Company Interviews

Company Interviews

Download on the App Store

All Company Interviews episodes

  • New Found Gold (TSX:NFGC) - Graduates to the TSX

    Interview with Keith Boyle, Director & CEO of New Found Gold

    Our previous interview: https://www.cruxinvestor.com/posts/new-found-gold-tsxnfg-construction-still-on-track-10918

    Recording date: 14th August 2026

    New Found Gold's transition from exploration company to emerging Newfoundland gold producer reached a milestone with its move to the TSX main board, a step CEO Keith Boyle frames as recognition of the company's operational progress over the past 18 months. The listing upgrade is intended to widen access to institutional capital and stock indices unavailable on the TSX Venture Exchange, with Boyle noting the company currently splits roughly 60% of trading volume on New York exchanges and 40% on the TSXV, and expects the TSX move to lift Canadian volume without reducing US liquidity.

    Operationally, the company is running a two-track strategy. Hammerdown, a smaller open-pit gold mine acquired as part of the Maritime Resources transaction, is being ramped toward a 20,000-25,000 ounce annual run rate and is expected to be declared in commercial production within months. Boyle was explicit that Hammerdown was never intended to be a major cash generator - its purpose is to cover general and administrative costs and exploration spend, freeing the balance sheet to focus on the larger Queensway project.

    Queensway itself is being built in phases rather than as a single large-scale mill, a decision Boyle said was made specifically to reduce the size of financing required at each stage. Phase one, a 700-tonne-per-day open pit feeding an expanded Pine Cove mill, is fully funded through to first ore delivery - targeted for the fourth quarter of next year - following a $220 million financing announced in April. The company expects production to climb toward 120,000-125,000 ounces annually by 2028 and 175,000-200,000 ounces from 2031, as later, larger phases come online.

    A key near-term catalyst is the forthcoming updated mineral resource estimate and preliminary economic assessment for Queensway. Rather than moving straight to a feasibility study, the company is choosing to publish an updated PEA so investors can see the full multi-phase project, since phases two and three have not yet received enough infill drilling to be classified beyond inferred resources. Phase one, by contrast, has been de-risked through 5-by-5-metre grade control drilling and orders already placed for the mill conversion, which Boyle said supports a feasibility-level capital cost estimate for that portion of the project.

    On exploration, New Found Gold is directing roughly 45% of its expanded 90,000-metre, $40-million-plus 2026 drill programme toward new discovery targets rather than infill - including strike extensions east of the high-grade core, ground picked up along the Appleton Fault from the November Exploits Discovery acquisition, and follow-up drilling at Pulse Pond/Greenwood Pond and Duder Lake. Boyle said per-ounce discovery costs have fallen from roughly $145 for the initial resource to below $100 currently, comparing favourably with M&A-driven ounce additions in the sector, which he put at $500-600 per ounce. For investors, the story combines a funded near-term production ramp with an aggressive, discovery-weighted exploration budget, and the updated Queensway study will be the next major data point to watch.

    View New Found Gold's company profile: https://www.cruxinvestor.com/companies/new-found-gold

    Sign up for Crux Investor: https://cruxinvestor.com

    21 min
  • The New Mining Cycle: Stronger Copper Market, Bigger Gold Projects

    Recording date: 21st August 2026

    Omai Gold Mines emerged as the central focus of Olive Resource Capital’s latest market review after releasing a preliminary economic assessment that highlighted the project’s potential scale. At a gold price of $3,600 per ounce, Omai’s after-tax net present value was estimated at $4 billion, increasing to $5.5 billion at $4,200 gold. The study outlined average annual production of 350,000 ounces over an 18-year mine life, including several years above 400,000 ounces, and $8.1 billion in cumulative undiscounted cash flow. Although the market initially reacted cautiously, Olive argued that investors are still adjusting to the multibillion-dollar capital requirements of large mine developments in a higher-gold-price environment.

    Olive also viewed Prospector Metals’ sharp selloff as a potential opportunity. The company’s shares fell about 40% following early Yukon drill results that did not immediately match the prior year’s standout intercepts. However, only two full holes and part of a third had been reported from a 44-hole program. With the company funded for its drilling campaign and management indicating it had identified a high-grade structural core, Olive added shares at approximately $0.80 to $0.90. The stock subsequently rebounded roughly 25% from its low.

