A critical issue arose during the construction of a groundbreaking direct air capture facility in the US Gulf Coast, risking the project timeline and costing over $500k per day in delays, as a particular coating specification for a vessel proved inadequate for the required environment and temperature ranges, requiring urgent intervention to prevent further setbacks. The urgency was heightened by the need to address the problem during the New Year holidays.
A critical issue arose during the construction of a groundbreaking direct air capture facility in the US Gulf Coast, risking the project timeline and costing over $500k per day in delays, as a particular coating specification for a vessel proved inadequate for the required environment and temperature ranges, requiring urgent intervention to prevent further setbacks. The urgency was heightened by the need to address the problem during the New Year holidays.