In episode 126 of The Subcontractors Blueprint podcast, host Jacob Austin continues his JCT Subcontract mini-series providing construction business leaders with a comprehensive overview of design liabilities under JCT 2024 subcontracts. He explains key legal standards, the impact of contract amendments, and the risks of fitness-for-purpose obligations. Jacob highlights the importance of careful contract review, maintaining professional indemnity insurance, and understanding BIM protocols. He shares practical tips for managing design approvals, submission procedures, and liability caps, emphasising how minor contract changes can significantly increase risk. The episode empowers subcontractors to protect their businesses by staying informed and negotiating fair, insurable terms.
KEY TAKEAWAYS:
BEST MOMENTS:
"Skill and care is about how you do the work—doing it professionally—whereas fitness for purpose is about the result."
"If you accidentally or otherwise accept a fitness for purpose obligation, your insurer can decline your coverage."
"Approval in a contract is about consent to move forward, not transferring design risk."
"Many SMEs understandably focus on price, scope and program and gloss over the legal terms, but design liability is one area where a few little sentences can completely change the game."
"High risk should command a higher price, and it may even mean higher insurance coverage."
"Managing design and the risk associated with it is not about avoiding design work, it's about doing it on fair terms, with awareness of where your responsibility ends."
HOST BIO: Meet Jacob Austin, a Chartered Quantity Surveyor with a rich background at construction industry giants Balfour Beatty, Kier, and Vistry Group. With extensive involvement in education, health, and residential projects spanning various scales, from £1000s to over £100M in concurrent developments, Jacob brings a unique perspective. Having collaborated with numerous small businesses, he's now committed to sharing his expertise to drive their success. Join Jacob on his podcast, where he blends his profound insights and personable approach to offer guidance, industry secrets, and inspirational stories.
LinkedIn - www.linkedin.com/in/jacob-austin/
Instagram - www.instagram.com/qs.zone/
www.qs.zone/all-links
In episode 125 of The Subcontractors Blueprint podcast, host Jacob Austin introduces a mini-series on JCT subcontracts, tailored for UK construction subcontractors. He explains the structure and risks of JCT contracts, highlights key changes from the 2016 to 2024 versions—including updates driven by the Building Safety Act 2022—and stresses the importance of reviewing both standard conditions and amendments. Jacob offers practical advice on contract review, payment procedures, and compliance, aiming to help subcontractors avoid costly misunderstandings and operate with greater confidence in today’s evolving contractual landscape.
KEY TAKEAWAYS:
BEST MOMENTS:
"As soon as your materials are on site, they belong to the project, so you can't just drive off with them if things go awry."
"Termination means ending the subcontract before all work is completed, which means both parties are freed from any further obligations to complete the construction of the work."
"If the process isn’t followed properly, then this is effectively a breach. The consequence of that breach is that the calculation is different—you will get full compensation without a deduction."
"Termination is a situation where nobody truly wins. It’s a salvage operation as a subcontractor, and your goal is likely to get out of there without a huge loss and without burning bridges."
"Many subcontractors have been strong-armed into accepting zero compensation after rough termination, simply because they don’t know what they’re entitled to—don’t let that be you."
"Demonstrating you know your stuff can change the conversation—it changes you from being a victim in the process to an informed participant."
Jacob is on a mission to help the 1 million SME contractors working within the construction industry. If you've taken something of value from this episode, please share the podcast with someone you know, and pass the value on.
HOST BIO: Meet Jacob Austin, a Chartered Quantity Surveyor with a rich background at construction industry giants Balfour Beatty, Kier, and Vistry Group. With extensive involvement in education, health, and residential projects spanning various scales, from £1000s to over £100M in concurrent developments, Jacob brings a unique perspective. Having collaborated with numerous small businesses, he's now committed to sharing his expertise to drive their success. Join Jacob on his podcast, where he blends his profound insights and personable approach to offer guidance, industry secrets, and inspirational stories.