    K92 Mining reported more than US$300 million in quarterly cash flow and reached a net-cash position while advancing its Stage 3 expansion. The company also announced a planned CEO succession, with John Lewins becoming non-executive chairman and internal executive David Medilek taking over as CEO. Olive characterized the change as a continuity move rather than a change in strategy.

    The broader second-quarter reporting season reinforced copper’s growing importance. Copper accounted for more than half of BHP’s EBITDA while being Rio Tinto’s largest contributing group (alongside aluminum and lithium), both firsts. Supply disruptions, constrained inventories and US stockpiling contributed to tighter copper markets. This renewed attention on miners with copper exposure, including DPM Metals, which generated record revenue and free cash flow. Olive was more cautious on Eldorado Gold, arguing that McIlvenna Bay is principally a zinc asset despite being widely described as a copper project.

    Sign up for Crux Investor: https://cruxinvestor.com

    34 min
  • Atomic Eagle (ASX:AEU) - Regains Control of 116.5Mlb Madaouela Uranium Asset

    Interview with Phil Hoskins, CEO of Atomic Eagle

    Our previous interview: https://www.cruxinvestor.com/posts/atomic-eagle-asxaeu-all-known-questions-answered-april-2026-10323

    Recording date: 3rd August 2026

    Atomic Eagle Limited (ASX:AEU | OTCQX:AEUXF) has negotiated the return of its Madaouela Uranium Project in Niger, transforming the company from a single-asset Zambian developer into a dual-asset uranium play with a combined resource base spanning two continents. The deal, agreed in principle after seven months of negotiation with Niger's Ministry of Mines, follows the 2024 expropriation of the project from Atomic Eagle's subsidiary GoviEx Uranium and the international arbitration proceedings that followed.

    The scale differential between the two projects is significant. Madaouela hosts 116.5 million pounds of U3O8 at 1,282ppm - roughly twice Muntanga's resource size and four times its grade - underpinned by more than $160 million of historical expenditure and 600,000 metres of drilling. At current uranium prices, management estimates the project's net present value at approximately $650 million US, with each $5-per-pound price increase adding a further $100 million.

    The commercial terms give Atomic Eagle 60% ownership of a newly formed Nigerien entity, with the government holding 40% - 15% as a standard free-carried interest and up to 25% as a contributory stake that dilutes if unfunded. Near-term cash outlay is limited to $10 million US in staged payments, plus a non-cash offer to carry the government for up to $40 million of its equity contribution. Critically for investors assessing execution risk, operational control - budgets, work programmes, and day-to-day decisions - sits unambiguously with Atomic Eagle, with no unanimous consent requirements from the government side.

    The company now has a two-year window to update feasibility studies, reapply for environmental approvals, and convert the historical NI 43-101 resource estimate into a JORC-compliant figure, targeted for the second half of 2026. With $13.8 million in cash as at 30 June 2026 and a further $16 million potentially available through early option exercises by strategic holders, management believes funding is adequate to meet these near-term obligations without an immediate capital raise.

    Management was explicit that Madaouela is not intended to divert resources or attention from Muntanga, which continues to grow toward a resource approaching 60 million pounds, supported by its own dedicated exploration and study teams. CEO Phil Hoskins framed the valuation opportunity in relative terms: African uranium developers currently trade around $3 a pound, which applied to Atomic Eagle's 60% attributable Madaouela resource implies roughly $210 million Australian in additional value - a figure he suggested could be exceeded given strategic interest already expressed by parties including the White House and major Chinese uranium companies, though he cautioned this depends on Atomic Eagle first demonstrating the deal's credibility to the market.

    Formal signing of the mining convention is imminent. Until then, the agreement remains non-binding, and investors should treat the current terms as indicative rather than final.

    View Atomic Eagle's company profile: https://www.cruxinvestor.com/companies/atomic-eagle

    Sign up for Crux Investor: https://cruxinvestor.com

    30 min
  • Cabral Gold (TSXV:CBR) - Operating Licence Secured, First Gold Targeted by September

    Interview with Alan Carter, President & CEO of Cabral Gold Inc.

