  • San Jose pauses data center approvals; commission backs new rules

    The City Council paused approvals of data centers and large energy projects until it adopts uniform standards, and the Planning Commission recommended those standards, with the commission rather than the Planning Director hearing permits first. Plus, a council study session on what it costs to live in San Jose.

    City Council, Monday, November 16

    • Council discussion: calls for an affordability focus area, minimum wage review and better measures (01:03:37)
      • The mayor said the council has spent less time on how the city can help people raise their incomes than on costs. (01:04:43)
      • The mayor asked how much more research staff would need to find where city income-boosting efforts give the highest return. (01:05:43)
      • City staff said most of Work2Future's budget is federal money whose allocation shifts from year to year. (01:07:21)
      • The mayor said the data suggest low pay matters more than access to jobs, and asked what levers could raise incomes for people already working. (01:08:31)
      • City staff said continuing to focus on traded-sector industries, where jobs tend to be more durable, will be important. (01:09:43)
      • A guest presenter from Sobrato Philanthropies said Sobrato is studying quality-job indicators beyond wages, such as benefits and time off, and offered to share that work with the city. (01:10:14)
      • The mayor asked the administration to bring a data-driven view of where limited city money and staff time would most raise incomes when the topic returns in the budget process. (01:12:15)
      • The mayor said by his analysis half of Austin's roughly 120,000 new homes over ten years were large multifamily buildings near transit corridors. (01:13:31)
      • The mayor said another quarter of Austin's new homes were single-family sprawl, and ADUs were only about 2.4%. (01:14:32)
      • The planning director said Austin's success came largely from multifamily housing, which is hard to deliver locally mainly because of construction costs. (01:15:25)
      • The planning director said the city has largely caught up on permitting process, so multifamily construction now depends on the economics. (01:15:25)
      • The mayor said the real answer on childcare would be a countywide funding measure like those in San Francisco and Marin, and asked how far city-level efforts alone could go. (01:16:42)
      • City staff said staffing costs are the main challenge in childcare, so easing zoning likely won't bring widespread affordability changes. (01:18:01)
      • Pamela Campos (Councilmember, District 2) argued there is a difference between work that contributes to affordability and making affordability itself a measure of the city's success. (01:20:51)
      • A guest presenter from Sobrato Philanthropies said Sobrato's most important step was adopting the self-sufficiency standard as its main measure of success. (01:22:12)
      • A guest presenter from Sobrato Philanthropies said Sobrato will launch a climate action strategy in 2027 aimed at cutting family energy costs. (01:24:20)
      • A guest presenter from Sobrato Philanthropies said 78% of Sobrato's nonprofit grantees have been directly hit by state or federal funding cuts. (01:28:32)
      • A councilmember cited the Turner Center simulator's San Diego model, which suggested missing-middle reforms could add upwards of 2,000 net new units a year, and asked whether planning staff can use such tools. (01:30:36)
      • The planning director said housing element reporting requirements push the city to find the highest-impact programs, and such tools are being explored. (01:31:50)
      • A councilmember said San Jose's minimum wage, once a regional leader, has fallen behind Mountain View, San Francisco, Sunnyvale and Santa Clara. (01:31:55)
      • A councilmember said a full-time minimum wage worker now earns about $38,000 a year, nearly $5,000 below the 30% area median income level. (01:33:00)
      • A councilmember said it may be time for the council to reconsider how the minimum wage is working, while weighing the effects on small businesses. (01:34:02)
      • Peter Ortiz (Councilmember, District 5) cited an analysis that San Jose families face the highest household bills among the largest U.S. cities, nearly $45,000 a year. (01:35:28)
      • Peter Ortiz (Councilmember, District 5) criticized the council's vote to redirect about $40 million in Measure E money from permanent affordable housing to temporary shelter operations. (01:36:29)
      • Peter Ortiz (Councilmember, District 5) said he sees more people living on District 5 streets despite reported drops in unsheltered homelessness. (01:36:29)
      • Peter Ortiz (Councilmember, District 5) contrasted city efforts to accommodate data center investment with what he called reluctance to act as urgently for struggling residents. (01:37:34)
      • Peter Ortiz (Councilmember, District 5) argued housing production can't be the only strategy because families can't wait years for the market. (01:38:40)
      • Peter Ortiz (Councilmember, District 5) cited Henrico County, Virginia committing $60 million in data center revenue to affordable housing. (01:39:46)
      • Peter Ortiz (Councilmember, District 5) proposed a San Jose Affordability Fund paid for by legally allowed contributions from major developments, including data centers, plus part of the new tax revenue they bring. (01:40:50)
      • Peter Ortiz (Councilmember, District 5) called for affordability to become an official council focus area and said a council vote on it will come. (01:41:50)
      • A councilmember asked what data the city would collect over time to know whether it is making a difference on affordability. (01:43:52)
      • City staff said the best approach would pair the subjective survey with an objective self-sufficiency measure, which exists for the county but not yet for the city. (01:45:45)
      • A guest presenter from Sobrato Philanthropies explained the self-sufficiency standard comes from the University of Washington's Center for Women's Welfare. (01:46:32)
      • A guest presenter from Sobrato Philanthropies described a coming Silicon Valley Financial Well-being Survey with Joint Venture Silicon Valley that will survey about 4,000 residents, including on assets and wealth. (01:48:11)
      • A councilmember suggested building affordability into every department's goals, as the city has done with climate and equity, with measurable outcomes. (01:49:26)
      • A councilmember asked staff to come back with options for how the council could track affordability, and to suggest one or two practices from other cities to test in next year's budget. (01:53:02)
      • A councilmember proposed that every staff recommendation analyze whether a policy makes life more or less expensive for residents. (01:56:52)
      • Pamela Campos (Councilmember, District 2) said removing childcare permitting barriers earlier this year saves prospective operators more than $30,000. (01:58:19)
      • City staff said wealth disparity is growing nationally, and where it is falling the cause is often higher-wage jobs leaving the city. (01:59:29)
      • Pamela Campos (Councilmember, District 2) asked how the city measures whether it is becoming more affordable, including for families already priced out or displaced. (02:01:34)
      • City staff suggested tracking a diversity-of-industries index, already reported in the annual economic forecast, more visibly. (02:02:51)
      • City staff said staff will weigh the council's feedback, including the difference between outputs and outcomes, but had no answer yet. (02:04:33)
      • Pamela Campos (Councilmember, District 2) said she will keep pushing for a dedicated affordability focus area that brings existing efforts together. (02:07:50)
      • The mayor agreed affordability should remain an ongoing priority and at minimum a key lens for the city's work. (02:08:46)
      • A councilmember suggested shifting half of the new-EV rebate money toward childcare support for families. (02:09:04)
      • A councilmember argued for building smaller homes so more people can afford to buy. (02:10:07)
      • A councilmember asked how the city accounts for moderate-income families who can't afford market-rate childcare. (02:11:11)
      • City staff said the city doesn't fund childcare co-ops but supports a family, friend and neighbor caregiver program that graduates about 50 caregivers a year. (02:13:47)
      • City staff said state and county licensing frameworks limit how much the city can do to help childcare facilities expand. (02:15:17)
      • The mayor said making it easier to build housing is currently the city's single most important bet on affordability. (02:17:51)
      • The mayor said the session had him thinking economic development work may need to be expanded or brought further into the focus area work. (02:18:51)
      • Study session introduction: who struggles with affordability in San Jose (00:00:49)
        • The mayor said the session follows the direction the council gave in its June budget message on the high cost of living. (00:00:49)
        • The city manager said the analysis is meant to lay the groundwork for February priority setting, where the council decides how the work shapes its focus areas. (00:02:21)
        • City staff said the city's community survey added a question on affordability in the first quarter of this fiscal year. (00:06:38)
        • City staff reported that survey respondents struggle most with housing, then utilities and healthcare. (00:06:38)
        • City staff said once more quarters of data are in, the survey results can be broken down by ethnicity, income and council district. (00:07:40)
        • A guest presenter from Sobrato Philanthropies presented Sobrato data that a family with two working adults and two children needs at least $166,584 a year to cover basics with no outside help. (00:09:56)
        • A guest presenter from Sobrato Philanthropies said a typical full-time worker in the valley earns about $90,000, barely half of what such a family needs. (00:09:56)
        • A guest presenter from Sobrato Philanthropies said by the self-sufficiency standard, 26% of working families in Santa Clara County cannot meet basic needs. (00:11:00)
        • A guest presenter from Sobrato Philanthropies said the federal poverty measure misses about five of every six struggling families in the county. (00:11:00)
        • A guest presenter from Sobrato Philanthropies said 70% of single mothers fall short, rising to 85% when they have a child age three or younger. (00:12:00)
        • A guest presenter from Sobrato Philanthropies said three council districts stood out on a social vulnerability index, at 75%, 67% and 61%. (00:13:05)
        • A guest presenter from Sobrato Philanthropies said residents of Downtown and East San Jose work at rates similar to or above the national rate, so the problem isn't jobs. (00:14:30)
        • A guest presenter from Sobrato Philanthropies said a single worker without a bachelor's degree in East and Downtown San Jose averages $44,000 a year, against a citywide average of $90,000. (00:14:30)
        • A guest presenter from Sobrato Philanthropies said 37% to 39% of households in Downtown and East San Jose fall short of self-sufficiency. (00:15:36)
        • A guest presenter from Sobrato Philanthropies said Sobrato organizes its investments around two goals, reducing costs and raising incomes. (00:15:36)
        • Improving affordability: housing, utilities, taxes, transportation, childcare and food (00:17:36)
          • The planning director said San Jose grew outward after World War II and had reached close to its current size, about 180 square miles, by around 1990. (00:19:07)
          • The planning director said single-family homes make up about 84% of the city's residential area. (00:20:09)
          • The planning director said the city's cost-of-development studies keep finding more projects that don't pencil out, many of them before land costs are even counted. (00:21:15)
          • The planning director said Austin grew its housing stock by about 10.5% from 2021 to 2024, and its rents fell about 4% while rents rose across Texas and nationally. (00:23:16)
          • The planning director said the main difference from San Jose is that Austin allowed two or three homes on lots that used to allow one, which San Jose is still studying. (00:23:16)
          • The San Jose Clean Energy director said San Jose Clean Energy's 2026 generation rates are the lowest they have ever been, but can't be sustained long term. (00:25:41)
          • The San Jose Clean Energy director said the rates are set below cost to offset a large exit fee for legacy contracts, the power charge indifference adjustment (PCIA). (00:25:41)
          • City staff said about 70% of the municipal water system's operating budget goes to buying wholesale water. (00:27:00)
          • City staff said the water utility has only been passing through wholesale cost increases and has absorbed its own cost increases. (00:28:01)
          • City staff said municipal water bills come to about 1.3% of area median income, at or below the federal and state affordability thresholds. (00:28:01)
          • City staff said garbage and recycling rates rise each year under multi-decade hauler contracts that allow an annual increase tied to an index. (00:29:04)
          • City staff said the storm sewer charge, about $8 a month, hasn't changed in fifteen years, and a deferred maintenance backlog is growing as a result. (00:31:14)
          • The San Jose Clean Energy director said a PCIA transparency bill the city ran passed the state legislature but was vetoed by the governor. (00:32:36)
          • The San Jose Clean Energy director said the San Jose Cares program gives about 82,000 households a 10% discount on top of state discount programs. (00:32:36)
          • City staff said preventive maintenance is one of the main ways the utilities keep rates down over time. (00:34:13)
          • City staff said the sales tax falls hardest on lower-income households, and the rate in San Jose is currently 10%. (00:37:39)
          • City staff cited a 2018 state bill, SB 993, that would have cut the sales tax on goods by 2% and made up the revenue with a new 3% tax on business-to-business services. (00:38:43)
          • City staff said Measure E, the property transfer tax, exempts sales below a threshold that started at $2 million and is now $2.3 million after adjustments. (00:39:44)
          • City staff said owning and running a typical vehicle costs a household about $13,000 a year, against about $990 for a VTA annual pass. (00:41:25)
          • City staff said Move San Jose tracks transportation costs as a share of household income, which averages 9.7% citywide. (00:42:33)
          • City staff said the East San Jose plan, En Movimiento, identifies 29 corridors for improvements. (00:42:33)
          • City staff described a mobility wallet that gives eligible East San Jose residents monthly prepaid funds for transit, electric rideshare and bike share. (00:43:39)
          • City staff said an on-demand electric shuttle for East San Jose, Palante, is expected to launch in about the first quarter of calendar 2027. (00:43:39)
          • The San Jose Clean Energy director said fast-charging hubs coming online in 2027 will pilot low-income and subscription pricing. (00:44:50)
          • The San Jose Clean Energy director said income-qualified customers can get $3,000 off a new EV and a smaller rebate on a used one. (00:44:50)
          • City staff said childcare costs have grown faster than the rest of the economy, which economists call cost disease. (00:46:00)
          • City staff noted the council directed in October that a revision of childcare land use rules be added to the planning department's work plan. (00:48:04)
          • City staff said cities that subsidize childcare directly mostly use voter-approved taxes, such as San Francisco's 2018 commercial rent tax, which funds what staff put at over $200 million in subsidies. (00:49:05)
          • City staff described a state pilot that matches SNAP spending on fruits and vegetables up to $60 a month, with four participating grocery stores in San Jose. (00:51:06)
          • Helping residents grow their incomes (00:51:55)
            • A library deputy director said the SJLearns program gives school districts grants for TK through third-grade reading proficiency. (00:54:13)
            • A library deputy director noted the council approved a digital empowerment and broadband strategy in December of last year, expanding digital skills programs. (00:55:15)
            • City staff said Work2Future's operating budget for 2025-2026 was $14,440,000. (00:56:10)
            • City staff said Work2Future served 2,422 job seekers during the year, 1,602 through federal WIOA funds and 820 through the city-funded San Jose Works program. (00:57:12)
            • City staff said 300 businesses received recruitment, layoff-aversion and other business help. (00:57:12)
            • City staff said the local minimum wage, set by a 2012 voter initiative and raised to $15 by 2019, is adjusted each year for inflation and now sits at $18.45 an hour. (00:58:42)
            • City staff said Work2Future can fund on-the-job and incumbent worker training in partnership with employers. (00:59:38)
            • City staff pointed to small-business loan funds in Vancouver, Washington and San Francisco as a way other cities help residents raise their incomes. (01:00:53)
            • City staff said the study session is meant to set up council deliberation during the budget process. (01:02:38)
            • Documents: Agenda, Agenda (2), Agenda (3)

              City Council, Tuesday, November 17

              • Pause on data center and large energy use approvals, and urgency ordinance (00:31:49)
                • Matt Mahan (Mayor) explained that the item would pause approvals of new data centers and large energy projects until the council takes up the uniform standards on December 8 (00:31:49)
                • Matt Mahan (Mayor) stressed that the item was not a vote on the data center regulations themselves, only on the pause and the urgency ordinance (00:32:52)
                • Matt Mahan (Mayor) credited Pamela Campos (Councilmember, District 2) with repeatedly pressing to make sure no project slipped through before the stricter standards (01:19:31)
                • Matt Mahan (Mayor) said urgency meant the standards would take effect as soon as approved, not that the council was rushing (01:20:36)
                • Matt Mahan (Mayor) said the standards process began in June and has run about six months (01:21:36)
                • Matt Mahan (Mayor) said the city's agreement with PG&E was being misrepresented a bit, and that it was about customer service and timely connections (01:21:36)
                • Matt Mahan (Mayor) said only about 13% of the city's land is for jobs, one of the smallest shares of any big city (01:22:37)
                • Matt Mahan (Mayor) argued that many other industrial uses, such as truck-heavy distribution, pollute more than data centers (01:23:40)
                • Matt Mahan (Mayor) said Monterey Park and others have adopted bans rather than standards, and that other cities are looking to San José for how to regulate (01:24:41)
                • Matt Mahan (Mayor) listed proposed requirements including 100% renewable energy and only tier four EPA-approved backup generators with strict limits on use (01:25:45)
                • Matt Mahan (Mayor) added that the proposed standards require closed-loop and recycled water, prevailing wages, and bar nondisclosure agreements and public subsidies (01:25:45)
                • Matt Mahan (Mayor) said the standards will go to the Planning Commission and that the staff memo was published November 10 (01:26:50)
                • Matt Mahan (Mayor) argued that the pause would push any projects into the new year, which is longer than the 45-day moratorium speakers asked for (01:26:50)
                • Matt Mahan (Mayor) said the proposed standards include new fees on data center builders for affordable housing and for energy efficiency and sustainability (01:27:51)
                • Peter Ortiz (Councilmember, District 5) said including an urgency ordinance was crucial so the new standards take effect immediately once approved (01:30:05)
                • Peter Ortiz (Councilmember, District 5) argued that environmental protections are only part of it and called for strong community benefit agreements (01:31:10)
                • Peter Ortiz (Councilmember, District 5) proposed a San José Affordability Fund paid for by contributions from major developments, including data centers, and part of their new tax revenue (01:32:13)
                • David Cohen (Councilmember, District 4) said developers' commitments were not enough and standards had to be written down for every project to follow (01:33:22)
                • David Cohen (Councilmember, District 4) said no projects were immediately in the pipeline, but the pause makes clear none would be approved before the standards (01:34:25)
                • David Cohen (Councilmember, District 4) argued that, since no project would come forward for approval until the new year, more than 45 days away, the choice between a 45-day moratorium and this action was immaterial (01:34:25)
                • David Cohen (Councilmember, District 4) said the standards will keep evolving before December and that no one could game the system in the coming month (01:35:27)
                • Consent calendar (00:25:10)
                • City Manager's report: storm drains and El Niño preparation (00:26:09)
                  • Jennifer Maguire (City Manager) said the city has more than 35,000 storm drain inlets that move stormwater from streets into creeks and rivers (00:26:18)
                  • Jennifer Maguire (City Manager) said catch basins, trash capture devices and street sweeping keep over 7,600 tons of oils, metals and debris out of the watershed each year (00:26:18)
                  • Jennifer Maguire (City Manager) said clearing drains matters more as the city prepares for a strong El Niño season expected to bring heavy rain and flood risk (00:26:18)
                  • Jennifer Maguire (City Manager) urged residents to call 311 to report weather-related problems (00:27:20)
                  • Jennifer Maguire (City Manager) said more than 200 residents, schools and community groups have signed up to adopt more than 300 storm drains (00:27:20)
                  • Documents: Agenda, Agenda (2), Agenda (3)

