#28. Shawn Tabor wants to know whether to estimate project effort in days or story points. Aren't they the same thing?
I've used four ways of estimating effort in my Dynamics 365 projects:
Estimating in days is an absolute estimation method, whereas t-shirts and story points are both relative estimation methods. This means that we compare the relative size of items using a scale, rather than trying to estimate the absolute size.
Story point estimation has several benefits:
Shawn, stop estimating Microsoft Business Applications projects in days and start using story points!
Resources
Shawn Tabor on LinkedIn
CRM Hobbit on Twitter
CRM Hobbit website
CONNECT
🌏 Amazing Apps website
🟦 Customery on LinkedIn
🟦 Neil Benson on LinkedIn
MY ONLINE COURSES
🚀 Agile Foundations for Microsoft Business Apps
🏉 Scrum for Microsoft Business Apps
📐 Estimating Business Apps
Keep experimenting 🧪
-Neil
5
55 ratings
#28. Shawn Tabor wants to know whether to estimate project effort in days or story points. Aren't they the same thing?
I've used four ways of estimating effort in my Dynamics 365 projects:
Estimating in days is an absolute estimation method, whereas t-shirts and story points are both relative estimation methods. This means that we compare the relative size of items using a scale, rather than trying to estimate the absolute size.
Story point estimation has several benefits:
Shawn, stop estimating Microsoft Business Applications projects in days and start using story points!
Resources
Shawn Tabor on LinkedIn
CRM Hobbit on Twitter
CRM Hobbit website
CONNECT
🌏 Amazing Apps website
🟦 Customery on LinkedIn
🟦 Neil Benson on LinkedIn
MY ONLINE COURSES
🚀 Agile Foundations for Microsoft Business Apps
🏉 Scrum for Microsoft Business Apps
📐 Estimating Business Apps
Keep experimenting 🧪
-Neil
77,473 Listeners
30,975 Listeners
32,087 Listeners
224,337 Listeners
182 Listeners
11 Listeners
10 Listeners
6,871 Listeners
20 Listeners
9 Listeners
8,756 Listeners
59 Listeners
4 Listeners
1 Listeners
809 Listeners