    Our previous interview: https://www.cruxinvestor.com/posts/cabral-gold-tsxvcbr-85-built-q4-production-district-growth-ahead-11014

    Recording date: 14th August 2026

    Cabral Gold has reached a pivotal stage in developing its Cuiú Cuiú gold district in Pará State, Brazil, having secured the Operating Licence (LO) needed to begin leaching gold from its first heap leach pad. The licence, granted by the state environmental authority SEMAS/PA, follows the earlier Preliminary Licence and sits alongside a separate approval from Brazilian military authorities covering the purchase and transport of cyanide which both prerequisites for gold recovery under the company's Phase 1 gold-in-oxide operation.

    Construction of the wet processing circuit, the last major piece of the build, is over 90% complete. The ADR plant which is built in Australia and shipped to site has finished mechanical assembly, with electrical work more than 90% done and commissioning under way. The simpler dry circuit, covering ore crushing, agglomeration and stacking, is already commissioned and operating. Ore is being mined, stacked and prepared for irrigation, which CEO Alan Carter expects to begin within days.

    Management's updated timeline puts first gold production in September 2026, around six weeks earlier than originally planned, with full commissioning wrapped up by late September and a ramp-up toward commercial production - defined internally as 60-70% of design throughput - through the fourth quarter. The company has deliberately avoided issuing formal 2026 production guidance given the number of ramp-up variables involved in a first-time mine build, though guidance is likely for 2027.

    Economically, the early mine life looks favourable relative to the broader resource. Infill drilling at the first deposit being mined points to average grades near 1.5 g/t gold over the first 12-18 months, roughly double the 0.7 g/t life-of-mine average, with life-of-mine costs guided at approximately US$1,200 an ounce against a gold price recently around US$4,300 an ounce. Management expects Phase 1 to generate at least US$50 million a year in cash flow once ramped up, which it intends to direct toward repaying a 39-month gold loan (signed in November 2025) and funding an active six-rig exploration programme, rather than raising further equity.

    The larger opportunity, as Carter frames it, is Stage 2: unweathered hard-rock gold beneath the oxide caps now being mined, which he says represents roughly three-quarters of the district's current resource. With six known gold deposits, five confirmed to carry oxide caps, and around 50 untested peripheral targets across the district, management plans to update Cuiú Cuiú's global resource estimate by year-end and, depending on the outcome, potentially advance a preliminary economic assessment on the hard-rock opportunity in the first half of 2027.

    Near-term risks centre on commissioning execution through the wet circuit and the inherent uncertainty of ramping up a new operation, while the current trial mining licence's 500,000-tonne cap - below the 1-million-tonne throughput contemplated in the Pre-Feasibility Study - remains a near-term constraint pending an expected licence upgrade. The project also recorded its first Lost Time Incident during the update period, a non-critical injury, against a Lost Time Injury Rate of 0.34 per 200,000 hours worked.

    View Cabral Gold's company profile: https://www.cruxinvestor.com/companies/cabral-gold

    Sign up for Crux Investor: https://cruxinvestor.com

    19 min
  • Capitan Silver (TSXV:CAPT) - 60,000m Drill Program Targets Large-Scale Potential

    Interview with Alberto Orozco, CEO of Capitan Silver

    Our previous interview: https://www.cruxinvestor.com/posts/capitan-silver-tsxvcapt-60000m-drilling-to-prove-scale-at-cruz-de-plata-9531

    Recording date: 11th August 2026

    Capitan Silver Corp. (TSXV:CAPT) is advancing its Cruz de Plata silver-gold project in Durango, Mexico, through a fully-funded 60,000 metre drill programme in 2026 - a 400% increase over the prior year's campaign and more than double all historic drilling on the property combined. CEO Alberto Orozco told Crux Investor the company is roughly halfway through the programme, with four rigs (one RC, three diamond) now active and the drill rate accelerating as additional rigs have come online through the year.

    The project's most advanced target, the Jesus María trend, has been drilled along a continuous strike length of 2.5 km, part of a broader 3.7 km surface-sampled mineralised trend and a cumulative 21 km of vein structures identified across the consolidated property. Historical and recent drill results include intercepts of up to 1 kg/t silver over two to three metres, within broader zones as wide as 40 m grading 100-300 g/t AgEq. Orozco was clear the project is a primary silver system rather than a base-metals story: silver represents 75-95% of AgEq value depending on location, and a west-to-east metal zonation pattern is being used to vector toward the deeper part of the system.