                    Planning Commission, Wednesday, November 18

                    • Citywide standards and permit rules for data centers and other large energy projects (00:59:53)
                      • The deputy city manager stressed the item sets standards only and approves no specific project (01:01:15)
                      • The deputy city manager said 10 data centers and one R&D project are currently under city review (01:03:23)
                      • Manira Sandhir (Deputy Director, Planning, Building and Code Enforcement) explained that data centers in industrial zones need a special use permit typically heard at the Director's hearing (01:04:10)
                      • City staff said that because most sites are already zoned for the use, the city can only require things tied to a project's impacts, so the policy is a floor (01:10:37)
                      • City staff reported that about three in ten online feedback responses opposed any new data centers and about half of oral comments raised a moratorium or pause (01:12:41)
                      • The deputy city manager laid out the timeline of City Council on December 8 and a second reading December 15, corrected the effective date to sixty days after second reading, and noted an urgency ordinance on December 8 would make the standards effective immediately (01:13:12)
                      • The deputy city manager said staff proposes sending all appeals, land use and CEQA, to the City Council (01:15:28)
                      • The deputy city manager said the clean energy standard was raised from carbon neutral to 100% renewable electricity (01:15:28)
                      • The deputy city manager said routine generator maintenance and testing would be capped at 25 hours, half the usual 50 (01:16:41)
                      • The deputy city manager described yearly noise monitoring for projects within 1,000 feet of homes and a complaint-triggered report within 30 days (01:16:41)
                      • The deputy city manager said projects must report energy and water use yearly with an audit every five years, and mailed notice would expand from 1,000 to 1,500 feet (01:17:42)
                      • City staff proposed applying the commercial linkage fee to data centers at $5.20 per square foot, about $2.6 million for a 500,000-square-foot building (01:18:46)
                      • City staff described a new one-time energy reliability fee of about $50,000 per megawatt, about $5 million for a 99-megawatt data center, to fund home batteries, solar, heat pumps and similar programs (01:18:46)
                      • City staff said staff recommends reserving 35% of each new fee for the host council district (01:19:48)
                      • City staff estimated a 99-megawatt data center yields about $6 million a year in utility tax and $1 million in property tax for the general fund (01:19:48)
                      • City staff said the city would seek to collect all of the sales and use tax on out-of-state equipment purchases instead of about 40% via the county pool (01:20:53)
                      • The deputy city manager told Pierluigi Oliverio (Commissioner) staff will keep evaluating comments and may modify the policy before the Council hearing (02:58:05)
                      • Daniel Cao (Commissioner) said health impacts, a top public concern, are not well addressed in the report (02:59:33)
                      • City staff said the city lacks standards or expertise to assess health impacts, which falls to the county (03:00:26)
                      • Daniel Cao (Commissioner) called the unknown cumulative health impacts a legitimate concern (03:02:01)
                      • The deputy city manager said San Jose has about 20 data centers and that the first 99-megawatt data center in Santa Clara was approved around 2010 (03:03:07)
                      • The deputy city manager explained that appeals were moved to the City Council because the community wanted elected officials accountable for controversial projects (03:05:07)
                      • Daniel Cao (Commissioner) raised concern that no outreach meeting was specifically held in District 1 (03:06:53)
                      • The deputy city manager said the 20-megawatt threshold reflects typical transmission-level load and an existing agreement with PG&E (03:09:04)
                      • Carlos Rosario (Commissioner) said conflicting information and strong District 2 opposition left him unsure how to vote (03:10:53)
                      • Michael Young (Commissioner; Vice Chair, Planning Commission) commended staff's outreach and questioned claims of insufficient input, suggesting people were unhappy with the result instead (03:13:35)
                      • Michael Young (Commissioner; Vice Chair, Planning Commission) called the standards probably the most stringent for data centers in the country (03:14:43)
                      • The deputy city manager said there is currently no threshold for infrasound and the city would add one if the state creates it (03:17:08)
                      • The deputy city manager said staff did not consult acoustical engineers in writing the standards but will hire on-call noise consultants for monitoring (03:17:55)
                      • The deputy city manager said the most recently approved 99-megawatt closed-loop campus uses about as much water as eight to ten single-family homes a year (03:19:22)
                      • City staff said the city's clean energy program expects enough renewable supply on the market to serve the new load (03:22:10)
                      • Michael Young (Commissioner; Vice Chair, Planning Commission) objected that the Planning Commission was removed from the permitting process and said the Council lacks bandwidth for individual land-use cases (03:22:31)
                      • Michael Young (Commissioner; Vice Chair, Planning Commission) moved to approve the staff recommendation with the Planning Commission, not the Planning Director, as initial decision-maker (03:24:32)
                      • Aimee Escobar (Commissioner) questioned whether input from late town halls, including District 3's on November 14, could realistically be incorporated before December 8 given Thanksgiving (03:25:13)
                      • The deputy city manager said some requests, such as banning backup generators, were rejected because they would effectively ban data centers (03:27:16)
                      • Lawrence Casey (Commissioner) argued yearly noise monitoring is inadequate and called for continuous, publicly posted monitoring at property corners (03:29:57)
                      • The deputy city manager said staff does not need more time and site-specific noise monitoring details belong in each permit, not the policy (03:33:25)
                      • City staff cited the PayPal Park concert series as an example of site-specific noise monitoring set through CEQA (03:35:20)
                      • The deputy city manager said large-load R&D facilities must meet the same standards as data centers (03:36:44)
                      • Dilpreet Bhandal (Commissioner) said the commission should have received its own briefing or study session given 40-plus community meetings (03:39:05)
                      • Dilpreet Bhandal (Commissioner) supported the commission, not the Director, holding the initial hearing, after staff said a conditional use permit was not considered (03:40:20)
                      • The deputy city manager confirmed yearly energy and water reporting with an audit every five years under the building performance ordinance (03:40:58)
                      • Dilpreet Bhandal (Commissioner) urged a shorter audit cycle or at least an initial audit in the first year (03:41:54)
                      • City staff said rates are set at the state level and new state laws and CPUC Rule 30 require data centers to pay their share of grid costs (03:45:14)
                      • The deputy city manager explained the host-district share stays in the district if committed within three years, otherwise becomes available citywide for the same purpose (03:46:10)
                      • Dilpreet Bhandal (Commissioner) recommended keeping the host district's share beyond three years (03:46:50)
                      • A commissioner argued standards hold developers accountable and that fear should not drive decisions (03:48:58)
                      • City staff calculated the host-district share of the energy fee for a 99-megawatt data center at about $1.75 million (03:55:40)
                      • The deputy city manager said 35% was chosen as a little over a third and the Council could pick a different number (03:58:43)
                      • The deputy city manager responded to a suggestion of a radius around each project instead of a whole district by saying it would be too complex to implement (03:59:51)
                      • The chair called the process the quickest lawmaking he had seen and asked how dissent among staff was handled (04:01:21)
                      • The deputy city manager said disagreements are worked through with deference to each department's experts (04:02:38)
                      • The chair contrasted a 20- to 30-year data center lifespan with a three-year district fee reservation (04:05:59)
                      • The deputy city manager said fee law requires funds to be committed within about five years, which drove the three-year window (04:06:44)
                      • The chair said San Jose's Black population fell from 4.7% in 1990 to about 2.7% today and asked who carries the risk and who benefits (04:08:11)
                      • The chair argued equity is missing from the report (04:09:12)
                      • The chair argued a 9 a.m. Director's hearing is less accessible to working residents than the commission's evening meetings (04:14:09)
                      • The chair noted the staff report's stakeholder list includes no Black or other community-of-color organizations (04:16:04)
                      • Someone at the dais said, before the vote on calling the question, that the remarks were veering off the subject on the agenda and could be made after the item (04:22:23)
                      • The chair insisted any community benefits package include the Black community, developed with it beforehand (04:24:58)
                      • Michael Young (Commissioner; Vice Chair, Planning Commission) declined the chair's friendly amendment and suggested an attached memo instead (04:28:18)
                      • Aimee Escobar (Commissioner) asked the attorney what the commission could realistically recommend, noting the request reaches beyond land use (04:30:23)
                      • The chair read the substitute motion's terms, including direct consultation with the Black community and targeted-hire requirements within 120 days (04:31:59)
                      • The attorney advising the commission said state law defines what counts as affordable housing (04:35:00)
                      • A commissioner said he could not support the substitute motion as written (04:40:04)
                      • Pierluigi Oliverio (Commissioner) said the City Council voted unanimously to make data centers part of economic development (04:41:08)
                      • The deputy city manager recalled that data centers contributed about $40 million to Santa Clara's general fund (04:45:28)
                      • Pierluigi Oliverio (Commissioner) argued all revenue should go to the city instead of designated community benefits (04:45:54)
                      • Pierluigi Oliverio (Commissioner) backed the original motion while saying the Council should ultimately decide (04:46:54)
                      • A commissioner said existing labor and apprenticeship rules already require outreach to disadvantaged groups (04:48:35)
                      • City staff agreed staff would explain affordability levels for the commercial linkage fee in the memo to Council (04:52:37)
                      • Daniel Cao (Commissioner) asked to attach the chair's requests as a memo separate from the motion (04:57:07)
                      • City staff said staff will summarize the discussion and attach an exhibit from the chair to the transmittal (04:58:33)
                      • 18 townhomes on long-vacant lot at Emory Street and The Alameda (00:11:14)
                        • City staff described the project as five three-story buildings with 18 townhome-style condos and removal of 13 trees (00:13:18)
                        • City staff noted staff had recommended denial at early consideration because the change conflicts with focused-growth and employment-land policies (00:14:22)
                        • City staff said the amendment on balance advances housing, land-use efficiency and transit goals and allows development of a long-vacant property (00:15:26)
                        • A speaker said, for the applicant, that everyone who attended the July community meeting supported the project (00:20:14)
                        • A speaker argued the city is far behind state housing targets, citing about 2,600 units approved in the last two years (00:24:37)
                        • Carlos Rosario (Commissioner) said, as a member of a local high school's board, that the school struggles to recruit teachers because of San Jose's housing shortage, and said he would vote yes (00:31:01)
                        • 12 townhomes on McKendrie Street parking lots (00:43:55)
                          • City staff said 10% of the units, which equals one unit, would be restricted to moderate-income households under state density bonus law (00:44:57)
                          • City staff said the project requests four waivers covering front, side and rear setbacks and private open space (00:45:59)
                          • City staff noted staff had recommended denial at early consideration over focused-growth and employment-land policies before the Council allowed processing to continue (00:46:57)
                          • A guest presenter said, for the applicant, that extra parking stalls were added in response to neighborhood meetings (00:54:19)
                          • A guest presenter answered a public question by saying the one affordable unit is a three-bedroom townhouse, likely set at 80% AMI with a 55-year deed restriction, deferring to staff on the details (00:57:43)
                          • San Jose Water well replacing a duplex on South 12th Street (00:33:58)
                            • City staff explained the permit would allow demolition of the duplex and construction of a water well and pump (00:35:42)
                            • City staff acknowledged the change conflicts with housing policy H-1.9 because it removes residentially designated land (00:36:43)
                            • Lawrence Casey (Commissioner) asked why the well needs to replace a duplex when the company appears to have plenty of land (00:41:03)
                            • A San Jose Water representative answered that new wells must be spaced from existing ones and the adjoining well site's existing equipment makes this lot cheaper than a new site (00:41:18)
                            • A San Jose Water representative said the company must follow state relocation-assistance and replacement-housing requirements for the duplex (00:42:24)
                            • Documents: Agenda, Agenda (2)

                              This episode was produced with AI from the public recordings of the week's meetings. Links to the sources are in the show notes.

                              Report an error · This episode's page

                              9 min
                            • El Niño emergency declared; council backs changes to Apple's North San Jose deal

                              The San Jose City Council proclaimed a local emergency ahead of El Niño storms. It also gave first approval to an amendment of Apple's North San Jose development agreement, approved a conditional vacation of part of Orchard Parkway, and backed a plan to wind down a struggling affordable housing developer's portfolio.

                              City Council, Tuesday, November 10

                              • El Niño flood preparedness and local emergency proclamation (00:37:31)
                                • The environmental services director warned that much of San Jose's creek system is natural channel without engineered levees and can overflow in heavy or prolonged rain. (00:37:31)
                                • The environmental services director urged all residents to sign up for county emergency alerts, noting you don't have to live by a creek to be flooded. (00:38:31)
                                • The environmental services director explained that the storm drain system is built for a once-in-ten-year rain, so street flooding in bigger storms is expected. (00:39:41)
                                • City staff said the joint plan identifies 59 flood hotspots from past experience, but flooding can happen elsewhere too. (00:44:04)
                                • City staff added that the transportation department monitors 22 more locations. (00:45:04)
                                • City staff described four response levels (preparedness, monitoring, watch, warning) tied to how full the creeks are, with creeks currently under 50% at the lowest level. (00:46:06)
                                • The environmental services director said Upper Penitencia Creek can only carry a two-year storm and has no federal funding for improvements. (00:48:04)
                                • A guest presenter said the second phase of Valley Water's Coyote Creek project will be done by 2028, giving roughly the capacity of the 2017 flood event. (00:49:55)
                                • A guest presenter said the federal Upper Guadalupe River project is years away, with a chief's report around 2031 or 2032, so Valley Water is pursuing interim protection. (00:50:57)
                                • A guest presenter reported about 167 stream maintenance projects this season, about 126 of them vegetation removal and bank stabilization. (00:53:08)
                                • A guest presenter said there are five county sandbag sites, three of them in San Jose, with webcams showing supply. (00:57:07)
                                • A guest presenter reminded residents that flood insurance takes 30 days to take effect, so it must be bought before the rain. (00:58:13)
                                • City staff reported 63 new CERT graduates since July and nearly 100 registered for the December course. (00:59:50)
                                • City staff said the emergency proclamation lets the city acquire and place emergency equipment and resources. (00:59:50)
                                • City staff said staff would return to the council every 60 days on whether to keep or end the local emergency. (01:00:54)
                                • Rosemary Kamei (Councilmember, District 1) asked whether the agencies are seeking permit waivers to clear the worst debris blockages this year. (01:06:39)
                                • A guest presenter said a second governor's proclamation waived many state Fish and Wildlife permits, but state water board permits are still required. (01:07:23)
                                • A guest presenter said San Jose is seeking emergency permits for some of the worst locations along Coyote Creek. (01:08:24)
                                • Rosemary Kamei (Councilmember, District 1) urged a joint push to get the worst sites cleared before the storms, then moved the recommendation. (01:08:55)
                                • A councilmember promoted a Friday walk along the Guadalupe River with Anthony Tordillos (Councilmember, District 3), a Valley Water board member, and an engineer about El Niño preparedness. (01:10:43)
                                • Domingo Candelas (Councilmember, District 8) asked for sandbag sites closer to outlying districts, such as community centers or libraries, after hearing concerns at a mobile home park near Thompson Creek. (01:13:46)
                                • A guest presenter said Valley Water would coordinate with the city on additional or smaller sandbag sites. (01:15:04)
                                • Anthony Tordillos (Councilmember, District 3) praised the Coyote Mudlarks' advocacy and the agencies' efforts with state and regional water boards to streamline debris removal. (01:16:09)
                                • A guest presenter said the Upper Penitencia project runs from I-680 to just past King Road, and Valley Water hopes to use exemptions for sediment removal next year. (01:17:58)
                                • David Cohen (Councilmember, District 4) faulted Valley Water for delaying the long-planned King Road Bridge widening and urged combining it with the creek work. (01:19:43)
                                • The mayor asked that information sessions target neighborhoods nearest the hotspots of greatest concern. (01:20:36)
                                • A guest presenter said Valley Water is hanging about 48,000 door hangers and running a media campaign, including movie and streaming ads. (01:21:26)
                                • The environmental services director said two webinars are planned on Valley Water's flood-ready map. (01:22:28)
                                • The mayor asked how well the agencies can monitor, verify, and alert residents in real time across about 60 hotspots. (01:23:58)
                                • A guest presenter said Valley Water is confident in its monitoring and keeps a staffed 24-hour line for reporting blockages. (01:24:39)
                                • City staff said field crews log conditions with photos on internal dashboards, partly to document the emergency for federal reimbursement. (01:26:31)
                                • City staff described outreach to unhoused people along creeks, including multilingual broadcasts from police vehicles. (01:27:58)
                                • Amending Apple's North San Jose development agreement (01:50:40)
                                  • The vice mayor said she was recusing herself because her husband has a financial interest in Apple stock. (01:50:56)
                                  • City staff said the original agreement dates from March 2016 and runs until March 2031. (01:51:31)
                                  • City staff said PG&E approached Apple to buy land on the site's 1st Street frontage for a substation to power North San Jose's growth. (01:53:41)
                                  • City staff said the amendment removes 9.7 acres for the PG&E sale. (01:54:44)
                                  • City staff said Orchard Parkway would not close right away; closure is tied to actual future development. (01:54:44)
                                  • City staff said Apple would contribute $2.5 million toward a crossing at Trimble where the Guadalupe River Trail underpass floods. (01:55:46)
                                  • City staff said Apple would also build protected bike lanes on Component Drive and give $90,000 for transit priority signals. (01:55:46)
                                  • David Cohen (Councilmember, District 4) said he was initially skeptical of the substation's location but came to see it as the only option for improving power reliability in North San Jose. (02:02:59)
                                  • City staff confirmed that the first building permit triggers many of the conditions, including the Trimble crossing, before the street would close. (02:04:33)
                                  • David Cohen (Councilmember, District 4) said his memo seeks talks with Apple on a bike connection from the Charcot side to the Guadalupe River Trail, with no specific route set yet. (02:06:01)
                                  • City staff said he did not know how the $90,000 transit figure was set. (02:08:27)
                                  • City staff said staff expects Apple to seek a renegotiation and extension of the agreement within a couple of years, a chance to seek more benefits. (02:09:36)
                                  • City staff said the city has very limited control over the substation's design, which goes through the CPUC. (02:11:16)
                                  • A councilmember urged pressing PG&E to soften the substation's 1st Street face with landscaping or other treatment at a major gateway. (02:11:53)
                                  • City staff said it will be a gas-insulated substation housed in buildings, and PG&E has discussed walls with possible art and added landscaping. (02:13:47)
                                  • Rosemary Kamei (Councilmember, District 1) asked why the city should approve vacating the road now if Apple won't close it right away. (02:16:10)
                                  • City staff said the agreement keeps the road open if Apple doesn't build. (02:17:57)
                                  • City staff said the 2005 North San Jose plan called for 16 million square feet of office and R&D, but only one hotel has been built since. (02:17:57)
                                  • Rosemary Kamei (Councilmember, District 1) argued that any mitigation for closing the road, such as bike access, belongs in the development agreement itself, not in side conversations. (02:20:21)
                                  • Conditional vacation of part of Orchard Parkway (02:21:51)
                                    • A councilmember asked whether the vacation could still be acted on if the development agreement expires. (02:25:56)
                                    • City staff said no; a later developer would have to go through a new entitlement process, reopening the street question. (02:26:30)
                                    • Stabilizing First Community Housing's troubled affordable housing portfolio (01:32:41)
                                      • The housing director said the city has invested about $125 million in the portfolio, more than $60 million of it in recent years. (01:33:45)
                                      • The housing director blamed inadequate underwriting and insufficient financial oversight for the portfolio's distress. (01:33:45)
                                      • A housing deputy director said the portfolio has about 20 properties and 1,400 units housing about 4,000 people, and named Curtner and 2nd Street Studios as the most distressed. (01:35:16)
                                      • A housing deputy director said the plan is to wind down the corporation over about 18 months, transferring properties to qualified developers. (01:37:25)
                                      • A housing deputy director said the overall portfolio has negative value and the city may trade debt forgiveness for upfront cash. (01:37:25)
                                      • The housing director said the $1.5 million to the corporation would hire three consultants experienced in disposing of distressed portfolios. (01:38:32)
                                      • The housing director said Curtner Studios has little or no site management and serious roofing problems, which the extra $1.5 million would address. (01:38:32)
                                      • The housing director said the corporation has no staff, so the consultants would do most of the work. (01:40:40)
                                      • The mayor said overly optimistic projections for deeply affordable housing put residents at risk. (01:41:09)
                                      • The mayor backed both group memos, saying his memo stressed strong oversight of how the properties are disposed of. (01:42:11)
                                      • Anthony Tordillos (Councilmember, District 3) said the situation shows why the housing department's stricter underwriting of new projects matters. (01:42:54)
                                      • Anthony Tordillos (Councilmember, District 3) backed the second memo's idea of possible strategic acquisitions if the cost is right, and moved both memos. (01:43:54)
                                      • A councilmember recounted Curtner Studios' decline despite a 2024 city reinvestment and thanked housing, police, and fire for stepping in when management walked off the job. (01:45:16)
                                      • A councilmember said the second memo aims to give housing staff room to consider acquisitions and act quickly when they report back quarterly. (01:46:44)
                                      • The mayor cautioned that city acquisition of these properties is in many cases unlikely to reduce costs. (01:46:58)
                                      • Council referral report: mobile home rent ordinance changes deferred, with a May 11 check-in (00:24:17)
                                        • A councilmember objected to deferring the mobile home rent ordinance amendments again with no timeline for the stakeholder meetings. (00:24:47)
                                        • A councilmember listed the housing department's past year of outreach, including office hours in three languages and meetings at mobile home parks. (00:24:47)
                                        • A councilmember proposed adding to the Rules Committee motion by Pam Foley (Councilmember, District 9; Vice Mayor) a requirement to return to the council no later than May 11. (00:26:41)
                                        • The housing director said the Rules Committee motion set no timetable and gave the housing department only a supporting role, so staff had not planned to return to council. (00:27:23)
                                        • The housing director said staff would not convene meetings but would monitor whether the parties reached agreement and report that in May. (00:29:37)
                                        • A councilmember said he doubted more time would bring the sides together but accepted giving space if the outside parties drive the talks. (00:30:12)
                                        • The mayor clarified the request is at minimum an informational memo by May 11, with anything more substantive up to the administration. (00:30:41)
                                        • Raises and extra leave for council appointees (01:31:13)
                                        • Communications Hill special tax district annexation (01:29:27)
                                          • The city clerk said she needed more time because the ballots were still in the ballot box. (01:31:03)
                                          • The city clerk reported 51 votes in favor and none opposed, clearing the two-thirds threshold. (01:48:58)
                                          • Land use consent: three new city landmarks and four Mills Act contracts (00:35:56)
                                            • A councilmember said most or all of the properties are in his district, voiced support for expanding historic preservation, and moved the land use consent calendar. (00:36:10)
                                            • Documents: Agenda, Agenda (2)