LinkedIn - www.linkedin.com/in/jacob-austin/
Instagram - www.instagram.com/qs.zone/
www.qs.zone/all-links
In episode 124 of The Subcontractors Blueprint podcast, host Jacob Austin continues his NEC4 mini-series, focusing on clauses 70, 80, and 90. He provides clear, practical guidance on material ownership, insurance obligations, and, most critically, termination procedures. Jacob explains how to protect your business by understanding payment entitlements, risk allocation, and the importance of following contract procedures. He highlights common pitfalls, offers actionable tips, and stresses the need for documentation and legal advice. This episode and mini-series equips construction business owners with essential knowledge to manage NEC4 contracts confidently and safeguard profitability.
KEY TAKEAWAYS:
BEST MOMENTS:
"As soon as your materials are on site, they belong to the project, so you can't just drive off with them if things go awry."
"Termination means ending the subcontract before all work is completed, which means both parties are freed from any further obligations to complete the construction of the work."
"If the process isn’t followed properly, then this is effectively a breach. The consequence of that breach is that the calculation is different—you will get full compensation without a deduction."
"Termination is a situation where nobody truly wins. It’s a salvage operation as a subcontractor, and your goal is likely to get out of there without a huge loss and without burning bridges."
"Many subcontractors have been strong-armed into accepting zero compensation after rough termination, simply because they don’t know what they’re entitled to—don’t let that be you."
"Demonstrating you know your stuff can change the conversation—it changes you from being a victim in the process to an informed participant."
Jacob is on a mission to help the 1 million SME contractors working within the construction industry. If you've taken something of value from this episode, please share the podcast with someone you know, and pass the value on.
HOST BIO: Meet Jacob Austin, a Chartered Quantity Surveyor with a rich background at construction industry giants Balfour Beatty, Kier, and Vistry Group. With extensive involvement in education, health, and residential projects spanning various scales, from £1000s to over £100M in concurrent developments, Jacob brings a unique perspective. Having collaborated with numerous small businesses, he's now committed to sharing his expertise to drive their success. Join Jacob on his podcast, where he blends his profound insights and personable approach to offer guidance, industry secrets, and inspirational stories.
LinkedIn - www.linkedin.com/in/jacob-austin/
Instagram - www.instagram.com/qs.zone/
www.qs.zone/all-links
In episode 123 of The Subcontractors Blueprint podcast, host Jacob Austin provides construction business owners with practical guidance on managing compensation event clauses under NEC contracts. He explains the crucial differences between early warnings and compensation events, outlines notification and quotation procedures, and emphasises the importance of timely communication, thorough record-keeping, and contract compliance. Using real-world examples, Jacob demonstrates how proactive management of these clauses can protect subcontractors’ interests, improve cash flow, and foster collaborative relationships with contractors—ultimately supporting business growth and successful project delivery.
KEY TAKEAWAYS:
BEST MOMENTS:
"The principle behind [Early Warnings] is that it's a proactive risk management tool to flag up issues that could impact time, cost and quality."
"Early warnings are future events—they may happen or they might not. Compensation events are guaranteed to happen."
"Compensation events are assessed on the basis of defined cost, which is essentially the reasonable cost that you incur yourself, plus an applicable fee."
"A well-prepared quote is critical. It needs to be clear with breakdowns of your labor, plant, materials, and descriptions of how it's been calculated."
"The point is to create early and binding agreements as you go throughout the contract, to avoid the need for lengthy disputes and final account meetings."
"The straight talking truth is that compensation events can become contentious if people can't get around the table and talk sense and come to sensible agreements."
Jacob is on a mission to help the 1 million SME contractors working within the construction industry. If you've taken something of value from this episode, please share the podcast with someone you know, and pass the value on.
HOST BIO: Meet Jacob Austin, a Chartered Quantity Surveyor with a rich background at construction industry giants Balfour Beatty, Kier, and Vistry Group. With extensive involvement in education, health, and residential projects spanning various scales, from £1000s to over £100M in concurrent developments, Jacob brings a unique perspective. Having collaborated with numerous small businesses, he's now committed to sharing his expertise to drive their success. Join Jacob on his podcast, where he blends his profound insights and personable approach to offer guidance, industry secrets, and inspirational stories.
LinkedIn - www.linkedin.com/in/jacob-austin/
Instagram - www.instagram.com/qs.zone/
www.qs.zone/all-links
In episode 122 of The Subcontractors Blueprint podcast, host Jacob Austin guides construction business owners through the payment mechanisms of NEC subcontract agreements, focusing on the 50 series clauses. He explains the importance of assessment dates, compliant payment applications, and the impact of main option clauses (A–E) on cash flow. Jacob highlights that contract amendments that can complicate payments and shares a practical checklist for managing the payment process. The episode offers actionable advice to help subcontractors protect their cash flow, avoid payment disputes, and ensure profitability under NEC contracts.
KEY TAKEAWAYS:
BEST MOMENTS:
"The NEC payment process is only fair if you run it properly and it can punish you with cash flow problems if you don't."
"If your application is non-compliant, you're basically volunteering not to be paid."
"Clause 50.4, The Quiet Assassin...if you miss your application date, you don't just get paid slightly late because you applied late. The contract says that you get nothing."
"Defined cost can be weaponised via audits if you don't have good records of what people were doing and when they were doing it."
"A defective notice could mean that you're entitled to full payment of your application without any deduction."
Jacob is on a mission to help the 1 million SME contractors working within the construction industry. If you've taken something of value from this episode, please share the podcast with someone you know, and pass the value on.
HOST BIO: Meet Jacob Austin, a Chartered Quantity Surveyor with a rich background at construction industry giants Balfour Beatty, Kier, and Vistry Group. With extensive involvement in education, health, and residential projects spanning various scales, from £1000s to over £100M in concurrent developments, Jacob brings a unique perspective. Having collaborated with numerous small businesses, he's now committed to sharing his expertise to drive their success. Join Jacob on his podcast, where he blends his profound insights and personable approach to offer guidance, industry secrets, and inspirational stories.
LinkedIn - www.linkedin.com/in/jacob-austin/
Instagram - www.instagram.com/qs.zone/
www.qs.zone/all-links
In episode 121 of The Subcontractors Blueprint podcast, host Jacob Austin continues the NEC contracts mini-series, providing construction business owners with practical guidance on managing NEC subcontracts. This week he explains the importance of time risk allowances (TRAs) and different types of float—free, total, and terminal—clarifying their roles, ownership, and impact on scheduling and compensation events. Jacob emphasises maintaining an up-to-date, accepted programme as a vital tool for managing risk, demonstrating entitlement to extensions of time, and minimising disputes. The episode offers actionable insights to help subcontractors protect their interests and improve project outcomes under NEC contracts.
KEY TAKEAWAYS:
BEST MOMENTS:
"A program with zero allowances is likely to be optimistic and could be deemed not practicable or unrealistic, and that is a reason for non acceptance of your programme.”
"By showing TRA, you're demonstrating that you built in time buffers for your own risks and thereby increase the confidence that plan completion can be achieved by the date you're saying."
"A well maintained programme also builds your credibility. If the contractor sees that each update is thorough and good and honest, not only are they more likely to accept them without a dispute, but it means when it comes to assessing a compensation event, they're more likely to trust your assessment of it."
"The NEC mantra is that the programme is a management tool, not just a contract requirement."
"If you treat the programme as your friend, invest time in it, invest effort in it, then it will pay you back by minimising disputes and helping you to secure your entitlements against changes."
Jacob is on a mission to help the 1 million SME contractors working within the construction industry. If you've taken something of value from this episode, please share the podcast with someone you know, and pass the value on.
HOST BIO: Meet Jacob Austin, a Chartered Quantity Surveyor with a rich background at construction industry giants Balfour Beatty, Kier, and Vistry Group. With extensive involvement in education, health, and residential projects spanning various scales, from £1000s to over £100M in concurrent developments, Jacob brings a unique perspective. Having collaborated with numerous small businesses, he's now committed to sharing his expertise to drive their success. Join Jacob on his podcast, where he blends his profound insights and personable approach to offer guidance, industry secrets, and inspirational stories.
LinkedIn - www.linkedin.com/in/jacob-austin/
Instagram - www.instagram.com/qs.zone/
www.qs.zone/all-links
In episode 120 of The Subcontractors Blueprint podcast, host Jacob Austin continues the NEC contracts mini-series, providing construction business owners with a comprehensive guide to program clauses under NEC4 subcontracts. He explains the critical requirements for program submission, acceptance, and ongoing updates, highlighting their impact on cash flow, entitlement protection, and project management. Jacob discusses practical strategies for ensuring compliance, avoiding payment penalties, and maintaining control over compensation events. This episode is essential listening for subcontractors seeking to strengthen their NEC4 contract administration and safeguard their business interests.
KEY TAKEAWAYS:
BEST MOMENTS:
“A well-managed program, and an accepted program, is absolutely central to administering the subcontract. It sets out how and when the work will be done.”
“If there’s no current accepted program, the assessment of compensation events may be taken out of your hands—potentially leading to smaller time and cost compensation.”
“By including key dates and requirements in your program, you are creating hooks within your program that the contractor or whoever else is going to snag on if they miss those dates.”
“Acceptance of a program doesn’t stop you from having to achieve any of your obligations, and it doesn’t transfer any risk of those to the contractor.”
“The goal here is to create a program that’s got clear and common reference points for both parties- it allows the contractor to verify the feasibility of your program and to see your needs and your constraints.”
Jacob is on a mission to help the 1 million SME contractors working within the construction industry. If you've taken something of value from this episode, please share the podcast with someone you know, and pass the value on.
HOST BIO: Meet Jacob Austin, a Chartered Quantity Surveyor with a rich background at construction industry giants Balfour Beatty, Kier, and Vistry Group. With extensive involvement in education, health, and residential projects spanning various scales, from £1000s to over £100M in concurrent developments, Jacob brings a unique perspective. Having collaborated with numerous small businesses, he's now committed to sharing his expertise to drive their success. Join Jacob on his podcast, where he blends his profound insights and personable approach to offer guidance, industry secrets, and inspirational stories.
LinkedIn - www.linkedin.com/in/jacob-austin/
Instagram - www.instagram.com/qs.zone/
www.qs.zone/all-links
In episode 119 of The Subcontractors Blueprint podcast, host Jacob Austin continues the NEC contracts mini-series, focusing on key obligations for subcontractors. He explains the importance of acting in a spirit of mutual trust and cooperation, details core responsibilities under the 10, 20, and 40 series clauses—including quality management, design duties, and defect handling—and emphasises proactive communication and collaboration. Jacob also provides practical guidance on defect management, highlighting the impact on client satisfaction and future business. The episode offers clear, actionable advice to help construction business owners protect profitability and maintain strong contractor relationships.
KEY TAKEAWAYS:
BEST MOMENTS:
"The NEC’s core principle is that parties act as stated in the contract and in a spirit of mutual trust and cooperation."
"Mutual trust and cooperation means openness, fairness, and tackling problems together—not hiding bad news or exploiting loopholes."
"Key dates are critical—miss one, and you could be liable for the contractor’s extra costs or delays to other trades."
"A quality management system isn’t optional; you must have documented procedures for inspections, testing, and approvals."
"Defects must be reported and corrected promptly—unfixed defects can lead to deductions or negotiated credits, impacting your reputation and payment."
Jacob is on a mission to help the 1 million SME contractors working within the construction industry. If you've taken something of value from this episode, please share the podcast with someone you know, and pass the value on.
HOST BIO: Meet Jacob Austin, a Chartered Quantity Surveyor with a rich background at construction industry giants Balfour Beatty, Kier, and Vistry Group. With extensive involvement in education, health, and residential projects spanning various scales, from £1000s to over £100M in concurrent developments, Jacob brings a unique perspective. Having collaborated with numerous small businesses, he's now committed to sharing his expertise to drive their success. Join Jacob on his podcast, where he blends his profound insights and personable approach to offer guidance, industry secrets, and inspirational stories.