    Management's stated priority for 2026 is proving scale rather than rushing a resource. Because the current programme is focused on step-out rather than infill drilling, any near-term resource estimate would be classified as inferred. Orozco indicated an internal benchmark of roughly 100 Moz AgEq for a credible first resource, a figure he said the company does not expect to be far from once the current programme concludes, though further drilling would be needed to build density around any initial estimate.

    Financially, Capitan Silver raised C$29 million in late 2025 to fund the expanded programme and reported a market capitalisation of $212.0 million as of August 2026. Over 70% of the share register is tightly held, with no free founder shares and most shares issued at $0.20. Two of the last three financings priced at a premium of more than 30% to market, each led by a new strategic investor, Jupiter Gold & Silver Fund, Michael Gentile and Construplan are the top three shareholders. Management has also contracted to remove all remaining project royalties.

    The company positions Cruz de Plata within the intermediate sulphidation epithermal deposit class responsible for several major Mexican silver discoveries and recent billion-dollar M&A transactions, including Las Chispas, Los Gatos and Juanicipio. Peer-comparison data prepared by Stifel Canada shows Capitan trading at a discount to the average resource-stage peer on both market capitalisation and enterprise value. For investors, the key watch items through the remainder of 2026 are continued assay flow from the deeper, western portion of the Jesus María trend and from newly-permitted step-out targets, with a maiden resource estimate representing a later-stage catalyst rather than a near-term one.

    Learn more: https://cruxinvestor.com/companies/capitan-silver

    Sign up for Crux Investor: https://cruxinvestor.com

    27 min
  • Latin Metals (TSXV:LMS) - Incoming $42M Option for Lacsha Copper-Moly Project in Peru

    Interview with Keith Henderson, President & CEO of Latin Metals

    Our previous interview: https://www.cruxinvestor.com/posts/latin-metals-tsxvlms-the-prospect-generator-model-few-juniors-follow-10250

    Recording date: 14th August 20206

    Latin Metals Inc. (TSXV:LMS) has added a third active partner-funded project to its portfolio with an ongoing agreement with Minsur, a private Peruvian mining company already in a 75/25 joint venture with Newmont on adjacent ground to cover the Lacsha copper-molybdenum porphyry project in southern Peru.

    Under the deal outlined by CEO Keith Henderson, Minsur can earn an initial 75% interest in Lacsha by completing 60,000 metres of drilling over six years and paying Latin Metals approximately $2.5 million in cash, a commitment Henderson estimated at roughly C$40 million in Minsur-funded exploration spending. Once that threshold is met, Minsur holds a time-limited option to acquire the remaining 25% for C$28 million which would leave Latin Metals with a 2% net smelter return royalty. Minsur separately holds a three-year option to buy 1% of that royalty for a further $20 million. Combined, Henderson said, the structure could deliver a little over $42 million in cash coming into the company.

    Latin Metals generated Lacsha internally, spending approximately $900,000 (CAD) on staking, mapping, geochemistry and geophysics before bringing in a partner - notably more than the company's typical $200,000-$300,000 generative budget per project, which Henderson attributed to years of incremental exploration work culminating in a stronger-than-usual technical package. Lacsha's location directly south of Minsur's existing Newmont joint venture ground gives the new partner a clear strategic rationale to test the structural and geochemical extension onto Latin Metals' claims.

    The Lacsha deal brings Latin Metals' total under-contract partner investment to approximately $120 million, spanning Lacsha, Cerro Bayo and La Flora (Daura Gold), and Zaha (Moxico Resources), all funded externally against a corporate budget Henderson described as flat at $3 million per year. Management is targeting further deals across the remaining pipeline including Organullo, Crosby and an Argentine sediment-hosted copper package during 2026, which it expects could push cumulative under-contract investment toward $150-180 million.

    Near-term catalysts sit with the Argentine silver-gold assets rather than Lacsha itself: Daura Gold's Phase II drill programme at Cerro Bayo is scheduled for Q3 2026, alongside the first drill test of the high-grade La Flora vein system, where surface sampling has returned grades as high as 82 g/t gold and 1,239 g/t silver historically. Combined partner-funded drilling across the portfolio is expected to reach approximately 18,000 metres in 2026.