                                              This episode was produced with AI from the public recordings of the week's meetings. Links to the sources are in the show notes.

                                              Report an error · This episode's page

                                              10 min
                                            • Council adopts detention facility moratorium; developer loses its appeal

                                              The City Council adopted a temporary moratorium on new detention facilities. The Planning Commission turned down a developer who wanted permit terms that city staff said would never expire. The council also cleared the way to negotiate a 2028 Olympic torch relay.

                                              City Council, Tuesday, November 3

                                              • Temporary moratorium on detention and custodial facilities (00:44:30)
                                                • A councilmember said the disruption caused by an increased ICE presence reinforces his belief that ICE harms rather than protects the community, and moved to approve (00:47:49)
                                                • A councilmember backed the moratorium as a matter of human dignity and of protecting immigrant communities, saying it is about getting the decision right, not stopping progress (00:48:36)
                                                • The chair praised staff's plan, which includes research, policy development, community engagement and environmental clearance, before new land use rules (00:49:35)
                                                • Torch relay agreement for the 2028 Olympic and Paralympic Games (00:24:53)
                                                  • A councilmember asked where the torch relay opportunity came from (00:25:32)
                                                  • City staff said LA28 started it by reaching out to the mayor's office as it seeks host city commitments across the country (00:25:41)
                                                  • City staff explained that the staff report's two cost tables cover a torch procession and an optional cauldron lighting, which can't happen without the procession (00:26:20)
                                                  • A councilmember asked how staff would protect the general fund if fundraising goals aren't met (00:26:58)
                                                  • City staff said staff would renegotiate terms of the agreement and, if fundraising still fell short, bring an alternative funding proposal to the council (00:27:09)
                                                  • City staff said the biggest cost drivers are the route length, destinations and security, which would be refined during negotiations with LA28 (00:27:54)
                                                  • City staff said the torch is expected to come through town in a June-July timeframe, leaving time to refine costs before then (00:28:55)
                                                  • A councilmember said she supports the item but urged the administration to limit risk to the community given projected budget challenges (00:29:24)
                                                  • Consent calendar (00:33:43)
                                                  • Public member appointments to both retirement boards (00:51:22)
                                                    • The city clerk explained that two incumbents were interviewing only for their own boards, while the rest, including a third incumbent hoping to move to Federated, were open to either board (00:51:34)
                                                    • The city clerk said the council could appoint by motion or by ballot after the interviews (00:51:34)
                                                    • Pam Foley (Councilmember, District 9; Vice Mayor) drawing on her time as council liaison to both boards, asked each applicant what a trustee's fiduciary role means to them (01:00:14)
                                                    • The chair said the late public comment matched the council's action and, with no one asking for it, held no second vote (01:09:21)
                                                    • Retiree representative appointment to the Federated Retirement Board (00:30:04)
                                                      • A councilmember asked why the retiree association forwarded only one candidate when it can refer up to three (00:30:09)
                                                      • The city clerk said the association is allowed to submit up to three names but isn't required to (00:30:43)
                                                      • City staff said the Federated Retirement Board interviewed the one candidate at its October meeting and unanimously recommended the appointment (00:31:03)
                                                      • A councilmember asked what safeguards retirees have for independent oversight (00:31:54)
                                                      • City staff said board members' fiduciary duty requires independent oversight of retirement assets strictly for members (00:32:08)
                                                      • A speaker said, speaking for the retiree association, that it considered several names, including one the city clerk sent it, and chose to forward one (00:32:39)
                                                      • A speaker said the association's board picked the candidate it knew best (00:33:20)
                                                      • Retirement plans' 2025 investment fee reports (00:37:43)
                                                        • City staff said the plans and their health care trusts paid 1.3% of plan assets to external investment managers in 2025 (00:39:42)
                                                        • City staff said internal costs to monitor the managers were six basis points (00:39:42)
                                                        • City staff explained that incentive fees rise when investments perform well, much like profit sharing (00:40:44)
                                                        • City staff said management expenses have come down by about a quarter of a percent over the past decade (00:40:44)
                                                        • City staff said internal monitoring has paid for itself three times over in savings (00:41:47)
                                                        • The chair called it a good sign that management fees are falling while above-market performance drives larger performance fees, as designed (00:43:56)
                                                        • Documents: Agenda, Agenda (legistar.granicus.com)

                                                          Planning Commission, Wednesday, November 4

                                                          • Developer's appeal of its own approval for 264 apartments at 741 South Winchester Boulevard (00:07:22)
                                                            • City staff described the site as a surface parking lot that once held a movie theater, where a seven-story, 264-unit building is proposed (00:08:32)
                                                            • City staff explained that because the project qualifies as a builder's remedy project, the city cannot deny it for being inconsistent with the general plan and zoning (00:10:36)
                                                            • City staff noted that the applicant chose not to hold a community meeting, and that city policy only says one should be held, so staff could not require it (00:12:42)
                                                            • City staff said accepting the applicant's changes to the expiration conditions would produce an entitlement valid forever, and that development permits should not exist in perpetuity (00:14:56)
                                                            • City staff said staff had removed two conditions calling for voluntary contributions to bike lanes and signal improvements but otherwise recommended keeping the public works conditions as approved (00:17:06)
                                                            • City staff said a letter from the applicant team that afternoon insisted its concession request be granted, and that the city considered the request untimely and would respond with findings for denial (00:18:13)
                                                            • The applicant's representative argued for the appellant that SB 330 was meant to set final approval late, and that short entitlement timelines make financing and building projects hard (00:21:20)
                                                            • The applicant's representative argued for the appellant that the state's revised builder's remedy law bars other parts of a city's affordable housing ordinance from applying, so condition 25 must change (00:22:23)
                                                            • The applicant's representative argued for the appellant that the public works condition was copied in late from a memo and that the city had not identified the objective health and safety standards behind it (00:23:24)
                                                            • City staff argued from the city attorney's side that the developer was seeking a permit with no real expiration date and special treatment other applicants don't get (00:25:53)
                                                            • City staff said permits expire so that land isn't banked while waiting for the best time to build, and that state housing laws aim at actual construction (00:26:53)
                                                            • City staff read findings into the record denying the density-bonus concession, saying the applicant gave no evidence of identifiable and actual cost reductions (00:31:03)
                                                            • City staff stated in the findings that state law sets a two-and-a-half-year SB 330 vesting period after final approval and that using a concession to cancel it is contrary to state law (00:35:19)
                                                            • A commissioner noted that the owner has held the land for over fifty years, so its cost basis differs from a new buyer's, then moved to adopt the city attorney's position (00:37:33)
                                                            • A commissioner contrasted the site with the Dome Theater down the street, whose owner could not redevelop after it was deemed historic, calling it another economic advantage for this applicant (00:38:39)
                                                            • A commissioner said the city needs the homes, hoped for common ground, and asked how long the developer would have to start construction under staff's recommendation (00:39:20)
                                                            • City staff answered that the developer gets two years plus two one-year administrative extensions, about four years, and that staff had never denied such an extension (00:40:25)
                                                            • City staff explained the two clocks, permit expiration and SB 330 vesting, and said any later dispute over what final approval means can be litigated then (00:42:00)
                                                            • The applicant's representative said the developer applied three years ago in better conditions and now can't get financing, and that drawings and building permits would take about two years (00:43:39)
                                                            • The applicant's representative said they couldn't name a specific time limit, only that it would have to be long (00:47:39)
                                                            • A commissioner said the two sides were at an impasse and that she could not support an open-ended appeal that ignored the city's needs (00:48:21)
                                                            • City staff said the city's timelines have not prevented housing from being built and that an indefinite timeline sounds unreasonable (00:49:26)
                                                            • City staff said a permit amendment can also restart the clock, and that some projects have stayed entitled for eight years before construction (00:50:31)
                                                            • The applicant's representative said the concern was managing risk rather than maximizing profit, noting that about $5 million would have to be raised for design and engineering documents (00:53:47)
                                                            • The chair asked why the developer expected certainty in a development market that can't provide it (00:55:43)
                                                            • The applicant's representative said the developer was only applying its reading that the new state housing law does not require the permit to expire (00:58:46)
                                                            • The chair said the city was already offering more time than state law requires (00:59:12)
                                                            • City staff clarified before the vote that the findings deny the density-bonus concession, not the project (01:04:20)
                                                            • The chair explained his yes vote, saying a developer who applies under the builder's remedy agrees to time frames that are certain (01:04:57)
                                                            • Report from City Council (01:06:07)
                                                              • City staff reported that the council approved a moratorium on detention centers and assigned citywide planning staff to develop ordinances and standards for future ones (01:06:07)
                                                              • City staff said the council is expected next week to take up the development agreement amendment for the Apple site on Orchard Parkway, plus historic landmark designations and Mills Act contracts including the De Anza Hotel (01:06:07)
                                                              • Consent calendar: October 28 minutes and San Jose Water PFAS treatment plant permit (00:05:55)
                                                              • Upcoming study session and the data center hearing (01:09:36)
                                                                • City staff said the November 18 agenda will include data center policy and ordinance changes and several privately initiated general plan amendments (01:09:36)
                                                                • A commissioner asked whether the November 18 agenda could be arranged so the other business still gets done, assuming the data center item will draw attention (01:10:35)
                                                                • A commissioner asked that the data center presentation include an overview of projects already approved or under way (01:12:03)
                                                                • The chair asked whether available electric capacity will be part of the data center discussion (01:13:05)
                                                                • Documents: Agenda

                                                                  City Council, Thursday, November 5

                                                                  • Remarks marking the Regional Wastewater Facility's 70th anniversary (00:03:16)
                                                                    • City staff described the Regional Wastewater Facility as the last stop for the area's wastewater before it goes into the Bay (00:03:16)
                                                                    • The mayor said that in the 1950s the city's wastewater, including tons of rotting fruit waste from the canneries, went straight into the South San Francisco Bay (00:06:22)
                                                                    • The mayor said the facility opened in November 1956, which began a regional partnership that continues today (00:06:22)
                                                                    • The mayor said the plant serves over 1.5 million people and more than 17,000 businesses across eight South Bay cities (00:07:27)
                                                                    • The mayor said the plant treats an average of 110 million gallons of wastewater a day and that it is over 99% purified by the time it reaches the Bay (00:07:27)
                                                                    • The mayor said nine employees ran the facility in 1956, compared with about 350 operators, technicians, scientists and other staff today (00:07:27)
                                                                    • The mayor said plant staff worked with Stanford University during COVID-19 to pioneer wastewater-based tracking of viral trends as an early warning for public health officials (00:08:28)
                                                                    • The mayor said the facility is carrying out a 30-year, $2.2 billion capital improvement program because infrastructure built in the 1950s cannot meet future demands (00:09:32)
                                                                    • The mayor said the program's goal is to deliver critical projects without passing the bills to the next generation and to keep rates affordable (00:09:32)
                                                                    • A county supervisor said about 200 acres of facility lands are set aside as habitat for the burrowing owl, a California species of special concern (00:14:19)
                                                                    • A county supervisor said a new digested sludge dewatering facility had opened about three weeks earlier, with an odor control system using carbon and ammonia scrubbers (00:15:28)
                                                                    • A county supervisor said the new dewatering project will shrink the plant's operational footprint by about 500 acres, freeing former lagoons and drying beds for other uses (00:15:28)
                                                                    • City staff said the plant delivered about $1.6 billion in capital work over the last ten years, with another $1.5 billion still to come (00:20:12)
                                                                    • City staff announced sold-out public tours on Saturday, November 7 and November 14, with about 200 people expected each day (00:21:15)
                                                                    • City staff said the plant is launching an interactive virtual tour so people can see the plant from home (00:21:15)
                                                                    • Documents: Agenda

                                                                      This episode was produced with AI from the public recordings of the week's meetings. Links to the sources are in the show notes.

                                                                      Report an error · This episode's page

                                                                      10 min
                                                                    • Council renames downtown plaza and reworks loan for foster youth housing

                                                                      The City Council renamed Plaza de César Chávez as Plaza de San José. It also changed how a city loan can be spent so that a supportive housing complex for foster youth doesn't run at a loss. And the Planning Commission backed an Apple deal that frees land for a planned PG&E substation.

                                                                      City Council, Tuesday, October 27

                                                                      • Plaza de César Chávez renamed Plaza de San José (01:46:50)
                                                                        • City staff said staff were responding to Rules Committee direction given in March after troubling details about the park's namesake came to light (01:47:20)
                                                                        • City staff recounted that the former Plaza Park was renamed in 1993 to honor the farmworker leader after his death (01:49:24)
                                                                        • City staff said the ranked-choice survey drew exactly 10,506 respondents (01:52:37)
                                                                        • City staff said 86 percent of responses came from San Jose ZIP codes and 96 percent from within Santa Clara County (01:53:40)
                                                                        • City staff said 432 of the first survey's 610 suggestions met policy criteria and were consolidated into 88 eligible names, the top five going to a ranked survey (01:53:40)
                                                                        • City staff said staff recommend Plaza de San José based on the engagement surveys (01:55:44)
                                                                        • City staff said staff will issue a request for qualifications for a conservancy at year's end and seek a contract in spring 2027 (01:55:44)
                                                                        • City staff said the Parks and Recreation Commission unanimously recommended Plaza del Pueblo de San José on October 7, which staff agreed also conforms (01:56:47)
                                                                        • The mayor said he co-authored the memo starting the renaming process with four councilmembers (02:15:09)
                                                                        • The mayor said the survey turnout shows how much the plaza means to the community (02:17:27)
                                                                        • A councilmember said the council should not dictate the name and the community should lead (02:17:58)
                                                                        • A councilmember said Plaza de San José was the most suggested name by more than two to one (02:19:01)
                                                                        • A councilmember said it drew more first-choice votes than the second- and third-place names combined, then moved the staff recommendation (02:19:01)
                                                                        • Rescue financing for Parkmoor foster-youth housing (02:20:48)
                                                                          • City staff said the developer used only about 4 percent of the city construction loan and later needed the full amount to pay down the senior loan, or it would lose money from day one (02:23:07)
                                                                          • City staff said operating costs came in 8.3 percent above projections (02:24:12)
                                                                          • City staff said Destination Home proposes $950,000 to bridge a cash-flow gap until year fifteen (02:24:12)
                                                                          • Anthony Tordillos (Councilmember, District 3) asked whether construction costs were overestimated and operating costs underestimated (02:26:01)
                                                                          • City staff acknowledged that the department did not catch an error in the sources-and-uses calculation in early 2023 (02:26:27)
                                                                          • Anthony Tordillos (Councilmember, District 3) asked why the city only learned of the problem in May 2026, eight months after construction finished in September 2025 (02:28:02)
                                                                          • City staff explained the developer was leasing up units before converting the loan and submitting a final budget (02:28:20)
                                                                          • City staff said estimated repayments to the city total about $164,000 until year twelve, with no guarantee after that (02:30:53)
                                                                          • City staff said the department has changed underwriting and shifted toward mixed-income projects that cross-subsidize (02:31:13)
                                                                          • The mayor warned that 100 percent supportive or very-low-income projects statewide are under financial strain and some may surface locally (02:32:30)
                                                                          • A councilmember asked why the developer would choose worse loan terms than the city's (02:33:38)
                                                                          • City staff said the city takes a second lien position after the senior lender, depending on whether the county or the city lends more, with its affordability restrictions above all deeds of trust (02:35:35)
                                                                          • A councilmember raised concern that the project is likely undercapitalized for ongoing maintenance (02:37:43)
                                                                          • City staff said the youth hub's services are county-funded through Behavioral Health Services, separate from building operations (02:39:29)
                                                                          • Pam Foley (Councilmember, District 9; Vice Mayor) objected that paying down a private loan was not what the council approved the money for (02:43:21)
                                                                          • City staff said without the change the property would run negative cash flow by early 2027 and could become a zombie building (02:43:49)
                                                                          • City staff said staff have no indication that any other Abode property is in a similar situation (02:45:01)
                                                                          • Pam Foley (Councilmember, District 9; Vice Mayor) said she would support it reluctantly to protect the young residents, while calling the situation distasteful (02:46:38)
                                                                          • City staff said a risk rubric from the auditor's recommendations is being applied to all 208 tax-credit buildings, and it gives no basis to replace Abode (02:47:38)
                                                                          • City staff estimated the city is taking out about 85 percent of the senior loan and promised the final figure later (02:48:51)
                                                                          • Anthony Tordillos (Councilmember, District 3) asked about another city-funded Abode project under construction on Santa Clara Street; staff reported no issues (02:49:07)
                                                                          • Audit of the abandoned-vehicle program (00:41:39)
                                                                            • City staff reported about 10,000 vehicle abatement cases between July 2025 and March 2026, roughly 3,650 from 311 and 6,350 from proactive patrols (00:43:17)
                                                                            • City staff found the program closed 98 percent of cases within 14 days and 80 percent through voluntary compliance, meeting its goals (00:44:18)
                                                                            • City staff found proactive patrols covered on average 57 percent of streets within 14 days, against a goal of every street (00:45:18)
                                                                            • City staff found some program information is not fully translated as the city's language equity policy requires; the report makes eight recommendations (00:47:25)
                                                                            • City staff said the administration accepts all the audit's findings and recommendations, and the joint memo's recommendations too (00:48:41)
                                                                            • A councilmember said a town hall at Seven Trees Community Center shaped the memo (00:52:23)
                                                                            • A councilmember said the memo asks staff to evaluate using license plate data and location history to link repeat reports of the same vehicle, then moved to accept the memo (00:53:25)
                                                                            • A councilmember described resident frustration at being told cases are closed while the car is still there (00:55:09)
                                                                            • City staff said nearly 89 percent of negative surveys involve cases closed without enforcement, which he called an expectations and communication problem (00:56:36)
                                                                            • City staff said the new 311 app goes live in March 2027, with a committee update in April (00:56:36)
                                                                            • A councilmember raised body and auto repair shops that store cars on city streets (00:58:38)
                                                                            • City staff said the audit did not cover repair shops, and that the problem falls to both transportation and code enforcement, which seek compliance first and then cite (00:59:49)
                                                                            • City staff said the audit led the department to start tracking hotspot enforcement, including at body shops (01:01:54)
                                                                            • A councilmember said nearly every neighborhood in his district has at least 10 stagnant vehicles and some reported in June are still there (01:02:57)
                                                                            • A councilmember asked that, until the new app arrives, the city tell people who report that it knows the system isn't working and when it will be fixed (01:08:00)
                                                                            • A councilmember asked why San Jose is the only surveyed city that requires three visits before a tow (01:10:33)
                                                                            • City staff explained that contract staff, who cannot cite or tow, make an extra check visit so city enforcement officers are sent only to vehicles still in violation (01:11:40)
                                                                            • City staff said 7,400 of the 10,000 cases reached a second visit and over 5,000 of those vehicles had moved (01:14:33)
                                                                            • City staff estimated that dropping the third visit would require at least two more enforcement officers plus vehicles (01:15:37)
                                                                            • The mayor said the program meets its timeliness goals yet gets poor satisfaction ratings, a mismatch of expectations (01:17:03)
                                                                            • The mayor said better communication may not be enough and the city may need to change local policy or ask the state for more flexibility (01:18:03)
                                                                            • The mayor floated a neighborhood pilot of monthly street sweeping that requires moving cars, if budget allows next year (01:20:19)
                                                                            • A councilmember noted the state allows towing cars with registration expired six months, but the city waits a year (01:22:01)
                                                                            • City staff said the department cites unregistered vehicles at six months and tows after a year, a practice choice, and has towed over 3,000 vehicles (01:22:16)
                                                                            • Orders of the Day: one labor agreement dropped (00:30:09)
                                                                              • The mayor relayed the administration's recommendation to drop the AMSP portion of item 3.5 based on the supplemental memo (00:30:09)
                                                                              • Three-year contract with MEF (AFSCME Local 101) (01:24:04)
                                                                                • City staff said the agreements include guaranteed 3 percent pensionable raises each year, a 1 percent lump sum, safeguards on artificial intelligence and promotion process improvements (01:25:38)
                                                                                • City staff said AMSP's tentative agreement was not ratified by its members and will go to closed session next week (01:24:30)
                                                                                • The mayor called the agreement fair and said the city has managed tough budgets without layoffs (01:28:13)
                                                                                • A councilmember argued the city cannot serve residents well while leaving its workers behind, and moved approval (01:30:00)
                                                                                • Three-year contracts with engineers (AEA) and managers (CAMP) (01:31:14)
                                                                                • Consent calendar, including winter warming sites (00:31:11)
                                                                                  • A councilmember thanked the Governor's Office of Emergency Services for three additional fire apparatus valued at about $1.06 million and moved the consent calendar (00:34:25)
                                                                                  • A councilmember asked how the city picks overnight warming locations for the winter (00:35:28)
                                                                                  • City staff explained that warming sites are referral-based and rotate among districts each year, and aren't necessarily placed closest to where need is greatest (00:35:58)
                                                                                  • City staff said the city is working to acquire one or two more permanent warming-location sites (00:35:58)
                                                                                  • City staff said social service providers help referred people get transportation to sites, though it is not guaranteed (00:37:01)
                                                                                  • Phased ban on watering nonfunctional turf with drinking water (01:37:46)
                                                                                    • David Cohen (Councilmember, District 4) asked how enforcement is split between the city and the water companies (01:41:01)
                                                                                    • City staff said state law lets cities impose civil penalties of about $1,000 per day per violation, but the city is taking an education-first approach (01:41:36)
                                                                                    • City staff said the proposal has each water retailer enforce in its own service area, as with past water-waste complaints (01:42:37)
                                                                                    • City staff said staff have worked with San Jose Water since July but received its formal letter only the day before, and that Great Oaks Water has not taken part (01:43:23)
                                                                                    • City staff said San Jose Water wants the city to enforce citywide, which staff disagree with, citing Proposition 218 limits and code enforcement capacity (01:44:47)
                                                                                    • City staff said Valley Water, as wholesaler, could also act as an enforcement authority (01:45:49)
                                                                                    • Documents: Agenda, Agenda (legistar.granicus.com)

                                                                                      Planning Commission, Wednesday, October 28

                                                                                      • Amendment to Apple's Orchard Parkway development agreement (01:23:19)
                                                                                        • City staff said the agreement allows 4,150,000 square feet on the site, and about 487,000 square feet has been built in two buildings (01:26:16)
                                                                                        • City staff said the amendment removes 9.7 acres fronting North 1st Street for a sale to PG&E (01:28:19)
                                                                                        • City staff described the conditional vacation of Orchard Parkway between Atmel Way and Component Drive, plus part of Atmel Way (01:28:19)
                                                                                        • City staff said the vacations happen only after Apple files a permit for its next building, improvement plans are approved, and Apple gives notice of intent to close the streets (01:29:21)
                                                                                        • City staff listed Apple's contributions: $2,500,000 for a Trimble Road bike and pedestrian crossing, and Class IV bike lanes on Component Drive (01:29:21)
                                                                                        • City staff added a $90,000 contribution to the Transit Priority Signal Fund, $30,000 for each of three North 1st Street intersections (01:29:21)
                                                                                        • City staff said the commission does not act on the street vacation, which the City Council decides while Public Works processes it (01:30:25)
                                                                                        • City staff said the environmental addendum found no new or more severe significant impacts and no need for new mitigation (01:35:03)
                                                                                        • City staff said staff dropped the General Plan consistency finding from its recommendation (01:35:34)
                                                                                        • The chair disclosed a recent conversation with an Apple representative and said he had read the speakers' letters (01:48:28)
                                                                                        • City staff confirmed the amendment is consistent with the Envision 2040 General Plan and the 2016 agreement (01:50:00)
                                                                                        • Luis Arguello (Commissioner) said he would move approval if the site were in his district (01:50:29)
                                                                                        • A commissioner stressed that the decision concerns land Apple owns, not a data center (01:51:19)
                                                                                        • City staff said a PG&E substation would go through a separate approval and that PG&E is largely exempt from city land-use review (01:53:16)
                                                                                        • City staff confirmed that PG&E is regulated by the California Public Utilities Commission, not the city's land-use process (01:53:42)
                                                                                        • A commissioner framed the question as whether Apple's concessions make up for the streets and public access the city would give up (01:54:02)
                                                                                        • City staff said the action shrinks the development agreement's footprint to keep the site buildable as a campus (01:54:47)
                                                                                        • City staff said staff will bring a data center item to the City Council in December (01:55:52)
                                                                                        • City staff said Orchard Parkway is an easement over land that would revert to the underlying property owner (01:56:54)
                                                                                        • City staff said Apple is not proposing a data center and the site isn't seen as one, and that nearby data centers are unrelated to this action (01:57:56)
                                                                                        • A commissioner moved the staff recommendation, citing Apple's interest in building non-data-center business space in District 4 (01:58:50)
                                                                                        • City staff confirmed that the area along the 1st Street light rail station is suitable for transit-oriented development (02:00:21)
                                                                                        • City staff said a traffic study routes pedestrians around via North 1st Street, and no bike access through Orchard Parkway has been considered (02:01:01)
                                                                                        • City staff advised that the city can't dictate where Apple carves off the parcel or where the substation goes, though it could raise health and safety issues with the CPUC (02:04:50)
                                                                                        • City staff pointed to existing substations near downtown and said the city's influence over major utility projects is limited (02:06:22)
                                                                                        • City staff said Component Drive has no bike lanes now, and Apple would install the protected Class IV lanes in the city's plans (02:08:20)
                                                                                        • City staff said Apple's Trimble crossing improvement is meant to keep the flood-prone section of the Guadalupe River Trail open in winter (02:09:44)
                                                                                        • City staff said the data center raised in public comment has not been approved and is a separate project several blocks away (02:10:43)
                                                                                        • City staff said data center standards coming to the commission in two weeks would include a proposal to send data center appeals straight to the City Council (02:11:28)
                                                                                        • The chair said the commission doesn't review the street closure or the data center, and urged residents to raise those concerns with their councilmember (02:13:01)
                                                                                        • The chair called a substation on that street unattractive and hoped the city would work with PG&E on a better approach (02:13:01)
                                                                                        • Appeal of Valley Recycling's capacity increase at 1611 South 7th Street (00:08:48)
                                                                                          • City staff presented the request: raising the facility's permitted daily capacity from 174.99 tons to 2,451 tons and its hours to 24/7 (00:09:23)
                                                                                          • City staff said code enforcement found no dust violation, and that the 24/7 operation had broken the state LEA permit rather than a city permit, an issue resolved before the director's hearing (00:11:32)
                                                                                          • City staff said the supplemental dust analysis found current operations within state and federal thresholds, but the proposed operation would exceed the PM10 threshold (00:13:46)
                                                                                          • City staff said the analysis recommended a 25-foot perimeter fence and/or lower tipping piles, and a condition keeps the permit from taking effect until a permit adjustment does this (00:13:46)
                                                                                          • The applicant's representative said the applicant supports the staff recommendation and asked the commission to deny the appeal (00:15:14)
                                                                                          • The applicant's representative said piles are limited to 25 feet and the fence will be raised to 25 feet (00:26:02)
                                                                                          • The applicant's representative said the facility cannot take more tonnage until it gets its solid waste facilities permit and air permits, and the fence must go up first (00:26:47)
                                                                                          • The applicant's representative said the facility has never received a violation for odor or dust, only areas of concern on other items (00:27:25)
                                                                                          • City staff said, as the LEA inspector, she has issued no dust or odor violations in three to four years of inspecting the site and can't cite what she doesn't see in person (00:28:27)
                                                                                          • City staff said she issued an area of concern for odor earlier this month after noticing an intermittent earthy odor, and that earlier record-keeping issues have been abated (00:29:33)
                                                                                          • City staff said two nearby construction-demolition sites run differently, and unlike them Valley Recycling operates in the open air with no roof or overhang (00:32:54)
                                                                                          • A commissioner questioned approving an increase before the operator shows a track record at its current capacity, comparing it to a liquor license the commission had held back (00:33:50)
                                                                                          • City staff said the site is surrounded by heavy industrial uses, the only designation that would allow this use, and that conditions were added for that reason (00:34:52)
                                                                                          • Luis Arguello (Commissioner) described dust-suppression equipment used in demolition work and asked whether the operator plans an ongoing dust-suppression system (00:37:05)
                                                                                          • The applicant's representative described a full-time 4,000-gallon water truck that fills about 10 times a day, plus street sweeping four to six times a day (00:38:24)
                                                                                          • The applicant's representative said more than 40 dust complaints have produced no violations from the LEA or the air district (00:38:24)
                                                                                          • City staff clarified that piles will stay the same height, since the operator chose the taller fence over lowering the piles (00:41:03)
                                                                                          • City staff explained that the LEA is state-funded but sits within city code enforcement (00:42:28)
                                                                                          • Michael Young (Commissioner; Vice Chair, Planning Commission) argued that the commission decides only whether the land use is appropriate, with dust and odor left to the LEA and the air district, then moved the staff recommendation (00:43:36)
                                                                                          • The applicant's representative said a bigger, more permanent sprinkler or dust-control system is planned in about six to nine months, though it was not in the original plans (00:46:33)
                                                                                          • The chair questioned how the operator could handle a much larger volume without hazards to neighbors if it can't process its current volume fast enough (00:53:37)
                                                                                          • The applicant's representative said the 2,451-ton cap is a safeguard for large one-time loads such as soil or concrete, and would rarely if ever be reached (00:58:00)
                                                                                          • A commissioner said the vote concerns land use, with air quality handled at other checkpoints, and backed the original motion (01:03:17)
                                                                                          • City staff said the dust study found prevailing winds blow mostly southeast, toward the adjacent 1615 parcel rather than the appellant's site (01:06:19)
                                                                                          • A commissioner argued that heavy industrial areas are where this kind of work belongs, and staff agreed (01:10:42)
                                                                                          • Michael Young (Commissioner; Vice Chair, Planning Commission) confirmed with staff that the facility was originally designed for the requested capacity (01:11:57)
                                                                                          • City staff said environmental review found the project exempt from CEQA as an existing facility (01:12:27)
                                                                                          • Michael Young (Commissioner; Vice Chair, Planning Commission) argued that mitigation measures aren't appropriate since no CEQA approval was needed, and noted the facility predates the complainants (01:13:04)
                                                                                          • City staff described the site's operations plan as enforceable through code enforcement, with watering, sweeping and equipment spray requirements (01:14:15)
                                                                                          • City staff said the operations plan estimates water use rising from 700 to 2,000 gallons a day under the proposal (01:15:20)
                                                                                          • Michael Young (Commissioner; Vice Chair, Planning Commission) pointed out that only two people came to oppose, compared with the dozens problem projects usually draw (01:16:33)
                                                                                          • City staff advised that the substitute motion's maker would need to make findings to deny the permit (01:17:38)
                                                                                          • Michael Young (Commissioner; Vice Chair, Planning Commission) said enforcing dust rules is up to code enforcement and state agencies, not the commission, and opposed the substitute motion (01:19:01)
                                                                                          • The chair withdrew the substitute motion after learning the facility was designed for the requested volume (01:19:21)
                                                                                          • A commissioner said the neighbors knew a recycling center was there when they moved in, and backed the original motion as a land-use vote (01:19:54)
                                                                                          • The chair said he would vote yes because the use is not changing significantly beyond its intended design (01:22:19)
                                                                                          • Good and welfare: council report and 2027 meeting schedule (02:28:19)
                                                                                            • City staff reported that on September 15 the council took up reasonable accommodation code amendments, a planned development permit on Cottle Road, and an appeal of a Builder's Remedy project (02:28:52)
                                                                                            • City staff reported that on September 29 the council heard the Sakura Market permit at 184 South Market, and that staff also brought the citywide planning work plan prioritization and an early consideration of a general plan change and an environmental appeal (02:28:52)
                                                                                            • A commissioner pointed out that the agenda attachment was the 2026 calendar, not 2027 (02:30:15)
                                                                                            • City staff said staff would look into it and bring the schedule back at the next meeting (02:30:31)
                                                                                            • Documents: Agenda

                                                                                              This episode was produced with AI from the public recordings of the week's meetings. Links to the sources are in the show notes.

                                                                                              Report an error · This episode's page

                                                                                              9 min
                                                                                            • Council steers housing study toward transit, accepts police auditor report

                                                                                              The San Jose City Council voted 9-2 to study tiered housing densities, higher near transit, in single-family neighborhoods. It also accepted the police auditor's 2025 report and denied an appeal over a data center in North San Jose.

