In this fifth episode introducing the Royal Institute of British Architects plan of work (RIBA), Ian moves on to Stage 4. In this continuing eight episode series Ian will explain the stages of creation and utilisation of this document. This is a UK centred document, but has international context and use for all construction projects. Ian will cover stage outcomes, employers governance, technical governance and various work streams such as program management, finance, BIM, core design, construction, operational management, statutory processes, procurement and information exchanges.
KEY TAKEAWAYS
BEST MOMENTS
‘In terms of programme management we need to review and oversee the value engineering strategy. In this stage it is very important to make sure that we know what we are doing.'
‘Clearly if this is going to be a traditional procurement the contractor will have his own construction phase program but we still need to do one at this stage to make sure that, overall, it's coming together.'
‘Now we're getting into the nitty gritty and the full detailed technical design. Some of this may be required for building control if that is in your jurisdiction.'
‘Again we need to identify very early on what are the long delay periods or long lead-in for materials so that we can get those ordered as early as possible.'
VALUABLE RESOURCES
https://www.ianjrogers.com/
ABOUT THE HOST
Ian Rogers is an entrepreneur running businesses in the Real Estate, Construction and Facilities Management arena. Ian has over 40 years' industry experience, as he was effectively born into construction with his father having his own building company and Ian spending time working on sites from the age of 11!. As a result Ian has seen the industry from a trades person perspective, as a chartered quantity surveyor working on large commercial projects, as a project manager and then working on structured project finance through PFI/PPP deals. This has given Ian a unique whole life approach to any project by considering the end game at the beginning.
CONTACT METHOD
https://www.ianjrogers.com/
Hosted on Acast. See acast.com/privacy for more information.
By Ian RogersIn this fifth episode introducing the Royal Institute of British Architects plan of work (RIBA), Ian moves on to Stage 4. In this continuing eight episode series Ian will explain the stages of creation and utilisation of this document. This is a UK centred document, but has international context and use for all construction projects. Ian will cover stage outcomes, employers governance, technical governance and various work streams such as program management, finance, BIM, core design, construction, operational management, statutory processes, procurement and information exchanges.
KEY TAKEAWAYS
BEST MOMENTS
‘In terms of programme management we need to review and oversee the value engineering strategy. In this stage it is very important to make sure that we know what we are doing.'
‘Clearly if this is going to be a traditional procurement the contractor will have his own construction phase program but we still need to do one at this stage to make sure that, overall, it's coming together.'
‘Now we're getting into the nitty gritty and the full detailed technical design. Some of this may be required for building control if that is in your jurisdiction.'
‘Again we need to identify very early on what are the long delay periods or long lead-in for materials so that we can get those ordered as early as possible.'
VALUABLE RESOURCES
https://www.ianjrogers.com/
ABOUT THE HOST
Ian Rogers is an entrepreneur running businesses in the Real Estate, Construction and Facilities Management arena. Ian has over 40 years' industry experience, as he was effectively born into construction with his father having his own building company and Ian spending time working on sites from the age of 11!. As a result Ian has seen the industry from a trades person perspective, as a chartered quantity surveyor working on large commercial projects, as a project manager and then working on structured project finance through PFI/PPP deals. This has given Ian a unique whole life approach to any project by considering the end game at the beginning.