    On financing, Henderson said Latin Metals expects roughly C$1.8 million from warrant exercises in September 2026, with warrants priced at 15 cents against a share price near 25 cents, a gap management is relying on to avoid raising additional equity capital through 2026 and 2027. As with all early-stage option structures, the eventual scale of Lacsha's payoff depends on drill results Latin Metals will not itself control, since the company does not intend to operate the project once Minsur's drilling begins.

    View Latin Metals' company profile: https://www.cruxinvestor.com/companies/latin-metals

    Sign up for Crux Investor: https://cruxinvestor.com

    17 min
  • Electra Battery Materials (NASDAQ:ELBM) - Pioneer Cobalt Refinery Enters Final Construction Stretch

    Interview with Heather Smiles, VP External Affairs & Corporate Development of Electra Battery Materials

    Our previous interview: https://www.cruxinvestor.com/posts/electra-battery-materials-nasdaqelbm-north-americas-first-cobalt-refinery-targets-2027-start-8710

    Recording date: 14th August 2026

    Electra Battery Materials is constructing what will be North America's only battery-grade cobalt sulfate refinery, located in Temiskaming Shores, Ontario. The project addresses a structural gap in the continent's battery supply chain: outside of a single Finnish facility, essentially all cobalt sulfate refining capacity sits in China, leaving North American EV, electronics and defence manufacturers dependent on a supply chain they don't control.

    The company has secured $84 million in financing to fund construction through mechanical completion, targeted for Q2 2027, with commercial production expected later that year. That financing includes $48 million in direct government support across three jurisdictions - the U.S. Department of War, the Canadian federal government, and Ontario - reflecting what management characterises as a broader shift toward governments taking direct financial stakes in strategic midstream infrastructure rather than relying solely on private capital.

    Commercially, the refinery's initial 5,100-tonne annual capacity (expanding to 6,500 tonnes) is anchored by a tolling agreement with LG Energy Solution covering 60% of output. The agreement uses a collar structure, with a floor protecting Electra's margins if cobalt prices fall and a ceiling preventing LG from overpaying in a price spike - management estimates this alone could generate $30-32 million in annual EBITDA at full run-rate. The remaining 40% of capacity is not yet contracted, and management is still weighing how much market exposure to take on for that portion versus locking in further tolling arrangements. Reported expressions of interest for offtake run at roughly 2-3x the refinery's initial nameplate capacity, suggesting more demand than the facility can currently supply.

    Feedstock is secured through supply agreements with Glencore and Eurasian Resources Group, covering material sourced from the Democratic Republic of Congo, which produces roughly 80% of the world's cobalt.

    Beyond the core refinery, Electra is pursuing several growth vectors: an engineering study for a nickel sulfate refinery in the southeastern United States (addressing a similar midstream gap in a second critical mineral), black mass recycling capability, and cobalt-copper exploration assets at the Iron Creek project in Idaho's Cobalt Belt, which management is evaluating as potential future feedstock rather than near-term production.

    Demand-side fundamentals remain supportive: cobalt demand for lithium-ion batteries grew roughly 30% in 2025, driven primarily by EV adoption outside North America, alongside growing demand from consumer electronics and an emerging defence-sector use case. A new U.S. policy requiring domestically produced black mass to remain in-country for one year signals policymaker intent to support onshore refining capacity, though management characterises it as an early, limited step rather than a comprehensive solution.

    View Electra Battery Materials' company profile: https://www.cruxinvestor.com/companies/electra-battery-metals

    Sign up for Crux Investor: https://cruxinvestor.com

    33 min
  • Namibia Critical Metals (TSXV:NMI) - Partnership and $23M Earn-In Secured for Lofdal HREE Project

    Interview with Darrin Campbell, President & CEO of Namibia Critical Metals Inc.

    Our previous interview: https://www.cruxinvestor.com/posts/namibia-critical-metals-tsxvnmi-japan-backed-path-to-dfs-in-q2-2027-9891

    Recording date: 13th August 2026

    Namibia Critical Metals (TSXV:NMI) has reached a pivotal moment in the development of its Lofdal Heavy Rare Earth Project in Namibia. In July 2026, the Japan Organization for Metals and Energy Security (JOGMEC) and Toyota Tsusho Corporation completed a C$23 million earn-in commitment, roughly 18 months ahead of the original March 2028 schedule, securing a combined 50% participating interest in the project. The two partners formed TJ Namibia Rare Earths Corporation (TJNREC) to hold that interest, and JOGMEC has separately committed up to C$47.668 million (approximately ¥5.5 billion) to capitalise the new entity, funding Lofdal through Definitive Feasibility Study completion and toward a Final Investment Decision.