                                                                                              City Council, Tuesday, October 20

                                                                                              • Citywide planning work plan priorities and missing middle housing direction (02:01:49)
                                                                                                • City staff said the citywide planning team is at about 130 percent of capacity for the coming year (02:04:36)
                                                                                                • City staff said meeting all current timelines would take 3.3 more full-time staff the division does not have (02:04:36)
                                                                                                • City staff said the legislature considered 1,800 bills in 2026, 300 of them on planning and land use, after more than 450 such bills in seven years (02:05:36)
                                                                                                • City staff said the next housing element is due in January 2031 and work must begin by January 2028 at the latest (02:12:02)
                                                                                                • City staff used the ADU condominium ordinance as an example, saying even an accelerated, clearly directed change took about six months (02:16:15)
                                                                                                • City staff said the next budget's planning fee update would aim to add at least two positions (02:17:20)
                                                                                                • City staff warned that adding geography to a graduated density approach requires more analysis and complexity (02:19:23)
                                                                                                • City staff said a March return with citywide outreach is unrealistic (02:20:29)
                                                                                                • City staff warned that excluding high-opportunity areas, as the second memo proposes, risks the state housing department rejecting the program (02:20:29)
                                                                                                • The chair said 90 percent of planning capacity goes to responding to state mandates (02:52:48)
                                                                                                • The chair said the childcare work is not new city funding but removing barriers to opening and running childcare centers (02:53:55)
                                                                                                • The chair described the group memo's intent as tiered density, higher closer to high-frequency transit (02:56:11)
                                                                                                • The chair said council members are seeking a meeting with the state housing department to test what it actually requires (02:57:16)
                                                                                                • A councilmember stressed that the council is approving an analysis of density, not any density (02:58:41)
                                                                                                • City staff said reaching all 10 council districts for outreach in about a month and a half is unlikely (03:03:11)
                                                                                                • A councilmember moved the group memo, changing the return date from end of March to as soon as possible (03:06:16)
                                                                                                • A councilmember added consideration of current densities for sites in moderate to severe fire hazard zones, restating August direction (03:07:18)
                                                                                                • A councilmember explained she did not include the second memo because she opposes carving high-resource areas out of possible upzoning (03:07:18)
                                                                                                • A councilmember objected that smoke shop zoning work, directed by the council in May 2024, was deferred again in the staff-preferred option (03:10:09)
                                                                                                • A councilmember argued East San Jose neighborhoods with more smoke shops and liquor stores also see disproportionate rates of cancer, diabetes and high blood pressure (03:13:02)
                                                                                                • The chair said the council could choose in the next budget to fund more planners to speed up the backlog (03:14:02)
                                                                                                • A councilmember said the department had previously told the council it did not need more planners, and urged staff to pursue outside grants (03:16:10)
                                                                                                • The chair said he recently helped bring in $750,000 from Bloomberg to speed multifamily permitting (03:17:19)
                                                                                                • George Casey (Councilmember, District 10) argued that if transit access justifies tiers, areas far from transit should stay at current density (03:17:52)
                                                                                                • George Casey (Councilmember, District 10) urged first absorbing new state missing middle laws before upzoning, saying upzoning cannot be reversed (03:20:07)
                                                                                                • Rosemary Kamei (Councilmember, District 1) said the current workload is not sustainable (03:22:05)
                                                                                                • City staff said the tiered analysis would force deferral of other housing element work, including updates to the public outreach policy (03:24:59)
                                                                                                • Rosemary Kamei (Councilmember, District 1) opposed the substitute, saying excluding areas would push density onto other districts (03:28:16)
                                                                                                • A councilmember thanked colleagues for elevating the childcare policy work (03:29:45)
                                                                                                • Anthony Tordillos (Councilmember, District 3) opposed the substitute as adding risk with the state and being unfair to other districts (03:31:34)
                                                                                                • Anthony Tordillos (Councilmember, District 3) noted state law (SB 9) already allows four units on any single-family parcel (03:33:40)
                                                                                                • Domingo Candelas (Councilmember, District 8) said his memo does not oppose the missing middle program but asks for judgment based on neighborhood conditions (03:34:34)
                                                                                                • Michael Mulcahy (Councilmember, District 6) asked whether dropping the 32-units-per-acre study would free up capacity (03:36:13)
                                                                                                • City staff said that before going that way, staff would want an early read from the state housing department (03:37:55)
                                                                                                • A councilmember proposed directing the city attorney to prepare a local control protection strategy on charter authority and state preemption limits (03:39:41)
                                                                                                • The chair suggested the city's intergovernmental relations team begin with research instead (03:41:49)
                                                                                                • City staff said the administration could give an update on the local control work in January, as part of the 2027 legislative program (03:43:56)
                                                                                                • A councilmember said she would vote against the substitute over fairness (03:46:28)
                                                                                                • The chair said he would not back the substitute if it meant Districts 8 and 10 were removed from consideration (03:50:16)
                                                                                                • City staff said transit access usually means within a half mile, so defining limited access beyond that is arbitrary (03:51:13)
                                                                                                • City staff proposed seeking written feedback from the state housing department before investing heavily in the analysis (03:53:06)
                                                                                                • The chair said the community has been told a final vote on the approach is expected by December next year (03:56:03)
                                                                                                • A councilmember cautioned that a new state administration could change the state housing department's leadership and philosophy (03:56:40)
                                                                                                • Anthony Tordillos (Councilmember, District 3) argued removing high-resource neighborhoods would push development into lower-resource areas (03:57:41)
                                                                                                • 2025 Independent Police Auditor year-end report and police response (01:02:17)
                                                                                                  • The police auditor said the office audited 330 internal affairs investigations in 2025, its most ever (01:06:25)
                                                                                                  • The police auditor said 102 of the 942 allegations closed during the year were sustained (01:06:25)
                                                                                                  • The police auditor reported procedural complaints up 58 percent, courtesy complaints up 33 percent and bias-based policing allegations up 40 percent, while cautioning that allegations are not findings of misconduct (01:07:29)
                                                                                                  • The police auditor said the department received 499 complaints in 2025, about 65 percent of them from members of the public (01:08:29)
                                                                                                  • The police auditor said the office agreed with department findings on first review in 290 cases, agreed after more investigation in 28, closed 11 with concerns and disagreed in one (01:10:54)
                                                                                                  • The police auditor reported 20 critical incidents in 2025, three of them officer-involved shootings, and use of force incidents up about 5 percent (01:14:02)
                                                                                                  • The police auditor recommended restricting license plate reader data to approved department systems with security and accountability controls (01:15:09)
                                                                                                  • The police auditor recommended the department give the auditor's office shooting and serious-injury investigative reports within 30 days of completion, with full evidence (01:17:22)
                                                                                                  • The police auditor summarized that the office reviewed 330 investigations, a record (01:19:28)
                                                                                                  • City staff said the department agrees with all 12 recommendations, either almost completely or in part (01:20:57)
                                                                                                  • City staff said a departmental order already bars employees from accessing sensitive law enforcement databases on personal devices (01:20:57)
                                                                                                  • City staff partly agreed on profanity, saying it is already forbidden and disciplined and that all four cases the auditor cited ended in sustained discipline (01:22:00)
                                                                                                  • City staff said implementation of the recommendations should be finished by February 2027 (01:26:20)
                                                                                                  • The chair said the officer in the license plate data misuse case immediately lost his job (01:43:12)
                                                                                                  • The chair listed council actions on license plate data: deleting it every 30 days, restricting access, and adding randomized audits of queries (01:43:12)
                                                                                                  • The chair said he is working with state legislators on a bill to make misuse of license plate data a criminal offense, after the district attorney found current law did not allow charges (01:44:13)
                                                                                                  • The chair said he will bring forward a nominee for the next permanent Independent Police Auditor later this year (01:45:14)
                                                                                                  • A councilmember praised the interim auditor's steady leadership during the transition and moved the staff recommendation (01:46:54)
                                                                                                  • City staff told Rosemary Kamei (Councilmember, District 1) the duty manual is updated constantly rather than on a schedule (01:50:17)
                                                                                                  • The police auditor said a dedicated community outreach position would help the office do more outreach (01:53:02)
                                                                                                  • A councilmember suggested the auditor's office report on open recommendations to the Rules Committee, as the City Auditor does, and said he would pursue it (01:53:36)
                                                                                                  • Anthony Tordillos (Councilmember, District 3) said his understanding is that Mountain View's data exposure came from that city's own system setup, which the police department has said does not apply here (01:54:34)
                                                                                                  • City staff said that when police damage property, the department usually tells people how to file a claim with the city, and the city decides whether to pay (01:56:59)
                                                                                                  • The police auditor said the notice card officers leave after property damage does not explain how to file a claim, and filing deadlines can pass (01:58:31)
                                                                                                  • A councilmember raised the case of businesses facing high insurance deductibles and legal costs after police damage their property (02:00:25)
                                                                                                  • City staff offered to work with the City Manager's Office on policy options for property damaged by police through no fault of the owner (02:01:08)
                                                                                                  • Appeal of environmental exemption for data center use at 300 Holger Way (05:04:11)
                                                                                                    • City staff described the permit as allowing a data center use up to 20 megawatts inside an existing R&D building (05:04:48)
                                                                                                    • City staff said the permit includes no exterior equipment, including no backup generators (05:05:49)
                                                                                                    • City staff said the San Jose Municipal Water System confirmed sufficient water supply for the use (05:10:57)
                                                                                                    • City staff said any expansion with new exterior equipment would require a new permit, air district permits and new environmental review (05:13:07)
                                                                                                    • An appellant representative argued for the appellant that a diesel generator applied for at the air district would emit six times the daily NOx significance threshold (05:15:59)
                                                                                                    • An appellant representative argued the city is piecemealing approvals in violation of CEQA instead of analyzing the whole project (05:17:01)
                                                                                                    • An applicant representative said for the applicant that the building is an entirely existing facility (05:19:56)
                                                                                                    • An applicant representative said all work on the building was done by a union signatory contractor (05:22:01)
                                                                                                    • An applicant representative said for the property owner that NVIDIA signed a ten-year lease about two years ago and has spent over $100 million remodeling (05:23:29)
                                                                                                    • A councilmember criticized the city code's data center definition as so broad it covers any building that houses computers (05:35:04)
                                                                                                    • City staff said data center standards coming in December will update the base definition (05:36:09)
                                                                                                    • City staff said the permit would expire if the use does not begin within two years (05:37:57)
                                                                                                    • An applicant representative declined to commit to letting the permit lapse, noting it can be extended two more years (05:40:43)
                                                                                                    • An applicant representative said the building has 8.5 megawatts of service now and future power needs are unknown (05:42:50)
                                                                                                    • A councilmember said there were no grounds for the CEQA appeal, urged fixing the definition so this does not recur, and moved staff's recommendation (05:44:58)
                                                                                                    • Invocation and ceremonial recognitions (00:01:12)
                                                                                                      • Pam Foley (Councilmember, District 9; Vice Mayor) presented the disability employment proclamation and honored a local nonprofit cafe that builds job pathways for neurodivergent adults (00:11:06)
                                                                                                      • A councilmember honored a 102-year-old resident who has lived in San Jose since the early 1950s and supported the World War II effort (00:15:46)
                                                                                                      • A councilmember said two federal grants were secured with the parks department to restore the Chinese cultural garden at Overfelt Gardens Park (00:21:39)
                                                                                                      • A councilmember recognized three organizations for partnerships with the parks department, including camp scholarships and Guadalupe River trail cleanup (00:26:52)
                                                                                                      • 2025-2026 City Manager's Annual Report and budget adjustments (00:37:26)
                                                                                                        • City staff said the general fund ended the year with an extremely small surplus and most other funds ended at or above estimates (00:39:48)
                                                                                                        • City staff said year-over-year employment growth of 1.3 percent, the main driver of revenue, points to low revenue growth ahead (00:39:48)
                                                                                                        • City staff said revenue and spending left $16.6 million, of which $8.1 million must carry forward to continue existing projects (00:41:54)
                                                                                                        • City staff recommended restoring the remaining $7.1 million to the budget stabilization reserve, as council policy calls for (00:42:55)
                                                                                                        • City staff proposed $1 million to design and bid a ventilation rehab at the police gun range, which he estimated as a $3 to $5 million project (00:45:00)
                                                                                                        • City staff proposed moving the police family violence unit out of leased space into the South San Jose substation, at about $300,000 one-time cost and roughly $300,000 in ongoing lease savings (00:46:09)
                                                                                                        • City staff said the budget stabilization reserve should be about $100 million but will be about $30 million, down from $61 million a couple of years ago (00:48:13)
                                                                                                        • City staff reported that Measure E property transfer tax revenue rose to almost $80 million, driven by 12 property sales over $100 million compared with five the year before (00:49:17)
                                                                                                        • Rosemary Kamei (Councilmember, District 1) welcomed adding money to the stabilization reserve, which she called very low, and moved approval (00:52:57)
                                                                                                        • A councilmember praised the budget office for keeping the general fund variance within 0.2 percent (00:53:44)
                                                                                                        • Appeals of 276-unit housing project at 470 West San Carlos Street (04:20:24)
                                                                                                          • City staff described the project as 276 units with 217 parking spaces (04:20:50)
                                                                                                          • City staff said the project includes 14 very low income units, which she described as 50 to 80 percent of area median income (04:21:51)
                                                                                                          • City staff said staff first questioned whether the site was on a hazardous materials list but concluded it is not and qualifies for the AB 130 exemption (04:23:33)
                                                                                                          • City staff summarized appellants' claims that the five density bonus waivers are unjustified (04:24:58)
                                                                                                          • City staff read into the record a new condition requiring height verification before a building permit, with AB 130 labor standards applying if the building exceeds 85 feet (04:29:27)
                                                                                                          • A councilmember disclosed that a member of her staff had an ex parte communication with the appellant (04:30:49)
                                                                                                          • An appellant representative argued for the adjoining commercial property's owner, an appellant, that the new building would sit directly against its building with no separation (04:31:17)
                                                                                                          • An appellant representative asked the council to require physical separation starting at six feet before fire issues are deferred (04:32:18)
                                                                                                          • An appellant representative argued for the neighborhood appellant that the council's June purchase of the Knox Goodrich building from the same developer creates a conflict (04:36:20)
                                                                                                          • An appellant representative argued that if the affordable units are actually low income rather than very low income, the project would not qualify for the density bonus (04:38:27)
                                                                                                          • A councilmember announced recusal after receiving campaign donations over $500 from Urban Catalyst (04:42:59)
                                                                                                          • An applicant representative said the developer accepts the staff height condition measured under the California Building Code (04:42:17)
                                                                                                          • An applicant representative said the fire variance was submitted October 16, after the director's hearing as the fire department directed, and is being processed (04:43:21)
                                                                                                          • Anthony Tordillos (Councilmember, District 3) said affordability requirements tied to low-moderate housing funds apply to the units eventually built at the Fountain Alley site, not to this project (04:51:45)
                                                                                                          • Anthony Tordillos (Councilmember, District 3) said he checked the law, and labor standards apply to buildings over 85 feet (04:51:45)
                                                                                                          • City staff confirmed that resolving fire code details through alternative means at the building permit stage is not unusual (04:52:56)
                                                                                                          • Michael Mulcahy (Councilmember, District 6) said neither his office nor the community knew of any link between the Knox purchase and this project when the council approved it (04:54:08)
                                                                                                          • Michael Mulcahy (Councilmember, District 6) listed neighborhood fixes under way, including nine streetlights on West San Carlos that were out because of copper wire theft (04:57:13)
                                                                                                          • City staff said the Knox Goodrich agreement includes timelines for this project but is outside the scope of this action (05:00:03)
                                                                                                          • City staff explained that under the building code the top floor surface measures about 84 feet 10 inches, with a three-foot parapet that does not count (05:01:06)
                                                                                                          • City staff told Domingo Candelas (Councilmember, District 8) that AB 130 itself has no affordability requirements (05:03:17)
                                                                                                          • City staff said the 5 percent very low income units let the project use unlimited waivers under density bonus law (05:03:32)
                                                                                                          • Conditional vacation of part of Spring Street for Columbus Park (00:54:47)
                                                                                                            • The chair recalled the city's commitment, made after the encampment at the site was decommissioned, to restore the park for public use, and asked for a timeline (00:55:04)
                                                                                                            • City staff said design is nearly done, construction should start in summer 2027 and the park should open in summer 2028 (00:56:03)
                                                                                                            • City staff said the project is funded, much of it with the last money from the Measure P bond passed in 2000 (00:56:38)
                                                                                                            • Michael Mulcahy (Councilmember, District 6) relayed concerns from nearby industrial-area users that Spring, Irene and Walnut serve as cut-throughs around backups on Taylor, and asked about striping and signal timing (00:57:31)
                                                                                                            • City staff said repaving in the area is planned for next summer, leaving time to adjust striping, and that the department would coordinate with Public Works on timing (00:59:35)
                                                                                                            • Michael Mulcahy (Councilmember, District 6) noted the park plan includes an enhanced crosswalk from the Heritage Rose Garden (01:01:33)
                                                                                                            • Early consideration: 525 Race Street general plan change for a private high school (04:03:28)
                                                                                                              • City staff said that if processing continues, a final approval or denial hearing could come at the end of 2027 (04:03:58)
                                                                                                              • City staff described the site as a vacant two-story office building built in 1998 (04:05:04)
                                                                                                              • City staff said the change would allow converting the building to a private high school for up to 800 students and 100 staff (04:05:04)
                                                                                                              • An applicant representative disclosed that the development advisors are registered lobbyists with the city (04:10:08)
                                                                                                              • An applicant representative said all pickup and drop-off queuing would be kept on the site (04:11:11)
                                                                                                              • A councilmember noted the project expands a school already operating a short walk away at Parkmoor and Race (04:14:14)
                                                                                                              • A councilmember responded to the jobs-land concern by noting a prior council had already set aside the larger block to the south for an 11-acre private school that never went forward (04:16:15)
                                                                                                              • A councilmember asked how the tuition-based school would serve underserved students (04:17:52)
                                                                                                              • An applicant representative answered that the school does not offer scholarships or tuition-reduction programs (04:19:24)
                                                                                                              • Civil Service Commission appointments (05:46:57)
                                                                                                                • The city clerk explained that three of the six applicants were present and the incumbent was eligible only for the full term (05:48:23)
                                                                                                                • A commission applicant said as incumbent he wants to continue after four years on the commission (05:50:05)
                                                                                                                • A commission applicant described retiring after 30 years with the county as a social worker and serving as a discipline review officer (05:52:00)
                                                                                                                • A commission applicant described his private-sector management career at a software company (05:54:58)
                                                                                                                • The chair asked applicants how they would stay impartial when they empathize with someone who broke a rule (06:04:51)
                                                                                                                • Documents: Agenda, Agenda (legistar.granicus.com)

                                                                                                                  Planning Commission, Friday, October 23

                                                                                                                  • Data centers: background ahead of proposed city standards (01:33:05)
                                                                                                                    • City staff said the standards will come before the commission on November 18, so this session would not present them (01:33:05)
                                                                                                                    • City staff said data centers are already allowed with a special use permit in four industrial and commercial zoning districts, which limits what the city can require (01:35:08)
                                                                                                                    • City staff said the California Energy Commission leads environmental review when backup generation exceeds 50 megawatts (01:36:11)
                                                                                                                    • City staff estimated a 99-megawatt data center brings about $6 million a year in utility user tax (01:39:20)
                                                                                                                    • City staff estimated annual property tax at $500,000 to $1 million for a 99-megawatt data center (01:40:22)
                                                                                                                    • City staff said one-time construction tax is likely closer to $17 million, and a commercial linkage fee and an energy programs fee are being proposed (01:40:22)
                                                                                                                    • City staff said the proposal caps backup generators at 25 hours a year with Tier 4 certification, versus the air district's 50 hours (01:43:17)
                                                                                                                    • City staff said the city's proposed requirements add to state CEQA standards even when the state leads the review (01:44:42)
                                                                                                                    • City staff said council directed the standards in a May rules memo voted in June, and an August memo added community benefits, tax revenue and design (01:45:28)
                                                                                                                    • City staff said the proposal sends all appeals of data center special use permits from the director's hearing to the City Council, bypassing the commission (01:48:49)
                                                                                                                    • A commissioner objected that removing the commission takes away a chance for residents to give input, noting community concern and moratoriums elsewhere (01:53:04)
                                                                                                                    • City staff said the appeal change responds to residents who want controversial data center decisions made by the council (01:53:20)
                                                                                                                    • City staff said council directed staff to develop standards, not a moratorium, and that choice rests with the council (01:56:12)
                                                                                                                    • A commissioner relayed residents' reports that no council members attend the data center listening sessions (01:57:05)
                                                                                                                    • City staff said the full package goes to the commission and then to the City Council on December 8, with materials public November 10 (02:02:17)
                                                                                                                    • City staff said a draft at roughly 80% was presented at a community meeting last week (02:01:08)
                                                                                                                    • City staff said the last community meeting drew over 300 people (02:06:25)
                                                                                                                    • City staff said remaining input opportunities include the Youth Commission on October 26 and an online comment form (02:05:24)
                                                                                                                    • A commissioner praised staff outreach and said he would rather see data centers in San Jose than elsewhere, with safeguards (02:08:53)
                                                                                                                    • City staff estimated about 20 data centers operate in the city, mostly much smaller than the 99-megawatt ones now proposed (02:10:32)
                                                                                                                    • City staff said many projects cap at 99 megawatts to stay under the Energy Commission's small power plant exemption (02:11:24)
                                                                                                                    • City staff said the standards are not streamlining, citing limits on cooling systems and generator hours (02:13:58)
                                                                                                                    • City staff said Santa Clara has so many data centers because its utility costs are lower than neighboring cities (02:14:38)
                                                                                                                    • Builder's Remedy, Housing Element and SB 79 updates (00:06:07)
                                                                                                                      • City staff explained that Builder's Remedy is a penalty on cities without a certified housing element, letting qualifying projects ignore general plan and zoning (00:06:33)
                                                                                                                      • City staff said the city can deny a qualifying project only by proving a specific adverse impact on public health and safety, and the burden is on the city (00:07:35)
                                                                                                                      • City staff said such denials are very rare and he could not recall San Jose doing it (00:09:04)
                                                                                                                      • City staff gave the required affordability options as 7% extremely low, 10% very low or 13% lower income (00:13:01)
                                                                                                                      • City staff said staff worked with the developer of the Camden project to make sure its very-low-income for-sale units could actually be filled (00:11:54)
                                                                                                                      • City staff said the city received 33 SB 330 preliminary applications between February and December 2023, and 24 of them became formal applications (00:13:17)
                                                                                                                      • City staff said eight have been approved and two are pending, including a Topgolf ministerial permit and 741 South Winchester, which comes to the commission on appeal on November 4 (00:13:48)
                                                                                                                      • City staff said three applications were withdrawn, two found a different path and 11 remain under review or inactive (00:14:50)
                                                                                                                      • A commissioner asked whether the consequences of lacking a housing element are too severe, given they let anyone build regardless of zoning (00:15:09)
                                                                                                                      • City staff agreed the penalty is very severe and said the city took over two and a half years to write and certify its housing element (00:15:52)
                                                                                                                      • City staff said the city plans to start the next housing element at the start of 2028 because it is due in January 2031 (00:16:59)
                                                                                                                      • City staff said cities out of compliance can face further penalties, including losing the ability to issue building permits or action by the Attorney General (00:18:40)
                                                                                                                      • City staff said the eight approved projects total 697 units and replace a mix of uses (00:19:46)
                                                                                                                      • City staff listed existing uses being replaced, including medical offices, restaurants, retail, Little League fields and an elementary school (00:19:46)
                                                                                                                      • City staff said permits carry a two-year entitlement with an option to extend two more years to start construction (00:21:04)
                                                                                                                      • City staff cited the 1655 Berryessa Road project of 62 townhomes beside the Berryessa BART station as an example of lower density than the city would want (00:21:20)
                                                                                                                      • City staff said none of the approved Builder's Remedy projects has broken ground yet (00:22:11)
                                                                                                                      • City staff said the housing element has over 130 programs whose progress the city must report to the state each year (00:24:46)
                                                                                                                      • City staff said penalties come from failing to carry out promised actions rather than from missing the housing target itself (00:27:06)
                                                                                                                      • City staff said the city had to show sites for 62,200 units on roughly 500 sites under the state's realistic-capacity rules (00:30:50)
                                                                                                                      • City staff said the goal is to finish the next housing element by June 2030, ahead of the January 2031 deadline (00:32:56)
                                                                                                                      • City staff said the city has produced several thousand units a year but has generally fallen far behind its targets, and offered to send the figures (00:34:20)
                                                                                                                      • City staff said the biggest barrier is approved units that have not moved to construction because of economics (00:36:40)
                                                                                                                      • City staff said three projects have been approved through the city's staff-level ministerial process adopted in December 2024, in about 100 days (00:36:40)
                                                                                                                      • City staff said residential entitlements previously took about eight to nine months at the fastest and up to two to three years (00:38:12)
                                                                                                                      • City staff said getting applicants' plans to completeness takes the longest, and staff are exploring earlier joint review with developers (00:40:30)
                                                                                                                      • A commissioner suggested the city offer some kind of class to help developers submit complete applications (00:41:21)
                                                                                                                      • A commissioner asked what penalties the city faces if it does not reach its housing allocation (00:43:05)
                                                                                                                      • City staff said the allocation is an aspirational goal and a capacity the city must show, since the city itself does not build housing (00:44:44)
                                                                                                                      • City staff said SB 79 took effect July 1 and covers about 56 light rail, Caltrain and BART stations in or near San Jose (00:45:23)
                                                                                                                      • City staff said five industrial areas were exempted, and since July 1 the city has received no formal applications and one preliminary application (00:47:25)
                                                                                                                      • City staff said staff will likely not pursue the exemption for sites lacking a one-mile walking path and will explain why in an information memo (00:49:30)
                                                                                                                      • City staff said staff are drafting an ordinance defining demolition for historic resources, targeted for the commission in November (00:51:33)
                                                                                                                      • Public comment (02:14:49)
                                                                                                                        • A commissioner thanked the speaker and invited them to attend the November hearing (02:17:42)
                                                                                                                        • Documents: Agenda

                                                                                                                          This episode was produced with AI from the public recording of the meeting. Links to the source are in the show notes.

                                                                                                                          Report an error · This episode's page

                                                                                                                          11 min
                                                                                                                        • Council and Valley Water prepare for El Niño; council asks for ranked flood hotspots

                                                                                                                          At a joint meeting with the Valley Water board, the San Jose City Council directed city staff to work with Valley Water on a risk-ranked list of flood hotspots, ideally before the rainy season. Plus a short update on Anderson Dam and Coyote Creek, and a look at next Tuesday's council agenda.

                                                                                                                          City Council, Tuesday, October 13

                                                                                                                          • Joint El Niño flood preparedness update (00:11:45)
                                                                                                                            • Valley Water staff said a stronger-than-normal El Niño does not necessarily mean flooding locally, but the national attention is a chance to educate the public (00:12:22)
                                                                                                                            • Valley Water staff explained that creek ownership is a patchwork across about 800 miles of county waterways, with Valley Water owning or managing about 350 miles and maintaining the roughly 185 miles where it built flood projects, while private owners must maintain their own land (00:14:36)
                                                                                                                            • City staff described the city's role: readying storm sewers, monitoring weather and creek debris, clearing streets, closing roads and supporting recovery (00:16:00)
                                                                                                                            • Valley Water staff said Valley Water's dry-season stream maintenance program did about 166 projects this year, a number that has been as high as 300 (00:18:30)
                                                                                                                            • City staff said the joint emergency action plan written with Valley Water after the 2017 flood has been tested 12 times in storms (00:19:44)
                                                                                                                            • City staff said the plan is updated every year and signed by the city manager and Valley Water's chief executive, and that 29 staff from both agencies last updated it on September 21 (00:20:54)
                                                                                                                            • An official said Valley Water has hosted three inter-agency exercises on Anderson Dam and flooding scenarios since the end of July, with the city taking part (00:23:34)
                                                                                                                            • Valley Water staff said Valley Water's annual multilingual flood awareness campaign would launch in two days (00:27:03)
                                                                                                                            • Valley Water staff said Valley Water sent more than 48,000 flood awareness mailers last year and expects a similar reach this year, plus about 17,000 targeted mailings in hotspot areas (00:28:04)
                                                                                                                            • Valley Water staff announced an annual winter preparedness workshop on October 29 and a joint press conference planned before the first big storm (00:28:04)
                                                                                                                            • Valley Water staff said Valley Water lobbied state and federal officials for permitting relief, including Endangered Species Act flexibility, so emergency storm-prep work can be done in creeks (00:30:11)
                                                                                                                            • Valley Water staff said Valley Water runs five sandbag sites countywide, with webcams at two San José sites, and will stock them before storms arrive (00:31:51)
                                                                                                                            • Valley Water staff reminded residents that a flood insurance policy takes thirty days to take effect, and later corrected the federal website to floodsmart.gov (00:34:07)
                                                                                                                            • An official said Valley Water monitors more than 100 blockage hotspots countywide and clears debris with cranes and excavators before, during and after storms (00:38:10)
                                                                                                                            • City staff said the city clears blockages on its own property through emergency contracts with Tucker Construction (00:39:36)
                                                                                                                            • Valley Water staff said Valley Water works with outreach crews before storms to warn unhoused people living below the high-water line (00:44:23)
                                                                                                                            • City staff said the city alerts unhoused residents to move to higher ground, has opened shelters, and once set up interim housing with raised tent platforms (00:44:42)
                                                                                                                            • An official said the city has had to keep 26 miles of waterways clear of encampments for the past two years and will hold shelter capacity for storms (00:45:31)
                                                                                                                            • The mayor asked whether the agencies have done a full risk assessment ranking the top hotspots, and what they will do about each before heavy rain (00:51:50)
                                                                                                                            • Valley Water staff said Valley Water inspects its own waterways every year but has no program to inspect all 800 miles of creek, and is limited by regulations on natural channels (00:52:48)
                                                                                                                            • City staff said the city is working now to remove two spots of woody debris mixed with carpet and chain-link fence along Coyote Creek (00:55:53)
                                                                                                                            • City staff acknowledged the city has historically relied on Valley Water to tell it about risk in the waterways (00:55:53)
                                                                                                                            • The mayor moved to have city staff, working with Valley Water, produce a flood risk analysis with ranked hotspots and a way for residents to report concerns (00:57:32)
                                                                                                                            • The mayor added longer-term direction for city staff to work with Valley Water on reducing flood risk and setting out each agency's role (00:58:35)
                                                                                                                            • A councilmember asked what maintenance is planned along Penitencia Creek on the East Side and what risks remain (00:59:55)
                                                                                                                            • City staff said Upper Penitencia is an unimproved channel and the city will partner with Valley Water to remove a fallen tree and clear an encampment under a bridge (01:00:44)
                                                                                                                            • Valley Water staff said a capital project for Upper Penitencia is years away, so Valley Water has asked the governor to waive permitting and mitigation requirements there for sediment removal (01:02:07)
                                                                                                                            • City staff said the encampment cleanup on Upper Penitencia is about two weeks out (01:03:33)
                                                                                                                            • An official said the city is working with its housing department to offer outreach and housing resources to the person living in the waterway (01:04:10)
                                                                                                                            • A councilmember noted there was no concrete housing destination yet, and asked what accountability measures keep problems from falling through the cracks between agencies (01:04:22)
                                                                                                                            • An official pointed to the two trail-user commenters and asked both agencies whether there is a plan to keep flooded Guadalupe River Trail underpasses open this year (01:06:49)
                                                                                                                            • City staff said trail underpass cleanup is not a standalone item in the plan, but the city will add it to its post-storm list (01:07:10)
                                                                                                                            • Valley Water staff said trail underpasses sit in the low-flow channel, the lowest point of a creek, so they are the slowest to drain (01:07:52)
                                                                                                                            • An official urged Valley Water to do a proactive creek bank assessment and a long-term prevention plan for homeowners along the Los Gatos Creek and Guadalupe River (01:09:18)
                                                                                                                            • Valley Water staff said Valley Water usually does not know about problems on private creekside land until someone reports them, and offers permitting guidance through its hotline (01:11:07)
                                                                                                                            • Valley Water staff said Valley Water lacks the resources to walk all 800 miles of creek each year, though new revenue could change that (01:14:00)
                                                                                                                            • An official said a website referral was not enough and residents deserve more proactive effort from Valley Water (01:15:42)
                                                                                                                            • An official noted that regulators close creeks to in-stream work after October 15 regardless of flood risk (01:15:58)
                                                                                                                            • An official urged both agencies to press state and federal officials together for permit waivers at the worst hotspots this year (01:18:04)
                                                                                                                            • An official said creek trails were designed to flood because they sit in low-lying areas (01:19:07)
                                                                                                                            • An official promoted the city's Adopt a Storm Drain program and asked colleagues to link the joint emergency action plan in their newsletters (01:21:12)
                                                                                                                            • A councilmember cited a petition from several hundred residents asking for the agencies to work together (01:22:47)
                                                                                                                            • A councilmember argued Valley Water's expertise puts it in a position to lead, possibly through central permitting help, fee-for-service maintenance, or city easements (01:22:47)
                                                                                                                            • Valley Water staff said Valley Water already offers permitting help and contracts to do work for San José when the city asks (01:24:18)
                                                                                                                            • City staff said the city will support Valley Water's lobbying for funds and waivers, and noted that woody debris is not always a flood risk (01:26:49)
                                                                                                                            • A Valley Water board member urged the city to stop allowing building in floodplains and to consider reclaiming such areas (01:29:17)
                                                                                                                            • A Valley Water board member asked whether the city's general plan update includes a policy against building in flood-prone areas (01:30:28)
                                                                                                                            • A councilmember said this probably wasn't in the scope of the council's four-year general plan review, but could be part of the coming housing element and next general plan (01:30:44)
                                                                                                                            • A Valley Water board member called for action and motions instead of long discussion, saying federal funding is needed to finish Penitencia Creek work (01:32:32)
                                                                                                                            • An official raised concern about the growing burden of flood protection and water costs on residents, citing a letter he sent (01:33:04)
                                                                                                                            • A Valley Water board member raised a point of order that water rates were not on the agenda and had already been adopted in June (01:34:54)
                                                                                                                            • An official asked the board to look for ways to reduce costs (01:35:44)
                                                                                                                            • The mayor restated the motion: a joint report back, ideally before the rainy season, listing and risk-ranking hotspots on the city's roughly 140 miles of waterways, with plans for high-risk sites (01:36:19)
                                                                                                                            • A Valley Water board member suggested a joint fiscal emergency team to get as much federal and state emergency money as possible, recalling the 1983 floods (01:38:08)
                                                                                                                            • The Valley Water board chair said the Valley Water board could direct its staff to work with the city on the council's motion as a joint effort (01:40:16)
                                                                                                                            • An official said city staff stand ready to work with Valley Water on pursuing outside funding (01:41:34)
                                                                                                                            • Anderson Dam seismic retrofit and Coyote Creek flood protection update (01:42:35)
                                                                                                                              • An official proposed a brief two-minute update and questions in place of the full presentation because time was short (01:42:35)
                                                                                                                              • Valley Water staff reported the Anderson Dam tunnel project is done, in testing, and can operate this winter together with the completed Coyote Creek phase one (01:43:14)
                                                                                                                              • Valley Water staff said contracts are awarded and construction is just beginning on the dam seismic retrofit and Coyote Creek phase two (01:43:14)
                                                                                                                              • Valley Water staff said Valley Water is working with the city on planned park closures, property purchases and encampment cleanups for the Coyote Creek work (01:44:23)
                                                                                                                              • Call to order, roll call and opening remarks (00:00:44)
                                                                                                                                • The city clerk announced that the mayor was taking part remotely under the Brown Act's just-cause provisions (00:01:12)
                                                                                                                                • The Valley Water board chair recounted that the two bodies first met jointly in 2002 and have met every year since, putting this at about their twenty-fourth meeting (00:03:55)
                                                                                                                                • The mayor said the agencies have learned a lot since the 2017 floods and are coordinating more closely than ever (00:06:59)
                                                                                                                                • The mayor argued that residents who see a blockage in a creek should not have to think about which agency owns it, and called for clear roles between the agencies (00:08:04)
                                                                                                                                • Pam Foley (Councilmember, District 9; Vice Mayor) announced there would be no open forum and asked elected officials to keep their comments to three minutes because of a two-hour limit (00:10:54)
                                                                                                                                • Pure Water Silicon Valley potable reuse project update (deferred) (01:48:50)
                                                                                                                                • Commendation for the retiring Valley Water board chair (01:49:10)
                                                                                                                                  • An official honored the chair for more than three decades of service on the Valley Water board and for advocating for vulnerable residents (01:50:19)
                                                                                                                                  • An official presented a commendation, noting the mayor had signed it remotely, and congratulated the chair on retiring (01:52:24)
                                                                                                                                  • The Valley Water board chair thanked the bodies and described coming to San José through Job Corps, going back to high school, and giving decades to legal aid and the water board (01:56:01)
                                                                                                                                  • Documents: Agenda

                                                                                                                                    This episode was produced with AI from the public recording of the meeting. Links to the source are in the show notes.

                                                                                                                                    Report an error · This episode's page

                                                                                                                                    9 min
                                                                                                                                  • Council approves delivery robot rules; new developer for the Arena Hotel

                                                                                                                                    The San Jose City Council passed rules for delivery robots on sidewalks and in bike lanes, started talks with a new developer for the city-owned Arena Hotel, and approved a loan of up to $5.7 million to turn a former Comfort Suites on North First Street into housing.

