A few days after a massive ice storm rocked northern lower Michigan, many thousands remain without power while crews from power companies, the Michigan Department of Transportation (MDOT) and other state and local agencies continue the cleanup and rebuilding process.
Bill Wahl, MDOT North Region associate engineer for operations, who is coordinating department efforts, joins the podcast to provide an update on the recovery.
Also joining is James Lake, MDOT North Region media relations specialist, who assists the Mackinac Bridge Authority (MBA) with communications. He talks about why falling ice necessitated closing the bridge three times in three days, including a record 30-hour period.
Wahl and Lake grew up in the region and neither has seen anything like this ice storm and the resulting destruction. Wahl recounts utility workers who had been on power-restoration projects following hurricanes in the Southeast saying the scenes are as bad or worse as anything they’ve seen.
Wahl says crews from several counties to the south, including Kent, Ottawa, Mason, Missaukee, Muskegon, Roscommon, Iosco and Wexford, were helping to clear roads.
While the Mackinac Bridge re-opened Thursday morning, April 3, after a 30-hour closure, officials will continue to closely monitor conditions for falling ice.
The MBA posted a video message on X from Bridge Director Kim Nowack about the falling ice, along with some photos from the bridge. More videos of falling ice that prompted the current closure were also posted on X.
The bridge has closed roughly 30 times in the past 30 years, and the average closure duration is several hours. More frequently asked questions about falling ice and other topics are available on the MBA website.
By Michigan Department of Transportation4.7
1515 ratings
A few days after a massive ice storm rocked northern lower Michigan, many thousands remain without power while crews from power companies, the Michigan Department of Transportation (MDOT) and other state and local agencies continue the cleanup and rebuilding process.
Bill Wahl, MDOT North Region associate engineer for operations, who is coordinating department efforts, joins the podcast to provide an update on the recovery.
Also joining is James Lake, MDOT North Region media relations specialist, who assists the Mackinac Bridge Authority (MBA) with communications. He talks about why falling ice necessitated closing the bridge three times in three days, including a record 30-hour period.
Wahl and Lake grew up in the region and neither has seen anything like this ice storm and the resulting destruction. Wahl recounts utility workers who had been on power-restoration projects following hurricanes in the Southeast saying the scenes are as bad or worse as anything they’ve seen.
Wahl says crews from several counties to the south, including Kent, Ottawa, Mason, Missaukee, Muskegon, Roscommon, Iosco and Wexford, were helping to clear roads.
While the Mackinac Bridge re-opened Thursday morning, April 3, after a 30-hour closure, officials will continue to closely monitor conditions for falling ice.
The MBA posted a video message on X from Bridge Director Kim Nowack about the falling ice, along with some photos from the bridge. More videos of falling ice that prompted the current closure were also posted on X.
The bridge has closed roughly 30 times in the past 30 years, and the average closure duration is several hours. More frequently asked questions about falling ice and other topics are available on the MBA website.

91,297 Listeners

43,837 Listeners

30,609 Listeners

37,595 Listeners

26,242 Listeners

1,534 Listeners

703 Listeners

153 Listeners

113,121 Listeners

56,944 Listeners

9,556 Listeners

369,956 Listeners

8,121 Listeners

158 Listeners

1,643 Listeners