    Critically, all project funding from this point forward is structured as non-interest-bearing, non-dilutive Pre-FID Capital Funding - a mechanism CEO Darrin Campbell described as a temporary free carry that removes near-term financing risk without forcing Namibia Critical Metals to make a dilution decision until FID itself. The company retains the option to participate at up to 45% ownership or dilute to a carried floor of 21%, with management signalling a preference to retain maximum exposure given the project's economics.

    The economics, laid out in a December 2025 PFS, show a 13-year mine life producing 2,000 tonnes of total rare earth oxide annually, including significant dysprosium, terbium and yttrium output. A base case using moderate pricing generates a $275 million after-tax NPV and 19% IRR on $348 million of capex; a divergent case reflecting the elevated non-Chinese pricing seen over the past 18 months delivers a $748 million after-tax NPV and 35% IRR. Campbell noted current market conditions increasingly resemble the divergent scenario.

    Technical work continues in parallel. A 13,000-metre, 83-hole drill programme launched in June 2026 is targeting a maiden resource at the Area 5 xenotime system, the project's first deep test hole at Area 4 to approximately 800 metres for underground mining studies, and infill drilling at Area 2B. SGS has been awarded pilot-scale flotation and hydrometallurgical testwork contracts aimed at producing separated - rather than mixed - light and heavy rare earth products, which Campbell said better matches offtaker demand. A DFS completion target of Q3 2027 is intended to lead into an FID shortly after.

    Despite this de-risking and the depth of sovereign-industrial backing, Campbell argues the market continues to price Lofdal as an early-stage exploration story, at roughly 0.15-0.2x price-to-NAV versus 0.4-0.8x for comparable PFS/DFS-stage peers. He attributes the gap to thin liquidity, minimal institutional coverage as the company has not needed to raise meaningful capital in six years due to JOGMEC funding, and market confusion over the earn-in's dilution mechanics. Final offtake pricing terms with the Japanese consortium remain under negotiation, representing a further catalyst to watch as the project approaches FID.

    View Namibia Critical Metals' company profile: https://www.cruxinvestor.com/companies/namibia-critical-metals-inc

    Sign up for Crux Investor: https://cruxinvestor.com

    23 min
  • Canada Nickel (TSXV:CNC) - Federal Approval + C$21 Million Funding for Crawford Project

    Interview with Mark Selby, CEO of Canada Nickel

    Our previous interview: https://www.cruxinvestor.com/posts/nickels-next-chapter-tight-supply-steady-demand-and-higher-price-floors-11311

    Recording date: 13th August 2026

    Canada Nickel Company Inc. (TSXV:CNC) has reached a milestone that few Canadian mining developers achieve: a positive federal decision statement for its 100%-owned Crawford Nickel-Cobalt Sulphide Project, the first project to complete Canada's Impact Assessment Act process from application through to decision since the legislation came into force in 2019. CEO Mark Selby frames the approval as a de-risking event on three fronts: it differentiates Crawford from peer projects still mid-permitting when courting strategic partners; it removes a major source of hesitation for larger institutional investors who had been waiting on permitting clarity; and it strengthens Canada Nickel's standing with government funding bodies already engaging with the company.

    That standing is reflected in Crawford's selection as one of five projects referred to the federal Major Projects Office, the earliest-stage project among that group, and as one of three projects named to Ontario's One Project, One Process fast-track framework, alongside a Thunder Bay lithium project and Kinross's Great Bear gold project.

    On financing, Selby laid out a capital stack in which government-linked sources do much of the heavy lifting. Of the approximately $1 billion in equity Canada Nickel needs to build Crawford, $600 million is covered by refundable investment tax credits, and a further $100 million comes from a Samsung commitment. The company is working with Scotiabank and Deutsche Bank on an additional $100-200 million through a further project stake sale or structured offtake financing. On the debt side, a letter of intent from Export Development Canada is progressing toward a term sheet, backed by four years of dialogue with global export credit agencies, and a roughly two-month-old mandate with Scandinavian bank SB1 Markets is intended to produce a bridge facility that draws on tax credits during construction rather than after.

    The company closed a $20 million financing overnight ahead of this interview, taken up entirely by a single family office, and separately upsized a non-brokered private placement on  from C$15.0 million to up to C$21 million in gross proceeds, scheduled to close around August 28, 2026. Selby flagged further financing initiatives expected in October and November 2026.

    With funding in hand, Canada Nickel is moving into detailed engineering and long-lead procurement, targeting a construction decision by mid-2027 and breaking ground by the end of that year, a schedule that has slipped from the year-end 2026 target in Crux's earlier coverage. Seasonal construction constraints in the Abitibi region mean any further delay risks pushing activity into the following year's window.

    Beyond Crawford, Selby pointed to the Reid Nickel Sulphide Project, roughly 39 kilometres northwest of Timmins, where August 2026 drilling returned the highest-grade intervals reported to date: 1.01% nickel over 4.5 metres within a broader 576.6-metre interval averaging 0.29% nickel. Reid's current resource stands at 0.87 billion Indicated tonnes and 1.45 billion Inferred tonnes, part of what Selby describes as a wider Timmins Nickel District pipeline behind Crawford.

    View Canada Nickel's company profile: https://www.cruxinvestor.com/companies/canada-nickel

    Sign up for Crux Investor: https://cruxinvestor.com

    17 min
  • Asante Gold (CSE:ASE) - 4.6 Moz Gold Resource Base Anchors Disciplined 2026 Production

    Interview with Campbell Baird, CEO of Asante Gold

    Recording date: 13th August 2026

    Asante Gold Corporation is working through an operational and leadership reset four months into Campbell Baird's tenure as Acting CEO, following the retirement of predecessor Dave Anthony. The company's investment case for 2026 hinges less on new catalysts than on execution against an already-disclosed plan: converting roughly $50 million of deferred or cancelled capital expenditure, combined with a narrower project focus, into the guided 275,000-300,000 ounce production range at an AISC of $3,200-$3,600 per ounce for the full year.

    The two operating assets are pulling in different directions operationally. Chirano has provided stability throughout 2026, delivering a consistent 10,000-11,000 ounces monthly even as Bibiani absorbed the impact of a January wall slip and an extended, costly stripping campaign in its Main Pit. Bibiani's ore has also proven more sulfidic than originally modelled, prompting a shift toward roughly 50% flotation processing and a sulfide recovery plant now being tied into the wider circuit - a process Baird estimated was roughly two months from completion.

    The key catalyst for H2 2026 performance is grade: Bibiani's head grade is expected to move from approximately 1.3-1.4 g/t over the past six months toward a targeted 1.7-1.8 g/t as mining progresses deeper into the Main Pit, directly underpinning the guided cost reduction weighted to Q4.

    On the resource side, Asante's 5 August NI 43-101 update showed combined Measured and Indicated Resources of 4.6 million ounces across both operations - effectively flat against December 2023 levels despite more than 430,000 ounces of production in the interim. Chirano's resource base grew materially (+443,000 ounces M&I since December 2023), supporting a seven-year mine life, while Bibiani's declined 17% on constrained exploration spend and open-pit depletion, even as its Main Pit is interpreted as geologically open to roughly 1,400 metres against only ~600 metres of current definition. The company frames the broader 80-kilometre Chirano-Bibiani Corridor as structurally comparable to far larger, more extensively drilled greenstone belts (Lefroy-Boulder, Abitibi), with a $23.4 million exploration budget allocated for 2026.

    On costs, management's own framing is notably conservative: Baird explicitly ruled out sub-$2,000/oz AISC as a credible near-term outcome, targeting below $3,000/oz only as a longer-term objective. This tempers what might otherwise be an overly optimistic reading of the company's cost trajectory, and is worth weighing against the wider sector-level cost inflation (diesel, labour, supply chain) that Baird cited as affecting gold producers broadly, not just Asante.

    The clearest risk flag for investors is guidance continuity: Asante's prior annual production target of 400,000-500,000 ounces remains formally withdrawn, with management stating directly it is not planning to reinstate it. The 275,000-300,000 ounce 2026 range should be treated as the only current, company-sanctioned figure.

    View Asante Gold's company profile: https://www.cruxinvestor.com/companies/asante-gold

    Sign up for Crux Investor: https://cruxinvestor.com

    29 min