  • 09: The EPC Tender - Selecting the right Contractor

    You have your permits, your equipment order, and your grid connection agreement. Now you need someone to actually build the thing. And this is where a lot of projects go wrong — not because of bad technology or poor financing, but because of a contractor selection process that wasn't designed to find the right partner.

    In this episode I cover the full EPC procurement process from both sides of the table — I've run RFP processes as an investor advisor and prepared bids as a contractor representative. That dual perspective changes what I think actually matters here.

    In this episode:

    • Three EPC delivery models — Full EPC, BoP, and Full Wrap with O&M — and what each one means for risk allocation and cost
    • When to issue your RFP and how to structure the process in phases, from RFI to BAFO
    • What a well-constructed tender document actually contains — and where most RFPs fail
    • How many contractors to invite and why a wide-distribution tender produces worse outcomes
    • The site visit — when to organise it and what it tells you about a contractor before you sign anything
    • How to evaluate offers beyond price: track record, team, financial stability, contract posture
    • Red flags on both sides — signals from contractors that something is wrong, and signals from investors that push the best contractors away
    • How the Polish EPC market compares to Germany and the UK, and what that means for your procurement strategy

    The cheapest offer is very often the most expensive project.

    Looking for support with EPC procurement or owner's engineering in Poland? 

    [email protected] 

    www.greenedge-solutions.com

    31 min
  • 08: NIS2 and Cybersecurity in BESS Project

    On the 19th of February 2026, Poland signed the amended Act on the National Cybersecurity System — the Polish implementation of the EU NIS2 Directive. For BESS investors and developers, this is not an IT compliance story. It's a project risk story, which affects you whether your entity is directly regulated or not.

    In this episode: why the energy sector — including battery storage — is explicitly covered by NIS2; how flow-down clauses mean NIS2 reaches your project even if you fall below the direct regulation threshold; what a BESS actually looks like as a cybersecurity target — the three system layers and four realistic attack vectors; what the Polish KSC Act requires from you and on what timeline; what to require from each party in your supply chain — BESS supplier, SCADA integrator, EPC contractor, O&M provider, and aggregator; what cybersecurity testing needs to happen before you sign off on commissioning and who should conduct it; which contract clauses lock this in; and why building security into a fifteen-year asset from day one is a fundamentally different calculation than treating it as an optional extra.

    Questions? Contact: [email protected]

    You can find our more at: www.greenedge-solutions.com

    27 min
  • 07: SGU - Significant Grid User

    In September 2025, for the first time in Poland's history, battery energy storage systems were included on the SGU list — Significant Grid Users. If you are developing or financing a BESS project with a capacity of at least 10 MW and 40 MWh — this episode is for you.

    In this episode: what SGU is and where this obligation comes from; who ends up on the list and how that process works from the investor's and developer's side; what specific technical and operational obligations the SGU status imposes; why there is no compensation for being an SGU and what costs to expect; what grid following, grid forming, and black start mean — and why this decision should be made at the EPC specification stage; whether you can build an off-grid installation and what that means legally for a large BESS project; and why SGU, Poland's grid connection reform, and NIS2 together tell one story — BESS as critical grid infrastructure.

    Questions? Write to: [email protected] 

    More: www.greenedge-solutions.com

    32 min
  • 06: Choosing a BESS Supplier

    You've developed your project, secured the permits, and now you need to buy the system. And this is where a lot of investors — including experienced ones — discover they weren't as prepared as they thought. The BESS supplier market is crowded, opaque, and the differences between offers that look identical on paper can be enormous in practice.

    In this episode, I walk through how the supplier market actually works — cell manufacturers, system integrators, technology developers, and why the distinction matters. I cover the structural shift that's making life harder for smaller investors as top-tier suppliers chase volume, how to evaluate supplier credibility before you commit, what scope of supply you should actually be asking for, how to run a proper RFP and BAFO process, what certifications matter specifically for projects in Poland, and the red flags in offers and term sheets that tell you something is wrong before you've signed anything.

    e-mail: [email protected]

    www.greenedge-solutions.com

    27 min
  • 05: How to Develop a BESS Project in Poland

    Development is where most BESS projects succeed or fail — not on the construction site, but in the eighteen to twenty-four months before a single container arrives. In this episode, I walk you through the full development process for a utility-scale stand-alone project in Poland: site selection, land rights, zoning under the new General Plan regime, environmental decisions, grid connection under the new UC84 rules, building permits, cable route negotiations, and what RTB actually means versus how it's often marketed.

    UC84 changed the economics of early-stage development significantly — higher upfront deposits, new performance securities, shorter validity periods for connection conditions, and mandatory milestones in connection agreements. The Zoning Conditions system is being replaced by General Plans, which municipalities must adopt by end of August 2026. And cable pooling has finally been extended to battery storage, which opens real opportunities for PV retrofit projects.

