9/5/24 SCCRTC - P6 - Hwy 1 Auxiliary Lane Cost Overrun Presentation


Listen Later

9/5/24 RTC Episode Notes

Presentation by Sarah Christensen of RTC staff, Madeline Jacobson, Caltrans Project Manager, and Tim Cambell, Caltrans deputy district director for construction and project delivery.

The meeting discusses a request for additional funding for the Highway 141st Avenue to Soquel Drive auxiliary lanes and bus-on-shoulder project, which also includes the Chanticleer bicycle and pedestrian overcrossing. Caltrans initially requested $5 million to cover cost overruns in the construction phase, but that amount has been reduced to $4 million. The current recommendation is for the commission to authorize up to $2.5 million to keep the project moving without exceeding current fiscal constraints.

The project, now 60% complete, has faced challenges including design changes, unforeseen conditions, and safety issues, all contributing to increased costs. These include replacing crash cushions, installing pedestrian access routes, and dealing with unsuitable materials. Despite the challenges, the team has made significant progress, including completing the northbound and southbound widening and retaining walls, and the pedestrian overcrossing is nearly finished.

Caltrans proposes a phased funding approach, seeking an additional $2.5 million now and addressing the remaining needs in November as part of the Measure D five-year plan update. The presentation concludes with a focus on project successes and continued collaboration to minimize further risks and ensure completion by spring 2025.

Agenda, Minutes, Handouts and Highlights

https://www.sccrtc.org/meetings/regional-transportation-commission/agendas/

Original video

https://communitytv.org/watch/government-demand/

...more
View all episodesView all episodes
Download on the App Store

Santa Cruz County Transit and Transportation Agency Meetings - Audio TracksBy Keith Bontrager


More shows like Santa Cruz County Transit and Transportation Agency Meetings - Audio Tracks

View all
The Daily by The New York Times

The Daily

111,864 Listeners