                                                                                                                                    City Council, Tuesday, October 6

                                                                                                                                    • Rules for delivery robots on sidewalks and in bike lanes (00:36:40)
                                                                                                                                      • A speaker said three operators approached the city this spring, and with no regulations in place the city let them operate while it developed a framework (00:39:53)
                                                                                                                                      • A speaker described the proposed 5 mph limit on sidewalks, pedestrian paths and crosswalks (00:42:57)
                                                                                                                                      • A speaker said a disabled robot must be moved within thirty minutes or the operator faces a fine (00:42:57)
                                                                                                                                      • A speaker said that on the advice of the Bicycle and Pedestrian Advisory Committee, bikeway robots would match the pace of cyclists instead of having a fixed speed limit (00:43:58)
                                                                                                                                      • The meeting chair asked what the city is doing to limit its liability exposure in future accidents, noting past lawsuits involving scooters and e-bikes (00:52:12)
                                                                                                                                      • City staff said the ordinance has a robust indemnification provision modeled on lessons from the city's micromobility programs (00:52:54)
                                                                                                                                      • Pam Foley (Councilmember, District 9; Vice Mayor) said she is very concerned about congestion on sidewalks, and asked whether the companies have the financial strength to back their indemnification (00:53:16)
                                                                                                                                      • City staff said the ordinance requires the city to be named as an additional insured, with policy limits to be set in administrative regulations before permits are issued (00:55:04)
                                                                                                                                      • Pam Foley (Councilmember, District 9; Vice Mayor) criticized outreach to the disability community as limited to a few organization leaders, and asked how many people with disabilities staff had heard from (00:55:25)
                                                                                                                                      • A speaker said staff will work with the Independent Living Center to set up a focus group of San Jose residents with disabilities to give ongoing feedback (00:56:32)
                                                                                                                                      • A speaker said more than 50 people attended the outreach webinar, though she did not recall the exact number (00:58:06)
                                                                                                                                      • A speaker gave the fines for improperly parked devices as $100, $200 and $500 for first, second and third offenses (00:58:06)
                                                                                                                                      • Pam Foley (Councilmember, District 9; Vice Mayor) said the fines did not seem stiff compared with the harm to someone in a wheelchair blocked by a device (00:59:09)
                                                                                                                                      • Pam Foley (Councilmember, District 9; Vice Mayor) raised concern about robots sharing sidewalks with electric scooters and said she was not sure she could support the item (01:00:09)
                                                                                                                                      • A speaker urged a go-slow-to-go-fast approach and limits on the number of devices, warning that congestion builds quickly when many devices share limited space (01:03:16)
                                                                                                                                      • City staff said the regulations reserve the right to limit operators, device numbers and service areas, but staff is not proposing those limits yet (01:04:58)
                                                                                                                                      • A councilmember said that downtown has been the testing ground, and that robots replacing car trips and double-parked delivery drivers could be a net safety benefit (01:09:54)
                                                                                                                                      • City staff said no state or local law currently regulates these devices, so without the ordinance the city has no direct authority to stop or shape their operation (01:11:07)
                                                                                                                                      • A councilmember asked about the process for making property owners whole, citing reports of a dispute over repairing a window broken by a robot on the Paseo (01:11:56)
                                                                                                                                      • City staff said a Coco robot cracked the window while under human remote control, and that his understanding is the company quickly agreed with the owner on responsibility and cost (01:12:48)
                                                                                                                                      • A speaker asked whether the department has the staff to oversee the program, especially in the pilot phase (01:13:55)
                                                                                                                                      • City staff said a paid-for position to oversee the program has been filled, and the hire accepted last week (01:14:31)
                                                                                                                                      • City staff said operators are expected to indemnify the city for ordinary sidewalk irregularities, but the city cannot waive liability where it is the sole cause of negligence (01:15:27)
                                                                                                                                      • A speaker asked whether data from the robots could be used to find sidewalk trouble spots before they become problems (01:16:21)
                                                                                                                                      • City staff said staff will evaluate using operator data during the pilot, weighing liability and accuracy concerns (01:17:03)
                                                                                                                                      • A speaker urged the operators to maintain their devices so they do not add to sidewalk clutter and blight, as he said scooters have (01:19:55)
                                                                                                                                      • City staff said the plan is nine months of operation followed by about three months of analysis before returning to council, with operations continuing in the meantime (01:21:17)
                                                                                                                                      • The meeting chair noted the city has roughly a $2 billion deferred maintenance backlog, while saying the city should still push to fix sidewalk problems quickly (01:21:52)
                                                                                                                                      • A speaker argued that human delivery drivers stopping in traffic are a bigger problem than robots (01:23:00)
                                                                                                                                      • A speaker described seeing delivery robots move safely through crowds at Oregon State University (01:24:08)
                                                                                                                                      • City staff said the regulations can be changed on twenty-four hours' notice to the companies (01:25:32)
                                                                                                                                      • City staff said staff could recommend ending the bikeway pilot if it pushes cyclists into traffic, and will do both quantitative and qualitative outreach (01:26:44)
                                                                                                                                      • Pamela Campos (Councilmember, District 2) asked what fees Los Angeles and West Hollywood charge, since the staff report describes them as the highest (01:29:29)
                                                                                                                                      • A speaker said Los Angeles charges $10,000 for up to 50 devices and a flat $20,000 above that, and West Hollywood works out to about $250 per device (01:29:55)
                                                                                                                                      • Pamela Campos (Councilmember, District 2) asked whether the city could raise the fee after a year if warranted (01:30:57)
                                                                                                                                      • City staff said fees are reviewed every year for cost recovery and go back to council in the budget cycle (01:31:21)
                                                                                                                                      • Arena Hotel: new developer and reworked Homekey plan (01:40:24)
                                                                                                                                        • City staff said the city bought the site in 2023 intending 30%-and-below permanent supportive housing with Urban Housing Communities, and is now recasting the project as mixed-income in two phases (01:40:43)
                                                                                                                                        • City staff said ECS was the highest-scoring respondent and has about forty years of experience, including converting eight hotels (01:43:12)
                                                                                                                                        • City staff said the parking lot phase is expected to hold around 200 or more units (01:43:12)
                                                                                                                                        • City staff said the city will ask HCD to move the 100% 30%-of-median-income occupancy requirement to other sites, giving the Arena property income flexibility (01:44:18)
                                                                                                                                        • City staff said the agreement includes a right to switch to a second developer if the first cannot move forward on time, a structure staff plans to use going forward (01:45:50)
                                                                                                                                        • A speaker said the city spent $46 million between Homekey and Measure E on the roughly acre-and-a-half site for 87 units, and that the BART tunnel's path now limits density there (01:47:46)
                                                                                                                                        • A speaker argued the community was promised new investment but got the opposite, and that the site was awarded to a developer that was not qualified (01:48:50)
                                                                                                                                        • A speaker described the memo's direction for staff to return in six months with an update on negotiations and, when ready, an amended Homekey agreement (01:51:59)
                                                                                                                                        • Pamela Campos (Councilmember, District 2) asked which parts of the transition from interim to permanent housing are in the city's control and which need approval from HCD, saying her district faces a similar situation at 1 Branham Lane (01:53:14)
                                                                                                                                        • City staff said all approvals go through HCD, and in early conversations HCD has been open to the city's requests, with no guarantees (01:55:07)
                                                                                                                                        • City staff said the conversion will need a fully funded financing plan, likely low-income housing tax credits, and the building is structurally suitable for permanent housing (01:55:33)
                                                                                                                                        • City staff said the city's 22 interim housing sites are too varied for one conversion approach, though the city wants a consistent policy framework (01:56:33)
                                                                                                                                        • $5.7 million loan to convert former Comfort Suites at 1510 North 1st Street (01:32:18)
                                                                                                                                          • City staff said the conversion will create 57 units at 30% of area median income and below, with services (01:32:56)
                                                                                                                                          • City staff said the city is contributing a total of $5.7 million, and the Housing Authority is developing the site and fully project-basing its vouchers there to cover operating costs (01:34:01)
                                                                                                                                          • City staff said the cost per unit, excluding the $10 million acquisition cost, is about $366,000 (01:34:56)
                                                                                                                                          • City staff said the Housing Authority's plan is to move the roughly 43 participants now living at the SureStay interim site into the converted building (01:35:57)
                                                                                                                                          • City staff described the financing as a 9% low-income housing tax credit project, with about $11 million in permanent financing from the Housing Authority and $5.7 million from the city (01:37:01)
                                                                                                                                          • A speaker said the area needs a lift and has been a challenge for the surrounding neighborhood, including Rosemary Gardens (01:38:28)
                                                                                                                                          • City staff said the official transfer of the neighboring SureStay property to the Housing Authority is expected around the end of October or November (01:39:10)
                                                                                                                                          • A speaker noted that a privately owned motel just south of the site, which had been a trouble spot, has been shut down and the owner plans to reinvest (01:39:30)
                                                                                                                                          • Proclamation: National Arts and Humanities Month (00:05:14)
                                                                                                                                            • A councilmember said she was proud to celebrate the arts and humanities and the impact they have on the community, at a time when major cultural institutions in the country are under threat (00:05:41)
                                                                                                                                            • A speaker announced that the annual Cornerstone of the Arts Awards will be celebrated on October 16 at the Hammer Theatre Center (00:08:34)
                                                                                                                                            • Proclamation: Walk and Roll to School Day (00:10:41)
                                                                                                                                              • Pam Foley (Councilmember, District 9; Vice Mayor) described the day as a way to encourage parents to walk their children to school instead of driving, and called for continued investment in crosswalks, sidewalks and protected bike lanes (00:10:57)
                                                                                                                                              • A speaker said the Department of Transportation's walk and roll program has grown to 115 participating schools (00:14:09)
                                                                                                                                              • Proclamation: Filipino American History Month (00:16:54)
                                                                                                                                                • A councilmember noted that he is the first Filipino American elected to the San Jose City Council and recounted the history of the month's national recognition (00:17:05)
                                                                                                                                                • Adjournment in memory of a longtime San Jose teacher and coach (00:23:34)
                                                                                                                                                  • A speaker described his nearly four decades at Yerba Buena High School teaching business, leading the cheer program and coaching basketball (00:24:04)
                                                                                                                                                  • City Manager's report: new director of racial and social equity (00:30:26)
                                                                                                                                                    • City staff said the new director will lead an office of six employees with an annual operating budget of about $3.3 million, and described her past work as the first chief equity officer for the District of Columbia (00:30:31)
                                                                                                                                                    • A speaker said she sees the work as changing outcomes and centering the experiences of the people most affected, including sharing power with the communities the city serves (00:35:34)
                                                                                                                                                    • Consent calendar (00:29:45)
                                                                                                                                                    • Orders of the Day: Civil Service Commission interviews deferred (00:22:36)
                                                                                                                                                      • The meeting chair relayed the clerk's recommendation to defer item 3.3 to October 20 (00:22:36)
                                                                                                                                                      • The city clerk reported the voting system was showing only 10 members and asked for a voice vote while it was fixed (00:23:20)
                                                                                                                                                      • Open Forum (01:57:39)
                                                                                                                                                        • The meeting chair thanked the speaker who raised bike lane debris and said the city would follow up offline (01:59:51)
                                                                                                                                                        • Documents: Agenda, Agenda (legistar.granicus.com)

                                                                                                                                                          This episode was produced with AI from the public recording of the meeting. Links to the source are in the show notes.

                                                                                                                                                          Report an error · This episode's page

                                                                                                                                                          11 min
                                                                                                                                                        • Council splits on downtown parking rates; detention facility moratorium adopted

                                                                                                                                                          The San Jose City Council passed a scaled-back downtown parking package that raises garage rates but leaves meters alone, and adopted a temporary moratorium on detention and custodial facilities on private and public property. Also: a Friday study session on two tools for paying for infrastructure.

                                                                                                                                                          City Council, Tuesday, September 29

                                                                                                                                                          • Downtown parking meter and garage rates and hours (00:53:24)
                                                                                                                                                            • A speaker gave the budget background: the council closed a $50 million ongoing general fund shortfall in the 2026-27 budget. (00:54:10)
                                                                                                                                                            • A speaker noted the adopted budget includes an ongoing transfer from the parking fund to the general fund, supported by the proposed meter rate and hour changes. (00:55:18)
                                                                                                                                                            • A speaker acknowledged staff fell short on outreach before the June 23 meeting and were told to do more. (00:56:26)
                                                                                                                                                            • A speaker said downtown meter rates were last updated in 2014 and most meter operating hours have not changed in more than twenty years. (00:57:37)
                                                                                                                                                            • A speaker said the city runs about 2,500 on-street metered spaces and that meter revenue has been roughly flat at about $3 million to $3.2 million a year. (00:57:37)
                                                                                                                                                            • A speaker compared rates: Santana Row charges $3 an hour on the street against San José's current $2. (00:58:41)
                                                                                                                                                            • A speaker said staff held eight stakeholder meetings between July 17 and September 2, including with the Downtown Association, business districts and the Downtown Parking Board. (01:00:45)
                                                                                                                                                            • A speaker said the employee permit discount would be open to workers earning up to 50% above minimum wage, up from 30%, with tips no longer counted. (01:01:48)
                                                                                                                                                            • A speaker laid out the five-year phasing, with downtown meter hours extending from 6 p.m. to 9 p.m. in year three. (01:03:55)
                                                                                                                                                            • A speaker said the plan keeps the $1.2 million annual general fund transfer and would produce about $5 million in new money for the parking system over five years. (01:03:55)
                                                                                                                                                            • A speaker listed upcoming capital needs, including adding an elevator at the Second and San Carlos garage, estimated at $11 million to $15 million. (01:05:08)
                                                                                                                                                            • A speaker said the administration supports the memo from Anthony Tordillos (Councilmember, District 3), with suggested wording on its item 2A. (01:08:23)
                                                                                                                                                            • Anthony Tordillos (Councilmember, District 3) proposed a two-year plan instead: year one raises garage special-event and daily rates ($1.25 per 15 minutes), and year two sets $3 an hour at meters in all meter districts. (01:28:15)
                                                                                                                                                            • Anthony Tordillos (Councilmember, District 3) said the memo drops the 6-to-9 p.m. meter extension and the extra downtown-only meter increases, based on feedback from downtown residents, businesses and workers. (01:29:22)
                                                                                                                                                            • Anthony Tordillos (Councilmember, District 3) said the memo would cover the $1.2 million general fund contribution and still leave about $800,000 a year for the parking fund, and moved approval of the memo. (01:30:24)
                                                                                                                                                            • A speaker confirmed the memo would replenish the parking fund over several years. (01:32:11)
                                                                                                                                                            • David Cohen (Councilmember, District 4) said it was frustrating that rates had not risen in years, and suggested the city consider regular CPI-style adjustments. (01:32:20)
                                                                                                                                                            • David Cohen (Councilmember, District 4) said he had found downtown Oakland and Sacramento parking to cost about twice as much as San José's. (01:33:21)
                                                                                                                                                            • A speaker said meter data comes from payment transactions, so staff cannot tell exactly how long cars stay or how many spaces are open at a given time. (01:34:45)
                                                                                                                                                            • A speaker said staff add manual counts and are working on a curb management program that uses cameras to track curb use. (01:35:51)
                                                                                                                                                            • David Cohen (Councilmember, District 4) suggested staff eventually report the utilization data to the Transportation and Environment committee. (01:36:33)
                                                                                                                                                            • A speaker said the smart meters are nearing the end of their useful life and staff are looking at replacing them with virtual, pay-by-plate payment, which would need an RFP. (01:37:49)
                                                                                                                                                            • A speaker told George Casey (Councilmember, District 10) the Downtown Parking Board has three vacancies and five applications on file with the clerk. (01:40:03)
                                                                                                                                                            • George Casey (Councilmember, District 10) asked whether staff had analyzed the effect on downtown businesses, which he said run on thin margins. (01:40:31)
                                                                                                                                                            • A speaker said staff had not done a detailed business impact analysis, and suggested the future parking plan could include one. (01:42:08)
                                                                                                                                                            • George Casey (Councilmember, District 10) said he would not support the memo and wanted more time to avoid harming businesses. (01:42:44)
                                                                                                                                                            • A speaker said that without the deficit, the general fund transfer probably would not be proposed, but staff would still seek rate increases to pay for capital needs. (01:43:56)
                                                                                                                                                            • A councilmember said the process began disingenuously, because the revenue was built into the budget without the council fully understanding it. (01:45:02)
                                                                                                                                                            • A speaker said that under the staff plan, money for extra garage security and cleaning would come in years four and five. (01:46:42)
                                                                                                                                                            • A speaker said the memo would leave about $800,000 a year in ongoing revenue beyond the general fund transfer, available for maintenance and capital work. (01:47:42)
                                                                                                                                                            • A speaker said the old garage bonds were refunded years ago and the parking fund now carries no debt obligations. (01:49:42)
                                                                                                                                                            • A speaker said staff review parking budgets with the Downtown Parking Board three times a year. (01:50:46)
                                                                                                                                                            • A councilmember asked the city to reconsider requiring parking board members to file Form 700 disclosures, and to present information to the board even when meetings lack a quorum. (01:51:03)
                                                                                                                                                            • A speaker said the city does not coordinate event pricing with private parking operators but reviews their rates once a year. (01:54:38)
                                                                                                                                                            • A councilmember asked what new meter technology would cost and whether there is a reserve for it. (01:56:40)
                                                                                                                                                            • A speaker said there is no cost estimate yet and no reserve for replacing the meters. (01:56:56)
                                                                                                                                                            • A speaker asked whether staff had studied how longer meter hours affected foot traffic in other cities' downtowns. (01:57:40)
                                                                                                                                                            • A speaker said staff compared only peer cities' rates and did not do an impact analysis. (01:58:57)
                                                                                                                                                            • A speaker argued that service workers who now park free after 6 p.m. would in effect pay to go to work, even with a discount. (01:59:59)
                                                                                                                                                            • A speaker questioned why the budget gap was being closed on downtown in particular, citing the hotel tax as well. (02:01:02)
                                                                                                                                                            • A speaker said he wished staff had brought information on other cities that made similar changes. (02:03:10)
                                                                                                                                                            • A councilmember pointed to aging meters and garages, including a garage between Second and Third Streets so old it is not ADA compliant, and urged earlier investment. (02:03:41)
                                                                                                                                                            • A councilmember urged filling the parking board vacancies quickly. (02:05:42)
                                                                                                                                                            • A speaker clarified that the memo's two main differences from staff are no 6-to-9 p.m. meter extension and no extra $1 downtown-only meter increase. (02:07:20)
                                                                                                                                                            • A speaker said that if nothing passed, the parking fund would spend more than it takes in, and the gap would have to be dealt with in the 2027-28 budget. (02:09:07)
                                                                                                                                                            • A speaker noted other budget trade-offs the council had already made, such as not opening a fire station or the police training center. (02:09:07)
                                                                                                                                                            • City staff added that the longer action on the fund is delayed, the deeper its structural imbalance becomes. (02:12:34)
                                                                                                                                                            • The meeting chair said she had heard from event ushers worried about parking costs, supported keeping meter hours ending at 6 p.m., and was unsure about the rest of the memo. (02:13:00)
                                                                                                                                                            • The meeting chair said she worries about her safety walking through the San Pedro garage at night. (02:14:01)
                                                                                                                                                            • Pamela Campos (Councilmember, District 2) asked whether the item could go to a joint meeting of the council and the Downtown Parking Board, since the board has been unable to meet for lack of a quorum. (02:15:24)
                                                                                                                                                            • City staff said a joint meeting is possible but the board would still need a quorum. (02:16:20)
                                                                                                                                                            • A speaker said four members are seated on the board, so all four must attend for a quorum, and the clerk's office is pressing for the three appointments. (02:16:35)
                                                                                                                                                            • A speaker said the formal five-year budget forecast is not available until March 1. (02:19:02)
                                                                                                                                                            • David Cohen (Councilmember, District 4) said the council could approve parts of the memo, since the meter-rate increases in items 1D and 1E seemed to be what concerned members. (02:19:58)
                                                                                                                                                            • Anthony Tordillos (Councilmember, District 3) preferred his full memo, warning that approving only the event and garage increases would not break even. (02:22:24)
                                                                                                                                                            • A councilmember called a joint meeting with an advisory board unusual and preferred filling its vacancies so it can advise the council. (02:23:05)
                                                                                                                                                            • A speaker said the city should not create barriers to coming downtown, while recognizing the budget urgency, and that he liked parts of the memo's phased approach. (02:25:07)
                                                                                                                                                            • A councilmember asked how much the downtown employee parking discount is used. (02:28:04)
                                                                                                                                                            • A speaker said fewer than about 70 permits are in use; the program offers garage parking for $50 a month to qualifying workers. (02:28:53)
                                                                                                                                                            • A councilmember urged better promotion of the employee discount through the downtown and Japantown business associations. (02:29:47)
                                                                                                                                                            • A speaker said the memo's $800,000 a year would be available for reinvestment starting in the first year. (02:31:15)
                                                                                                                                                            • George Casey (Councilmember, District 10) backed the joint-meeting motion, calling it unusual but warranted by the circumstances. (02:33:00)
                                                                                                                                                            • David Cohen (Councilmember, District 4) asked the maker of the joint-meeting motion to add some memo items, including the event rates, the employee permit expansion and the Convention Center free parking. (02:33:35)
                                                                                                                                                            • A councilmember declined the amendment, saying those items were exactly what the joint meeting should discuss. (02:34:22)
                                                                                                                                                            • A councilmember confirmed that no action could be taken at the joint meeting; the item would come back to the council afterward. (02:35:53)
                                                                                                                                                            • Anthony Tordillos (Councilmember, District 3) opposed the joint meeting, noting the parking board had already met twice and made its objections clear. (02:37:08)
                                                                                                                                                            • The meeting chair opposed the joint meeting, saying it would set a precedent for other advisory boards. (02:37:55)
                                                                                                                                                            • Anthony Tordillos (Councilmember, District 3) moved the reduced package, acknowledging the parking fund would still lose some money each year under the $1.2 million transfer. (02:39:36)
                                                                                                                                                            • A councilmember said the dais clearly wants the parking board fully staffed and its appointments expedited, though that was not written into the motion. (02:41:01)
                                                                                                                                                            • Temporary moratorium on new or expanded detention and custodial facilities (00:45:57)
                                                                                                                                                              • A speaker thanked a member of Congress's office and the coalition of supporters, said he hoped other cities would follow San José's lead, and moved approval. (00:50:55)
                                                                                                                                                              • The meeting chair said the item passed as it should have and thanked the colleagues who brought it forward. (00:51:48)
                                                                                                                                                              • Commendation for On Lok's 55th anniversary (00:06:44)
                                                                                                                                                                • George Casey (Councilmember, District 10) described On Lok's 55 years serving Bay Area seniors and noted its newest PACE center opened in District 10. (00:07:24)
                                                                                                                                                                • A guest presenter accepted for On Lok, saying it serves more than 2,000 seniors through its PACE program and is the only PACE provider serving the whole county. (00:08:43)
                                                                                                                                                                • Proclamation: September 2026 is Transit Month (00:10:34)
                                                                                                                                                                  • Pamela Campos (Councilmember, District 2) credited SJSU student advocacy for bringing the Bay Pass to campus, which lets students ride transit across the nine Bay Area counties. (00:11:53)
                                                                                                                                                                  • Pamela Campos (Councilmember, District 2) noted the city's transit-first policy, adopted with the Move San José plan in 2022. (00:12:56)
                                                                                                                                                                  • A speaker said, speaking for SJSU's Associated Students, that during the Bay Pass pilot, students with the pass dropped out or left campus 6% less often than students without it. (00:15:52)
                                                                                                                                                                  • Proclamation: International Day of the Girl (00:20:38)
                                                                                                                                                                    • The meeting chair said City Hall will join other downtown landmarks in lighting up pink from October 5 through 9 for Day of the Girl. (00:22:43)
                                                                                                                                                                    • The meeting chair said she is the honorary chair of this year's Day of the Girl event, hosted by the Boys & Girls Club. (00:22:43)
                                                                                                                                                                    • Joint Council/Financing Authority: wastewater commercial paper program up to $200 million (00:30:45)
                                                                                                                                                                      • A speaker described the sewer system the program funds: more than 2,000 miles of mains and 17 pump stations. (00:31:58)
                                                                                                                                                                      • A speaker said about $300 million of sewer work is planned in the five-year capital improvement program. (00:33:02)
                                                                                                                                                                      • A speaker said about $1.6 billion of investment is expected at the treatment plant over the next ten years, correcting a figure he misspoke first. (00:34:06)
                                                                                                                                                                      • City staff said a request for proposals led to a contract award to Bank of America, and that the city plans to issue notes before October 16, 2026 to refund $90.1 million in outstanding subordinate revenue notes. (00:34:28)
                                                                                                                                                                      • City staff said the facility fee will be 0.31% under the city's credit rating, that wastewater revenues repay the notes, and that the general fund is not pledged. (00:34:28)
                                                                                                                                                                      • City staff said the debt management policy and the municipal code require a two-thirds council vote to approve the notes. (00:36:37)
                                                                                                                                                                      • David Cohen (Councilmember, District 4) thanked staff for their management of the wastewater system and its finances, and moved approval. (00:39:18)
                                                                                                                                                                      • Higher payment to Santa Clara County for household hazardous waste collection (02:42:03)
                                                                                                                                                                        • A councilmember asked why the payment to the county was roughly quadrupling. (02:42:46)
                                                                                                                                                                        • A speaker explained that lower fee revenue, more participation and higher costs combined, leaving the city to pay more or residents to lose access to the program. (02:43:14)
                                                                                                                                                                        • A councilmember called a roughly 400% increase surprising but said the program is important to continue. (02:43:51)
                                                                                                                                                                        • Contract for replacing elevators in the airport terminal (00:51:48)
                                                                                                                                                                        • Consent calendar (00:29:11)
                                                                                                                                                                        • Land use consent: alcohol sales permit for Sakura Market (00:30:18)
                                                                                                                                                                        • Audit of the economic development office's performance measures (00:40:59)
                                                                                                                                                                          • A speaker presented the audit's single finding: the measures are generally useful and reliable, but reporting could be improved. (00:41:27)
                                                                                                                                                                          • A speaker said OEDCA reports 39 measures in the operating budget and that the audit makes five recommendations, including documenting how each measure is calculated. (00:42:31)
                                                                                                                                                                          • City staff said the administration accepts all five recommendations and has prepared a response. (00:43:48)
                                                                                                                                                                          • A councilmember asked whether OEDCA could report small business assistance by council district or neighborhood business district, to show whether help reaches businesses across the city. (00:44:53)
                                                                                                                                                                          • City staff said the office can sort its data that way and will coordinate with the councilmember. (00:45:16)
                                                                                                                                                                          • Documents: Agenda

