Interview with Alex Black, Executive Chairman of Rio2 Ltd.
Our previous interview: https://www.cruxinvestor.com/posts/rio2-tsxrio-fenix-gold-ramp-up-persists-as-condestable-expansion-takes-shape-12207
Recording date: 23rd November 2026
Rio2 Limited is finishing its first year as a dual-asset producer, with the Fenix Gold heap leach mine in Chile and the Condestable underground copper mine in Peru. In a live interview in London, Executive Chairman Alex Black said the company has proven the Fenix concept: a heap leach operation at roughly 5,000 m above sea level, running on trucked water, leaching at 75% recoveries.
The third quarter tested that operation. Two major storms in July and August, followed by further snow and high winds in September, left up to 5 m of snow on site and disrupted access to Fenix South and the leach pad. Fenix produced 8,500 oz of gold at a cash cost of $2,370/oz sold and AISC of $2,615/oz. Rio2 withdrew 2026 gold guidance and will guide for 2027. The company still targets 20,000 tpd and commercial production in the fourth quarter of 2026.
Black said Rio2 is now targeting 20,000 to 25,000 tpd because ore moisture is higher than first measured, so the leach process needs less water. Snowmelt also removed the need for trucked water for a couple of months. Fenix South carries a sulfide profile closer to surface, while Central is opening and North will follow, both expected to behave as standard oxide.
Condestable provided the stability. It produced 9.6M lb of copper, 3,807 oz of gold and 93,854 oz of silver in the third quarter at C1 cash costs of $2.62/lb and AISC of $3.40/lb, in line with guidance of 21,500 to 23,500 t of payable CuEq for January 30 to December 31, 2026. A modified environmental permit approves expansion to 10,000 tpd. Rio2 is targeting an investment decision in the fourth quarter of 2026, construction in 2027 and 2028, and 10,000 tpd in 2029. A surface exploration program, the first in 50 years according to Black, and an ore sorting pilot on about 10 Mt of mineralized waste are under way. Black said a path from 25,000 t to 50,000 t of annual copper would draw larger copper producers.
Third-quarter revenue was $115.4M and adjusted EBITDA was $50.0M. Reported EBITDA was a $1.8M loss after a non-cash $41.1M stream obligation fair value loss. Cash fell to $26.8M at September 30 from $46.4M at the end of 2025, and the November presentation lists total debt of $96.2M.
December is the catalyst window. The Fenix Phase 2 PFS assesses 80,000 tpd and about 300,000 oz/yr, using desalinated water, against roughly 100,000 oz/yr from Phase 1. An amended Condestable technical report will show expansion options. Fenix holds 1.8 Moz of reserves, 4.8 Moz M&I and 1.0 Moz inferred.
Funding is the open question. Black states copper has fallen from $6.50/lb to $5.50/lb while labor, fuel and supplier costs rose, reducing margin available for reinvestment. He named equity, debt (complicated by two streams) and consolidation, possibly with a larger company, as options. He also argued that the junior sector, with too many companies competing for capital, to look at the consolidation picture as essential for the business.
View Rio2 company profile: https://www.cruxinvestor.com/companies/rio2-limited
Sign up for Crux Investor: https://cruxinvestor.com/subscribe
Interview with Farhad Abasov, Director & Chairman of Millenial Potash
Our previous interview: https://www.cruxinvestor.com/posts/millennial-potash-tsxvmlp-us-dfc-backed-giant-gabon-project-targets-2027-construction-10709
Recording date: 23rd November 2026
Millennial Potash Corp. (TSXV: MLP) has signed a non-binding Memorandum of Understanding with Abu Dhabi-based EXG Investments and Gabon's Ministry of Transport, Merchant Marine and Logistics to develop a multipurpose deep-water port near Mayumba, in Nyanga Province. The port is designed for up to 4 Mt per year of marine shipments, with Millennial's Banio Potash Project expected to be a principal user. The site is on the Atlantic coast, roughly 40 km from Banio's identified resources, and is being designed for vessels of 50,000 to 65,000 DWT.