LinkedIn - www.linkedin.com/in/jacob-austin/
Instagram - www.instagram.com/qs.zone/
www.qs.zone/all-links
In episode 118 of The Subcontractors Blueprint podcast, host Jacob Austin launches a mini-series on the NEC4 suite of contracts, focusing on the engineering and construction subcontract “ECS”. He explains the contract’s structure, main and secondary option clauses, and their impact on risk, pricing, and delivery. Jacob provides a practical checklist to help subcontractors review NEC4 subcontracts, emphasising the importance of understanding triggered clauses, design obligations, liability caps, and payment terms. This episode equips construction business owners with essential knowledge to manage contractual risks, protect profitability, and ensure project success under NEC4.
KEY TAKEAWAYS:
BEST MOMENTS:
“As a subcontractor, you're operating in a framework that talks back to the main contract and feeds in to the main contractor's obligations to their client, so it reduces surprises and mismatches in timescales and obligations.”
“The most collaborative tool within the main contract, the early warning process, is flowed down to you as a subcontractor as well.”
“As you go through the options from A to E, you start with a situation where the subcontractor holds the biggest amount of risk through to option E, where the subcontractor holds the least amount of risk.”
“It would certainly be sensible to discuss before you set off down a road that you both struggle to get to the end of, but you need to understand with this, the option isn't just a letter. It completely changes the feel and the nature of the subcontract.”
“It's important that you appreciate what those letters and numbers mean because when you read the subcontract data for an NEC contract, it will list out all of the option clauses that apply to that particular subcontract.”
Jacob is on a mission to help the 1 million SME contractors working within the construction industry. If you've taken something of value from this episode, please share the podcast with someone you know, and pass the value on.
HOST BIO: Meet Jacob Austin, a Chartered Quantity Surveyor with a rich background at construction industry giants Balfour Beatty, Kier, and Vistry Group. With extensive involvement in education, health, and residential projects spanning various scales, from £1000s to over £100M in concurrent developments, Jacob brings a unique perspective. Having collaborated with numerous small businesses, he's now committed to sharing his expertise to drive their success. Join Jacob on his podcast, where he blends his profound insights and personable approach to offer guidance, industry secrets, and inspirational stories.
LinkedIn - www.linkedin.com/in/jacob-austin/
Instagram - www.instagram.com/qs.zone/
www.qs.zone/all-links
In episode 117 of The Subcontractors Blueprint podcast, host Jacob Austin provides UK construction business owners with a clear, practical overview of the Housing Grants, Construction and Regeneration Act and the Scheme for Construction Contracts. He explains key protections for subcontractors, including rights to interim payments, payment notices, pay less notices, suspension for non-payment, and fast-track dispute resolution through adjudication. Jacob emphasises the importance of written contracts but reassures listeners that statutory rights apply even without one. This episode empowers subcontractors to secure timely payments, maintain healthy cash flow, and confidently handle disputes in the UK construction industry.
KEY TAKEAWAYS:
BEST MOMENTS:
"If the contractor misses that window or fails to issue a valid Payless notice, they can't by law short to pay you. And the law is really clear on that."
"The law says that you can [suspend work for non-payment] without liability, meaning you won't be in breach of contract for stopping work in those circumstances."
"Adjudication can be a game changer for subcontractors because it embodies that pay now, argue later ethos that we mentioned earlier by giving you a way to quickly secure payment or resolve disputes."
"The Construction Act outlaws that, and any provision that makes your payment conditional on receipt of payment from a third party is ineffective."
"Knowing these rules and asserting them at the right time will help you to ensure you get fully paid and on time for the work that you do."
Jacob is on a mission to help the 1 million SME contractors working within the construction industry. If you've taken something of value from this episode, please share the podcast with someone you know, and pass the value on.
HOST BIO: Meet Jacob Austin, a Chartered Quantity Surveyor with a rich background at construction industry giants Balfour Beatty, Kier, and Vistry Group. With extensive involvement in education, health, and residential projects spanning various scales, from £1000s to over £100M in concurrent developments, Jacob brings a unique perspective. Having collaborated with numerous small businesses, he's now committed to sharing his expertise to drive their success. Join Jacob on his podcast, where he blends his profound insights and personable approach to offer guidance, industry secrets, and inspirational stories.