                                                                                                                                                                            City Council, Friday, October 2

                                                                                                                                                                            • Study session on infrastructure financing tools: Community Facilities Districts and Enhanced Infrastructure Financing Districts (00:00:47)
                                                                                                                                                                              • The presiding officer said he asked for the study session to learn how infrastructure financing tools could help investment in jobs, housing and downtown revitalization (00:00:47)
                                                                                                                                                                              • City staff stressed that the session is only for information and does not authorize forming any district or structure (00:02:45)
                                                                                                                                                                              • City staff went through the history: redevelopment agencies authorized in 1945, the 1982 Mello-Roos Act creating CFDs, redevelopment agencies dissolved in 2012, EIFDs created in 2014, and EIFDs streamlined in 2019 (00:04:48)
                                                                                                                                                                              • City staff explained that a CFD creates a new special tax, while an EIFD funds infrastructure from future growth in property tax without raising taxes (00:06:05)
                                                                                                                                                                              • City staff said a CFD needs two-thirds approval from voters or landowners, while an EIFD needs no vote to form but must go through a set series of public hearings (00:07:06)
                                                                                                                                                                              • City staff said a CFD can sometimes be set up in less than a year (00:08:06)
                                                                                                                                                                              • City staff noted that San Jose already has a Convention Center Facilities District, a special tax paid by hotel property owners that goes back into the convention center (00:08:06)
                                                                                                                                                                              • City staff said an EIFD is much slower, because new property value has to build up before it can be borrowed against, which could take five, eight, ten years or more (00:09:07)
                                                                                                                                                                              • A speaker said, speaking for Public Works, that bonds from a CFD can pay for roads, public parking, streetlights, parks, water and sewer, and flood control (00:12:52)
                                                                                                                                                                              • A speaker said CFDs can fund added services but cannot replace services that existed before the district was formed (00:13:55)
                                                                                                                                                                              • City staff gave a made-up CFD example: 65 units on one acre needing about $5 million of streets, water and sewer work, bonded over about 30 years (00:14:07)
                                                                                                                                                                              • City staff said the example works out to about $4,500 of special tax per unit per year, or about $378 per unit per month once debt service is added (00:15:07)
                                                                                                                                                                              • A speaker said Council Policy 1-14, last amended in 1993, sets a $10 million minimum for the council to consider a new CFD that borrows money (00:15:51)
                                                                                                                                                                              • A speaker said the policy also requires 1,000 single-family homes, a density that may not fit the Envision 2040 general plan, and called the policy out of date and in need of an update (00:15:51)
                                                                                                                                                                              • A speaker said the made-up CFD example would not meet the policy's minimums (00:16:54)
                                                                                                                                                                              • City staff explained that agencies taking part in an EIFD commit all or part of their share of new property tax, either to pay costs as they go or to repay bonds (00:17:06)
                                                                                                                                                                              • City staff listed what an EIFD can fund, including highways, roads, water systems, public safety, civic facilities, parks, site preparation and affordable housing (00:18:08)
                                                                                                                                                                              • City staff said, citing the county controller's figures, that the city's share of new property tax is 13.5%, school districts get 44%, the county 18%, and other taxing entities 24% (00:20:11)
                                                                                                                                                                              • City staff said school districts' share can never go into an EIFD, while most other taxing entities can choose whether to commit their share (00:21:14)
                                                                                                                                                                              • City staff said a made-up $10 billion mixed-use development would, once mature, support about $9 million a year in debt payments from the city's share alone, or about $138 million of bonds over 30 years at 5% interest, and called that yield somewhat modest (00:22:16)
                                                                                                                                                                              • City staff mentioned a state transportation infrastructure loan program that could stretch borrowing capacity further, with conditions attached (00:23:16)
                                                                                                                                                                              • City staff said an EIFD needs a separate public financing authority with a lot of administration and reporting, and can pay costs as it goes, repay developers, or issue bonds (00:24:16)
                                                                                                                                                                              • City staff compared San Francisco, a combined city and county with a single school district that captures about 64 of the yield, with San Jose's roughly 13% share spread among dozens of school and special districts (00:26:19)
                                                                                                                                                                              • A guest presenter explained that under state law an EIFD's public financing authority has five members: three elected officials from the participating bodies and two members of the public who live or work in the district (00:30:13)
                                                                                                                                                                              • A guest presenter described the protest hearing: under 25% protest the district goes ahead, between 25% and 50% an election must be held within 90 days, and over 50% stops it (00:32:17)
                                                                                                                                                                              • A guest presenter clarified that private developers can build market-rate housing inside an EIFD, but housing paid for with EIFD increment or bonds must be affordable (00:34:17)
                                                                                                                                                                              • A guest presenter cautioned that committing the city's property tax share to an EIFD requires weighing the effect on the city's future ability to pay for everyday services (00:35:20)
                                                                                                                                                                              • A guest presenter explained that business owners inside a CFD who are neither registered voters there nor landowners cannot vote on forming it (00:37:22)
                                                                                                                                                                              • A guest presenter described the $10 billion example's bonding capacity as $238 million, after the staff slide had said $138 million (00:40:25)
                                                                                                                                                                              • A guest presenter said timing usually points to using CFDs early in a project and EIFDs later (00:40:25)
                                                                                                                                                                              • A guest presenter said developers benefit because the tools let them borrow at tax-exempt interest rates instead of higher construction-loan rates (00:41:26)
                                                                                                                                                                              • A guest presenter described Sacramento's Aggie Square EIFD, formed in 2021 together with a CFD, where a city policy sends 80% of the increment to infrastructure and 20% to affordable housing (00:43:29)
                                                                                                                                                                              • A guest presenter described West Sacramento's EIFD, formed in 2017 over a little more than 4,100 acres in 14 subareas, which issued bonds in 2025 (00:45:30)
                                                                                                                                                                              • A guest presenter described the Placentia EIFD from 2019, a city-county partnership, and the Eastern Coachella Valley EIFD from 2023, both of which will take years to produce usable value (00:46:30)
                                                                                                                                                                              • A guest presenter noted that the Eastern Coachella Valley district covers 91,000 mostly undeveloped acres and includes 20% of the county's increment (00:47:32)
                                                                                                                                                                              • A guest presenter described San Francisco's Treasure Island financing district, formed in 2017 on a former naval station with 8,000 homes and 300 acres of parks, as a success (00:48:35)
                                                                                                                                                                              • City staff suggested questions for judging future proposals, starting with whether the investment enables development that would not otherwise happen (00:49:57)
                                                                                                                                                                              • City staff said the city could set up a policy framework or decision tree ahead of time for ranking projects and deciding how much increment to commit (00:51:05)
                                                                                                                                                                              • City staff said Public Works, Transportation, Finance, and to some extent planning and housing staff took part in working-group meetings on the session (00:52:09)
                                                                                                                                                                              • A speaker asked who pays the costs of issuing CFD bonds and of compliance, and whether the city does (00:53:07)
                                                                                                                                                                              • A guest presenter answered that issuance costs come out of bond proceeds and ongoing administration out of the special tax, so the city does not pay, though those costs reduce borrowing capacity (00:54:39)
                                                                                                                                                                              • A speaker asked whether an EIFD built on the city's share alone would be worth the effort (00:55:44)
                                                                                                                                                                              • A guest presenter agreed that 13.5% is not a big share and said generating only $138 million from such a development may not be worth it (00:56:02)
                                                                                                                                                                              • A speaker pointed to Measure T's success and said going directly to voters seems more practical than these tools (00:56:55)
                                                                                                                                                                              • A speaker said she does not think the tools are appropriate right now, noting that affordable housing does not bring in property tax (00:57:55)
                                                                                                                                                                              • A speaker said the city has a lot of aging infrastructure and must start thinking about how to pay for it (00:59:04)
                                                                                                                                                                              • The presiding officer responded that the tools are not only for affordable housing and may be useful at some specific sites in the city even today (00:59:40)
                                                                                                                                                                              • A speaker asked what income-level requirements apply to housing funded by tax increment, citing a state code section that lists housing for very low to moderate incomes as eligible (00:59:54)
                                                                                                                                                                              • A guest presenter offered to follow up afterward with the specific requirements (01:00:42)
                                                                                                                                                                              • A speaker said he is interested in using tax increment to support mixed-income housing while keeping properties on the tax rolls (01:01:35)
                                                                                                                                                                              • A speaker suggested EIFDs could add to funding for the city's existing alternative housing finance efforts (01:02:58)
                                                                                                                                                                              • A speaker pointed to Google's Downtown West, approved after years of negotiation and then stalled when the market turned, and asked how forming a district would fit with land assembly and negotiations with developers (01:02:58)
                                                                                                                                                                              • City staff said each case would be judged on its own, ideally starting once land is already assembled and there is a clear development plan, and that hotel and sales tax gains could also be considered (01:04:33)
                                                                                                                                                                              • A speaker summed up the council's homework as updating the CFD rules and getting the city ready to move quickly on large projects with assembled land, rather than forming a district now (01:05:58)
                                                                                                                                                                              • A speaker asked whether staff had modeled any particular areas of the city (01:06:34)
                                                                                                                                                                              • City staff declined to discuss specific locations, saying it could distort landowners' behavior (01:07:16)
                                                                                                                                                                              • A speaker asked whether the county took part in Sacramento's Aggie Square EIFD, where the city's share was 22.6% (01:07:58)
                                                                                                                                                                              • A guest presenter answered that Aggie Square is a city-only EIFD, in partnership with Wexford and UC Davis (01:08:30)
                                                                                                                                                                              • The presiding officer asked how the CFD and EIFD work together at Aggie Square, as a possible model for combining the two (01:09:24)
                                                                                                                                                                              • A guest presenter explained that CFD bonds can be issued once phase one is built, and the expectation is that tax increment from that phase will cover the debt payments instead of levying the special tax (01:11:01)
                                                                                                                                                                              • The presiding officer asked what made county participation possible in some examples and what shared benefits might encourage it (01:11:50)
                                                                                                                                                                              • A guest presenter said Riverside County joined in Eastern Coachella Valley because a large undeveloped area needs infrastructure it wants built sooner (01:12:11)
                                                                                                                                                                              • A speaker noted that special districts and water districts, not only the county, can be EIFD partners (01:12:53)
                                                                                                                                                                              • The presiding officer asked whether school districts are left out by practice or by law, and the answer given was by law (01:13:15)
                                                                                                                                                                              • A guest presenter warned that agencies with small shares usually need a bigger partner, and that some agencies elsewhere that formed EIFDs without one now feel their hands are tied (01:13:35)
                                                                                                                                                                              • City staff said the memo shows the county-wide distribution and she can share a breakdown of the other taxing entities (01:15:13)
                                                                                                                                                                              • The presiding officer said San Jose's share seems low for the city's size and services, and asked what drives it and whether reform is possible (01:15:31)
                                                                                                                                                                              • City staff pointed to a state bill adopted last year on EIFDs for commercial-to-residential conversions, and said she would need to research whether it changed the share available to cities (01:16:20)
                                                                                                                                                                              • A speaker said there probably has been no state bill in the last decade rebalancing the shares, only fixes for specific projects (01:17:08)
                                                                                                                                                                              • A speaker confirmed that the 13.5% is a share of the 1% property tax, and asked for a concrete San Jose case where an EIFD would beat a CFD (01:17:48)
                                                                                                                                                                              • City staff declined to name a specific site, saying near-term CFD revenue could build momentum toward a broader EIFD (01:18:23)
                                                                                                                                                                              • A speaker asked what measure the city would use in five or ten years to tell whether a tool delivered the promised benefits (01:19:12)
                                                                                                                                                                              • City staff said that by the end of a district's life the added land value and other tax revenue should be greater than the cost of the investment (01:19:52)
                                                                                                                                                                              • A speaker asked how the long wait for revenue fits with developers needing infrastructure money upfront (01:20:27)
                                                                                                                                                                              • City staff acknowledged, in reply to an earlier question, that the staff time and consultants needed for analysis bring near-term costs and extra workload (01:23:12)
                                                                                                                                                                              • Documents: Agenda

                                                                                                                                                                                This episode was produced with AI from the public recording of the meeting. Links to the source are in the show notes.

                                                                                                                                                                                Report an error · This episode's page

                                                                                                                                                                                10 min