Chair Farhad Abasov told Crux Investor on November 23, 2026 that EXG is a new Abu Dhabi entity staffed largely by the team that built and expanded Abu Dhabi Ports, including that group's chairman. Under the structure he described, EXG and its partners would fund, build, own and operate the port, and charge Millennial handling fees that fall as volumes grow. Gabon's government would provide licensing and support. Millennial holds an option to take equity in the port but prefers to keep its own capex low for now. The release is more conditional on funding. Subject to Banio securing financing and proceeding to construction, the parties intend to explore third-party financing structures for the port. EXG is to fund a port feasibility study, and the parties aim to finalize the agreement in roughly two to three months.
Port capacity sets the scale of the production plan. The 2024 PEA assumed 800,000 tpa. Abasov said the company is targeting a start at that rate within two to three years, then 1.2 Mt, 2.4 Mt and eventually 4 Mt, with the full 4 Mt reserved for Millennial. Other users, such as a regional iron ore project and oil and gas operators, would share costs and could lower handling fees over time.
Geology supports the ramp. Banio hosts 648.2 Mt Measured at 15.7% KCl, 1.8B tonnes Indicated at 15.6% KCl and 3.56B tonnes Inferred at 15.6% KCl. The latest Phase 2 hole logged about 132 m of cumulative carnallitite, one of the thickest intersections to date, and the sequence remains open to the west. Assays are pending. An updated MRE is targeted before year-end and will feed the DFS, which is due in early 2027. The ESIA is targeted for the end of the first quarter of 2027.
Millennial holds about C$20M in cash. The US DFC has released US$1M of a US$3M feasibility commitment and is matching the rest. The company plans no equity raise before construction funding and is targeting mostly non-equity capital for the build. The DFC has signaled interest in construction financing.
On markets, Abasov cited African potash prices of $400 to $425/t, against a global average near $350 to $370/t. He linked the gap to weak distribution networks on the continent. Millennial plans to sell 30% to 40% of its output in the US and keep about half in Africa. It is also running talks with buyers in South America and Asia, and has a hybrid partnership with a major producer under consideration.
The milestones to watch are a final port agreement, the assays and updated MRE, the DFS, the ESIA and a construction financing package.
View Millenial Potah's company profile: https://www.cruxinvestor.com/companies/millennial-potash-corp
Sign up for Crux Investor: https://cruxinvestor.com/subscribe
Interview with Tim Clark, Director & CEO of Fury Gold Mines Ltd.
Our previous interview: https://www.cruxinvestor.com/posts/fury-gold-mines-tsxfury-diversified-assets-recent-pea-toll-milling-optionality-drive-upside-8033
Recording date: 23rd November 2026
Fury Gold Mines (TSX:FURY) is moving its Eau Claire gold project in the Eeyou Istchee James Bay region of Quebec from exploration toward development. Chief Executive Officer Tim Clark, a former investment banker, states a prefeasibility study (PFS) is targeted for around the second quarter of 2027.
Eau Claire and the adjacent Percival zone host measured and indicated resources of 1.16 Moz at 5.64 g/t Au and inferred resources of 723,000 oz at 4.13 g/t. The 2025 preliminary economic assessment (PEA) modeled 75,852 oz a year over an 11-year mine life at US$2,400/oz gold. It tested 3 processing routes. A standalone mine returned an after-tax NPV5% of C$554 million and a 41% IRR on C$217 million of initial capital. A hybrid case with 2 years of toll milling returned C$610 million and 53%. Full toll milling returned C$639 million and 84%, with initial capital of C$117 million.
Toll milling depends on spare capacity nearby. Clark said the Éléonore mill, sold by Newmont to Dhilmar Ltd, is running at about one-third of capacity, and that lakes limit expansion on Dhilmar's own property. He said Dhilmar owns 4% of Fury and Agnico Eagle owns 6% while no processing agreement has been announced.
The PFS will add a year of drilling and a higher gold price. Clark said gold is up about US$1,000/oz since the PEA assumption, which could bring more ounces into the mine plan without lowering the cutoff. Brokers and producers want more than 100,000 oz a year, and Clark said price alone may get Eau Claire there. Metallurgical results, 2 resource updates and the PFS are the next milestones, and Clark said he intends to keep accelerating toward a feasibility study.
Fury's board includes Chair Brian Christie, formerly of Agnico Eagle, and Phillips Baker, former CEO of Hecla Mining. Agnico Eagle has paid for Fury's Nunavut exploration over the past 2 years. Fury holds about $3 million in cash, a $2 million investment and about $20 million in Contango Silver & Gold shares.
At Committee Bay in Nunavut, Fury owns a 300 km greenstone belt. The Three Bluffs deposit holds 524,000 oz indicated at 7.85 g/t and 720,000 oz inferred at 7.64 g/t. November 2026 infill drilling hit the shear zone in all 5 holes, including 3.88 g/t over 17.82 m. Sakami in Quebec holds 825,000 oz inferred at 1.07 g/t. Fury's September 2026 peer table put its EV at C$57/oz on Eau Claire alone, against C$297/oz for Amex and C$228/oz for Radisson. Clark said Fury could sell, spin out or joint venture non-core assets.
Risks remain. The PEA includes inferred resources, toll milling needs a third-party agreement, and construction funding would need partner support or further capital. Clark's own estimate puts Eau Claire's value in production at at least $1.5 billion.
View Fury Gold Mines' company profile: https://www.cruxinvestor.com/companies/fury-gold-mines
Sign up for Crux Investor: https://cruxinvestor.com/subscribe
Interview with Mark Selby, CEO, Canada Nickel
Our previous interview: https://www.cruxinvestor.com/posts/canada-nickel-tsxvcnc-federal-approval-c21-million-funding-for-crawford-project-11497
Recording date: 23rd November 2026
Canada Nickel is moving its Crawford Nickel-Cobalt Sulphide Project in Ontario from approval to financing. Crawford received its federal Decision Statement in July 2026, the first mining approval under Canada's amended Impact Assessment Act since 2019. The company is now targeting a US$2.5B funding package in the first quarter of 2027. Its October 2026 presentation targets construction permits and a final investment decision (FID) in the third quarter of 2027, a 27-month build and first production in the fourth quarter of 2029. CEO Mark Selby described the goal as being in a position to make the FID by the end of 2027.
The nickel market Crawford will sell into is now managed by Indonesia, which controls 67% of global supply. Since 2025 Jakarta has cut mining license terms to 1 year, banned new NPI and HPAL capacity and cut ore quotas. Selby said Indonesian finished nickel output will fall 4% to 5% in 2026, citing the analysts he follows, even though poor communication left the market believing supply had risen. With nickel just under US$16,000/t, he expects the 2027 quota, due before the end of December 2026, to lift prices toward US$19,000/t to US$20,000/t. He expects Indonesia to accept US$20,000/t to US$21,000/t while staying below the US$22,000/t level most restarts need. In that range, he said, a handful of advanced Western projects could proceed.
Crawford's answer to that price range is cost. The 2023 BFS puts life-of-mine net C1 cash cost at US$0.39/lb and AISC at US$1.54/lb, in the first quartile of the global cost curve. FEED lifted after-tax NPV8% to US$2.8B with initial capital of about US$2.0B. Proven and probable reserves contain 3.8 Mt of nickel, second only to Norilsk on the company's chart. Phase I costs are higher, at US$2.67/lb net C1, before the Phase II expansion to 120,000 tpd brings them down to US$0.68/lb.
Financing is the central 2027 task. The plan is 40% equity and 60% debt. It includes about US$600M of ITCs, a US$100M Samsung SDI option, a US$500M EDC letter of intent as Mandated Lead Arranger and a C$500M support letter from a second Canadian agency. SB1 Markets takes an ITC facility of up to US$600M to market in early January 2027. Selby said Canada's new accelerator fund, run through EDC, and the First and Last Mile Fund are now operating and should deploy capital in 2027. He said equity raises would be limited to bridging and to starter positions for large funds, and he would accept extra time to secure non-dilutive capital.
Partners extend the funding pool. The US imports 100% of its nickel, and nickel was in the first-round call of the Defense Industrial Base Consortium. In Europe, carbon costs support the Swiss Steel Group agreement, and Selby said links with Swiss Steel and RWE open European funds. Korea's mineral agency is regaining capacity to invest.
View Canada Nickel's company profile: https://www.cruxinvestor.com/companies/canada-nickel
Sign up for Crux Investor: https://cruxinvestor.com/subscribe
Interview with Alan Carter, President & CEO of Cabral Gold Inc.
Our previous interview: https://www.cruxinvestor.com/posts/cabral-gold-tsxvcbr-commercial-production-weeks-away-resource-update-by-year-end-12688
Recording date: 20th November 2026
Cabral Gold Inc. (TSXV:CBR) released an updated Mineral Resource Estimate (MRE) for its Cuiú Cuiú gold district in Pará State, Brazil. The estimate totals 998,800 ounces (oz) Measured and Indicated (M&I) at 0.73 grams per tonne (g/t) gold from 42.5 million tonnes (Mt), and 2,512,900 oz Inferred at 0.95 g/t from 82.1 Mt. Those totals are 49% and 376% above the previous oxide and hard rock estimates combined. The MRE covers 6 deposits, against 3 in the last hard rock estimate in 2022.
President and Chief Executive Officer Alan Carter said the district resource has grown from about 1.2 million ounces (Moz) to about 3.5 Moz, and that most of the increase came from drilling. The MRE draws on 149,835 meters (m) of drilling, including 604 holes for 46,118 m completed since 2022. The pit shells use US$3,500/oz gold. Carter said the company used a 0.35 g/t cut-off for the hard rock, against 0.26 g/t in 2022, even though gold is about double its level of 4 years ago.
The hard rock resource is 20.8 Mt at 1.09 g/t for 733,200 oz Indicated and 65.4 Mt at 1.09 g/t for 2,302,000 oz Inferred, up 63% and 406% on 2022. Carter said about 86% of the district total is primary material. At a 1.00 g/t cut-off inside the same pits, the hard rock holds 463,200 oz Indicated at 2.32 g/t and 1,452,200 oz Inferred at 2.37 g/t.
The oxide resource stands at 265,600 oz M&I at 0.38 g/t and 210,900 oz Inferred at 0.39 g/t, up 21% and 190% in 16 months. It feeds the Phase 1 heap leach operation, a 3,000 tonne per day plant that poured first gold on September 10, 2026. Cabral is targeting commercial production in the fourth quarter of 2026. Carter said the mine is producing about 3,000 oz a month and that this cash flow makes the company self-funded without further dilution. Cabral reported C$68 million in cash as of November 6, 2026. The July 2025 prefeasibility study (PFS) put first-year all-in sustaining cost at US$1,210/oz at a US$2,500/oz base case.
Carter is targeting a preliminary economic assessment on the Phase 2 hard rock by the end of the third quarter of 2027. The company's timeline places Phase 2 infill drilling in the third and fourth quarters of 2027 and a Phase 2 PFS in the fourth quarter of 2027. All 6 deposits remain open at depth, 4 remain open along strike, and more than 50 peripheral targets are untested or partially tested.
View Cabral Gold's company profile: https://www.cruxinvestor.com/companies/cabral-gold
Sign up for Crux Investor: https://cruxinvestor.com/subscribe
Interview with Peter Akerley, President & CEO of Erdene Resource Development Corp.
