The Member Firm performed a geotech study for a housing development and observed grading of the site during the construction of ten buildings. Six years after construction, the developer built two additional units but, because the Member Firm could not provide a representative to monitor the earthwork construction, they recommended another geotech firm. The second geotech firm monitored the placement of at least four feet of fill but without reviewing the Member Firm’s report. Four years after the second phase was completed, settlement problems arose and the developer sued the two geotechs, the civil engineer, and the earthwork constructor. After claims were dropped against the civil engineer and constructor, the geotechs settled with the developer for nearly $1,000,000.
Our Hosts:
Elizabeth is the Principal Geotechnical Engineer at JLT Consultants in Boise, Idaho. Elizabeth has performed and/or assisted with numerous geotechnical investigations throughout Idaho, Oregon, Washington, and Wyoming managing projects, providing geotechnical design, project quality control, cost and value engineering, and evaluating geotechnical constructability issues.
Abi is a Project Consultant at SME experienced in managing a variety of steel, concrete, coatings, and nondestructive testing projects. She specializes in managing projects related to DOT fabrication quality assurance reviews but also supports project managers throughout SME’s various service groups.
Lessons Learned:
Calls-to-action:
Subscribe
This episode was produced by the following GBA Members:
By Geoprofessional Business Association5
3939 ratings
Summary
The Member Firm performed a geotech study for a housing development and observed grading of the site during the construction of ten buildings. Six years after construction, the developer built two additional units but, because the Member Firm could not provide a representative to monitor the earthwork construction, they recommended another geotech firm. The second geotech firm monitored the placement of at least four feet of fill but without reviewing the Member Firm’s report. Four years after the second phase was completed, settlement problems arose and the developer sued the two geotechs, the civil engineer, and the earthwork constructor. After claims were dropped against the civil engineer and constructor, the geotechs settled with the developer for nearly $1,000,000.
Our Hosts:
Elizabeth is the Principal Geotechnical Engineer at JLT Consultants in Boise, Idaho. Elizabeth has performed and/or assisted with numerous geotechnical investigations throughout Idaho, Oregon, Washington, and Wyoming managing projects, providing geotechnical design, project quality control, cost and value engineering, and evaluating geotechnical constructability issues.
Abi is a Project Consultant at SME experienced in managing a variety of steel, concrete, coatings, and nondestructive testing projects. She specializes in managing projects related to DOT fabrication quality assurance reviews but also supports project managers throughout SME’s various service groups.
Lessons Learned:
Calls-to-action:
Subscribe
This episode was produced by the following GBA Members: