  • Value engineering analysis achieved cost savings, but escalation offset most savings.
  • Secured additional $19.5 million funding; funding gap remains.

Financing Scenarios, Borrowing Models, and Cash Flow Analysis

  • Presented three funding scenarios for Measure D active transportation: current, near-term, long-term.
  • Current scenario based on adopted five-year plan, updated annually and as needed.
  • Near-term needs include environmental mitigation for North Coast Rail Trail Segment 5 and additional design/right-of-way funding for Santa Cruz projects.
  • Long-term commitments may require construction funding for Segments 8–11; commission committed to fully fund Segments 10 and 11 in April 2024.

Summary, Next Steps, and Recommendations for Financing and Project Delivery

  • Three expenditure scenarios evaluated: current (~$40M), near-term (+$10M), long-term (~$80M).
  • Borrowing needs: $12.5M (current), $23M (near-term), $55M (long-term/constrained).
  • All scenarios assume ongoing corridor maintenance; trail maintenance only funded through FY28-29.
  • Maximum borrowing ($55M) insufficient to fully fund segments 8–11A; multi-pronged funding approach required.
  • Next steps: establish legal framework for debt, refine cash flow models, prepare financing plan for commission approval.
...more
View all episodesView all episodes
Download on the App Store

Santa Cruz County Transit and Transportation Agency Meetings - Audio TracksBy Keith Bontrager


More shows like Santa Cruz County Transit and Transportation Agency Meetings - Audio Tracks

View all
The Daily by The New York Times

The Daily

111,821 Listeners