Our previous interview: https://www.cruxinvestor.com/posts/erdene-resource-development-tsxerd-bayan-khundii-cash-flow-funds-deep-porphyry-hunt-11741
Recording date: 20th November 2026
Erdene Resource Development is a TSX-listed gold producer whose Bayan Khundii Gold Mine in southwestern Mongolia poured first gold in September 2025. Erdene owns the mine 50:50 with Mongolian Mining Corporation (MMC) through Erdene Mongol LLC, and holds a 5% net smelter return royalty on production above 400,000 ounces (oz). It also owns 100% of the Zuun Mod molybdenum-copper project.
Third-quarter 2026 results showed a mine moving out of ramp-up. Bayan Khundii sold 11,853 oz of gold at a realized US$4,313/oz, generating US$51M in revenue. Cash costs were US$1,742/oz and all-in sustaining cost was US$1,848/oz. Erdene booked C$9.6M of net income for the quarter. Throughput rose 6% and recoveries held at 96%, but feed grade averaged 2.3 grams per tonne (g/t) while the pit was widened to reach the higher-grade Striker and Midfield zones.
Grade is the operating focus. President and Chief Executive Officer Peter Akerley said about 80% of the deposit's value is in 20% of the rock, so selective mining drives head grade. Blasting control, dig-line discipline, more pit geologists and high-precision GPS have moved grade from about 2 g/t toward 3 g/t. Holding 3 g/t through the fourth quarter would put 2026 output in the 50,000 oz range.
The 2027 target is aorund 70,000 oz. The swing factor is Dark Horse, a satellite pit with about 50,000 oz of 7 g/t material at surface, according to Akerley. The mine plan scheduled Dark Horse for 2028. Erdene is working to bring it into mid-2027 and is targeting a timing decision in the first quarter of 2027. Bayan Khundii and Dark Horse together hold about 450,000 oz in the 4.5 g/t range, which Akerley said supports roughly five years at 70,000 oz or more.
Management's stated near-term goal is 100,000 oz a year. A heap leach facility could lift output toward 90,000 oz. It would be fed by Dark Horse material below 7 g/t, the Bayan Khundii low-grade stockpile and the Altan Nar oxide blanket. Column tests on Dark Horse oxide ore show recoveries in the mid-60% range. Construction is targeted for late 2027 or early 2028, subject to joint venture (JV) board approval and final studies. A modest carbon-in-pulp plant expansion of about 20% throughput would take output into the 100,000 oz range.
Debt is falling. The JV repaid US$30M in the third quarter, leaving US$93M (US$53M MMC shareholder loan, US$40M Mongolian bank). It is targeting full repayment in 2027, depending on the gold price. After that, surplus cash goes to the two partners, and Erdene can repatriate its share at about 5% withholding tax. Erdene is already buying back shares under a normal course issuer bid, repurchasing 130,300 shares in the third quarter at C$5.57.
Exploration adds optionality. A 9,000 m program at West Striker follows earlier drilling of 42 m of 7.27 g/t, and Akerley sees 150,000 to 200,000 oz of potential there. Erdene received a mining license at Ulaan, according to Akerley, and is in discussions with a state-owned holder of intervening ground about a second deposit. A 30,000 m Altan Nar program for 2027 awaits December approval.
At Zuun Mod, the preliminary economic assessment shows an after-tax net present value at an 8% discount rate of US$745M and a 16.1% internal rate of return at base-case prices. At spot, those figures are US$2.0B and 27.8%. Upfront capex is US$687M. Erdene is seeking partners, offtake and joint venture discussions are underway.
View Erdene Resource's company profile: https://www.cruxinvestor.com/companies/erdene-resource-development
Sign up for Crux Investor: https://cruxinvestor.com/subscribe
Interview with Rodrigo Roso, Director & CEO of Scotia Metals
Our previous interview: https://www.cruxinvestor.com/posts/scotia-metals-csesmet-nova-scotias-largest-lithium-holder-preps-q3-2026-drill-11333
Recording date: 20th November 2026
Scotia Metals (CSE:SMET) has started drilling at its Acadia Lithium Project in southwestern Nova Scotia. Its board brings together lithium developers from Galaxy Resources and Allkem with capital markets investors behind K92 Mining and Dolly Varden Silver. In early November 2026, the company started a 6-hole scout program of about 1,000 m at the Green Wolf target, about 2 months ahead of the early-2027 date in its original plan. CEO Rodrigo Roso said total drilling will be between 1,000 m and 1,500 m and aims to hit one or more pegmatites.