    This episode also addresses the retroactivity provisions of UC84 and what they mean for anyone evaluating a project acquisition, and why remote development of Polish projects without local presence almost always ends in frustration.

    Questions or project enquiries: [email protected]

    28 min
  • 04 - UC84 - Poland's New Grid Connection Rules

    On April 15, 2026, Poland published UC84 in the Journal of Laws — a comprehensive amendment to the Energy Law that fundamentally changes how grid connections work. The law enters into force on April 29, 2026. After almost a year of legislative work, numerous controversies, and Senate amendments, we have the final text. Time to explain what changed and what it means for BESS and renewable energy investors and developers.

    In this episode: grid connection conditions validity shortened from two years to one and what this means for the development process; three new financial instruments — application fee, doubled advance payment, and an entirely new security deposit — with specific amounts; milestones in connection agreements and the force majeure clauses the Senate introduced at the last moment; two new types of connection agreements — why flexible and configurable agreements are two completely different things and why banks won't finance your full capacity under the latter; cable pooling extended to energy storage — the change the market has been waiting for; and retroactivity — the most controversial element of the law and the specific compromise that ultimately made it into the final text.

    Questions? Contact: [email protected]

    28 min
  • 03: C&I Energy Storage

    C&I storage is not just small cabinet systems — we're talking about containerized solutions of several megawatt-hours that can fundamentally change how your business operates, with payback periods of three to four years for energy-intensive facilities rather than the seven to eight years typical in utility-scale projects.

    This episode covers the Commercial & Industrial segment: energy storage at factories, logistics centers, cold storage facilities, and office buildings. Different economics than stand-alone trading assets, often faster development timelines, and systems that can operate for fifteen to twenty years because they're cycled less aggressively.

    In this episode:

    • C&I scale: from small cabinets to multi-MWh containerized solutions
    • Why C&I can achieve 3-4 year payback compared to 7-8 years for utility-scale
    • Four applications: peak shaving, PV self-consumption, backup, power quality
    • Battery vs diesel generator: response time, maintenance, flexibility
    • How a C&I battery can generate revenue on weekends by providing grid services
    • Sizing fundamentals: why 15-minute consumption data is essential
    • Common calculation mistakes and how to avoid them
    • What we're working on now: early-stage C&I projects, RFQ/RFP support

    This episode is for business owners and facility managers considering storage investments who want to understand whether it makes financial sense before committing capital.

    E-mail: [email protected]

    Website: www.greenedge-solutions.com

    28 min
  • 02: What's Really Inside a BESS Container?

    From the outside, a battery container looks simple — just a box. But what's inside determines whether your investment performs for fifteen years or starts causing problems after two.

    In this episode, we open up the container and examine every critical component: battery cells and chemistry, BMS architecture, power conversion systems, cooling and heating (critical for Polish winters), fire safety, and energy management systems.

    In this episode:

    • Key components inside a container
    • RTE explained: the difference between marketing specs and real-world performance at the point of connection
    • BMS: why the "brain" of your system might limit performance
    • AC-block vs DC container: "plug and play" doesn’t exist
    • Cooling ang heating and what happens when it's - 27°C
    • A real life example: servicing a 5-year-old container with no manufacturer contact, fake SOH readings, and completely unbalanced cells
    • The essential questions to ask suppliers before you commit

    This episode is for anyone evaluating battery storage investments who wants to understand what they're actually buying — beyond the marketing brochures.

    📧 [email protected]

    29 min
  • 01: What is BESS and Why Poland

    The first episode of the English edition of Best in BESS — a podcast for international investors and developers exploring the Polish battery energy storage market.

    Poland has issued grid connection permits for an estimated 70 GWh of energy storage. Over 400 projects applied for the NFOŚiGW subsidy program, and the first utility-scale BESS projects are finally going live in 2026. The opportunity is real — but so are the challenges.

    In this episode:

    • The Polish BESS market in 2026: subsidies, pipeline, and first projects commissioning
    • What is BESS and why do we need energy storage
    • The difference between cell manufacturers and system integrators — and why it matters
    • Stand-alone vs C&I vs hybrid:
    • What's actually inside a battery container — components, hidden costs, and real-world examples
    • Fire safety, cooling challenges, and the gap between marketing specs and reality
    • Why most project delays come from administrative decisions and investor overoptimism
    • Navigating through the Polish grid landscape

    This podcast is for investors, developers, EPC contractors, and energy professionals who want honest, practical insights into the Polish BESS market — including what can go wrong and how to avoid it.

    Looking to enter the Polish market? [email protected]

    Want to know more? www.greenedge-solutions.com

    32 min

About GreenEdge: Best in BESS - ENG

From the publisher's feed

A podcast about battery energy storage and the Polish renewable energy market — no marketing fluff, just real examples and verified information.