The target is a ridge at the up-ice end of a dense cluster of spodumene boulders. The boulder train ends at the ridge, glacial flow points to it, and some large upright boulders may be outcrop. A ground radiometric anomaly and a fault follow the same feature. Across Green Wolf, five boulder trains over about 3 km by 1 km have returned historical grades up to 3.40% Li₂O. In September 2026, channel sampling of 38 boulders returned 20 samples above 1.0% Li₂O, with a maximum of 2.72%.
Acadia covers 37,268 ha across 43 licenses. It is the largest lithium land position in Nova Scotia, with more than 80 km of prospective strike. The ground continues north and south of the privately held Brazil Lake deposit, which hosts 10.0 Mt at 1.20% Li₂O (JORC), although Brazil Lake results do not necessarily apply to Scotia's ground. Roso highlighted infrastructure: Shelburne deep-water port is 1 hour away, paved roads reach the drill sites, and power and water are available.
Scotia is targeting a visual update from the core in December, with assays later. If the scout program succeeds, Scotia is targeting a full-property drill program toward the end of the first quarter of 2027.
Scotia signed an option to acquire 100% of the Nordestina Lithium Project in Bahia, Brazil: 9 permits covering 16,566 ha. Mapping found suspected spodumene at 100 locations along a corridor of about 3.3 km by 1.4 km, plus lepidolite and pollucite. A historic artisanal pit exposes all 3 minerals. It remains subject to permit transfer approval in Brazil and CSE acceptance.
Assays from 1,355 samples are expected from late November 2026. Roso said Nordestina should be drill-ready early in 2027 and will be funded separately from Acadia's flow-through money. On funding, Roso said the company holds enough cash to start both programs. Warrant exercise would add about $1.5 million, and a raise is targeted around mid-2027, after results.
The main risks are exploration risk: neither project has a drill result or resource yet. Other risks are option conditions at Nordestina, lithium price volatility, and future dilution. In the short term, the stock depends on the December core update, the assays that follow, and the first Nordestina results.
View Scotia Metals' company profile: https://www.cruxinvestor.com/companies/scotia-metals
Sign up for Crux Investor: https://cruxinvestor.com/subscribe
Interview with Layton Croft, President & CEO of Carolina Rush Corp.
Our previous interview: https://www.cruxinvestor.com/posts/carolina-rush-tsxvrush-first-drill-confirmation-of-copper-gold-porphyry-system-at-brewer-10871
Recording date: 19th November 2026
Carolina Rush Corp. (TSXV:RUSH) has regained 100% ownership of the Brewer gold-copper project in South Carolina after OceanaGold withdrew from an earn-in agreement in September 2026. OceanaGold, whose Haile Gold Mine lies 15 km from Brewer, had committed to an 80/20 structure focused on the deep porphyry target and spent about US$2 million, drilling three deep holes for more than 2,500 m in 2026 CEO Layton Croft said the partner left because the porphyry is early stage and its priorities sit with advanced projects, and he noted that full ownership removes the cap the 80/20 split placed on shareholder upside. Carolina Rush keeps all core and data.
The asset has two value paths. The first is near-surface gold. The 2025 NI 43-101 maiden resource contains about 540,000 oz Au: 192,000 oz indicated at 0.97 g/t, 210,000 oz inferred at 0.74 g/t, and 139,000 oz of inferred backfill at 0.36 g/t, which the company treats as theoretical pending metallurgy. The resource lies within about 175 m of surface. Croft is targeting 1 million oz or more from 10,000 to 15,000 m of drilling, citing repeated intervals of 50 to 100 m near 1 g/t Au in company drilling. The company now has 11 drill targets across 9 areas at Brewer and the adjacent Jefferson project, including Tanyard, B6 and the newly leased A1 prospect. Its best intercept to date is 62.5 m at 8.45 g/t Au and 0.28% Cu.
The second path is a copper-gold porphyry at depth. A step-out hole about 1 km northwest of the former mine pierced the lithocap for the first time and returned 60 m at 681 ppm Cu and 0.24 g/t Au from 1,027 m. Croft said this proved a porphyry exists but has not located the deposit. Dr. Richard Sillitoe's review supports a tilted model, and the next deep test requires a 500 to 600 m step-out onto Jefferson ground. A second deep hole near the mine added 51.15 m at 0.62 g/t Au and 0.22% Cu outside the resource.
Commercial terms improved in August 2026. The estimated US$30 million purchase price for Brewer is no longer due at closing, but after a new mine is fully permitted, payable over 10 years. Croft said the EPA indicated a financial assurance bond of about US$8 million, against about US$100 million at Haile. The option runs to the end of 2030. Croft argued that processing the backfill could also reduce the acid drainage that costs the government about US$1.3 million a year to treat, and he cited a sludge pile assaying about 0.4 g/t Au and 0.7% Cu.
With C$1.5 million cash, the company runs metallurgical, physical property and age-dating work, plans to raise capital when timing improves, and is in partnership talks with larger companies. Croft is the third-largest shareholder and plans to buy more. Key risks are dilution, limited near-term news flow, the conceptual status of the porphyry and the 2030 option deadline.
View Carolina Rush company profile: https://www.cruxinvestor.com/companies/carolina-rush
Sign up for Crux Investor: https://cruxinvestor.com/subscribe
Interview with Gavin Ferrar, CEO of Central Asia Metals PLC
Our previous interview: https://www.cruxinvestor.com/posts/central-asia-metals-lsecaml-proposed-cygnus-acquisition-fills-missing-piece-in-strategy-10672
Recording date: 19th November 2026
Central Asia Metals (AIM, TSX:CAML) has changed from a dividend-paying base metals producer into a self-funded copper growth company. On October 27, 2026, it completed the acquisition of Cygnus Metals and its 100%-owned Chibougamau copper-gold project in Québec, and its shares began trading on the TSX the same day.
The cash engine is Kounrad in Kazakhstan, an SX-EW operation that leaches historical waste dumps. 2026 guidance is 12,000-13,000t of copper cathode, and 9,758t was produced in the first nine months. First-half C1 cash cost was $0.91/lb, up from $0.79/lb because of a stronger tenge and payroll inflation. Kounrad still delivered an 84% EBITDA margin. The asset generates around 75% of group cash. Group adjusted free cash flow was $46.8M in the first half, and management points to roughly $100M a year at current prices for at least another 2-3 years. Sustaining capex is $2-3M a year, with no trucks, crushers or mill.
The upside case at Kounrad is life extension. CEO Gavin Ferrar states the license runs to 2034, but dump recovery has beaten the leach curves from the original test work. Management once expected only around 1,000t/yr of copper after 2034 and now expects multiples of that. A team is defining the extension requirements, and the company is targeting an answer on the process by end-2026. The company estimates 75,400t of recoverable copper at end-2025, enough to support operations to at least 2034.
Chibougamau provides the growth. The current MRE is 6.4Mt M&I at 2.3% Cu, 0.8 g/t Au and 7.6 g/t Ag, plus 8.5Mt Inferred at 2.1% Cu, 1.7 g/t Au and 7.9 g/t Ag. Corner Bay, Cedar Bay, Devlin and Golden Eye would feed the 900ktpa Copper Rand mill in a hub-and-spoke model. The mill has been idle since 2008 and needs heavy refurbishment. The deposits are steeply dipping, extend to around 1,200m depth, and suit the underground methods used at Sasa.
The work programme is fully funded. Three rigs are in place by end-November and a fourth arrives in Q2 2027, for up to 70,000m of drilling through 2027. Ausenco is leading an expanded-scope PEA due mid-2027, and an updated MRE is scheduled for Q3 2027. Management is targeting a firm project view by December 2027, followed by a feasibility study. The land package covers about 18km of strike.
On capital allocation, the company held $97.2M of cash at June 30, 2026, against a $0.9M overdraft. The dividend policy is 30-50% of FCF, and the first-half dividend of 8p was 40%. Cash also funds exploration in Kazakhstan and Canada, Sasa life extension and Chibougamau studies, while building a construction balance. No equity raise is planned unless a value-accretive deal requires it. Sasa is out of its turnaround, with zinc output up 9% and lead up 11% year-to-date.
Learn more: https://www.cruxinvestor.com/companies/central-asia-metals
Sign up for Crux Investor: https://cruxinvestor.com/subscribe
Interview with Rick Winters, CEO of Blossom Gold
Our previous interview: https://www.cruxinvestor.com/posts/made-in-america-blossom-gold-tsxvbgau-visiting-the-rosebud-project-10965
Recording date: 18th November 2026
Blossom Gold (TSX:BGAU) is nine months into work at the Rosebud Project in Pershing County, Nevada. It has drilled about 30,000m and reopened the historic underground, and it has its first metallurgical results. The company is targeting an updated resource estimate in Q1 2027 towards construction in 2029 and production in 2030.
Metallurgy is now driving the flowsheet decision. Preliminary oxide bottle rolls averaged about 73% Au recovery at a 25mm crush. Fresh rock returned around 36%. CEO Rick Winters says the weaker-leaching zones reflect liberation, possibly silica encapsulation, not refractory ore, and that historic data show these zones are discrete. They can therefore be mapped and mine-planned. Winters says even 28% fresh-rock recovery would still return roughly a 100% EBITDA margin per ton mined at current gold prices. The company is still testing whether higher-grade fresh rock earns a mill. KCA leads the heap leach and feasibility work, and McClelland Laboratories handles milling and flotation tests.
Silver is the surprise. Blossom assumed 25% Ag recovery internally, and preliminary tests are averaging above 60%. In situ, Rosebud carries about 10oz Ag per oz Au. Winters estimates a silver credit at these recoveries would cover about one-third of heap leach opex. Silver is not yet in the company’s economics.
Cutoff grades define two flowsheets. On a full-cost basis, the heap leach cutoff is about 0.17 g/t. The current inferred resource at that cutoff is 70.8 Mtons at 0.62 g/t Au and 6.49 g/t Ag, for 1.28 Moz Au and 13.4 Moz Ag. A CIL cutoff of about 0.4 g/t leaves about 45 Mtons at 1.1 g/t. Management describes either route as roughly a $500M project: a ~15 Mtons/yr heap leach or a 7 Mtons/yr CIL plant. Both would produce about 200,000 oz Au a year at current grades. The likely outcome is a large heap leach with a smaller mill.
Drilling for the resource update has grown from 28,000m planned to 46,000m. The search radius was tightened from 220ft to 160ft. The remaining ~12,000m surface and ~8,000m underground program targets at least 70% measured and indicated. Management expects a gross resource on the order of 150 Mtons. Underground rehab is about one-third complete, and Timberline Drilling is targeting infill drilling in the first half of December. A 23,000-ton bulk sample permit and toll-milling talks offer possible early cash flow from plus-3 g/t material.
While water is a main risk, Pershing County’s basin is over-allocated but under-pumped: about 32,000 AF appropriated, about 31,000 AF recharge and only about 11,000 AF pumped. Hycroft controls most mining rights. Blossom is pursuing waivers, a 275 AF purchase, state engineer applications and a possible Hycroft lease, and it expects a two-year process with protests.
On valuation, Winters says peer P/NAV multiples have roughly halved since mid-2026. Blossom trades at about 0.08x NAV, around one-third of its peer average. Catalysts are column results from December, underground infill drilling, the Q1 2027 resource update and the June 2027 Plan of Operations filing.