Interview with Alan Carter, President and CEO, Cabral Gold
Our previous interview: https://www.cruxinvestor.com/posts/cabral-gold-tsxvcbr-phase-one-heap-leach-on-schedule-q4-production-targeted-10682
Recording date: 14th July 2026
Cabral Gold is nearing a key milestone as it transitions from an exploration-focused company to a gold producer, with mining and ore stacking now underway at its Cuiú Cuiú gold-in-oxide project in Brazil. The activity forms part of the commissioning process for the Phase 1 heap leach operation, which is approximately 85% complete. Commercial gold production remains on track for the fourth quarter of 2026.
The project is designed to process oxidized surface material using a low-cost heap leach method that avoids drilling, blasting, and complex milling. Ore from the MG deposit is currently being mined, sized, agglomerated, and stacked on leach pads, marking significant progress toward initial gold output. The remaining step before full production is commissioning the wet circuit, which will recover gold from solution.
A key component of this process is the adsorption-desorption-recovery (ADR) plant, recently shipped from Australia and expected to arrive on site in late July 2026. Once installed, it will enable final commissioning stages through the third quarter. While initial gold production may begin earlier, Cabral has emphasized that commercial production will be declared only once steady-state output is achieved.
Financially, the project remains aligned with the 2025 pre-feasibility study, including an estimated all-in sustaining cost of around $1,200 per ounce, offering strong margins even amid softer gold prices. The company is also evaluating a potential expansion of Phase 1, with further details expected soon.
Meanwhile, exploration continues across the district, where Cabral is now modeling six deposits, double the previous estimate. With six drill rigs active and an updated resource estimate expected by year-end 2026, the company is positioning itself for both near-term cash flow and long-term growth.
Learn more: https://www.cruxinvestor.com/companies/cabral-gold
Sign up for Crux Investor: https://cruxinvestor.com
Recording date: 11th July 2026
Olive Resource Capital delivered an approximate 15% return in the first half of 2026, outperforming many peers in a more moderate market environment compared to the strong gains of 2025. Returns were further supported by three portfolio company acquisitions, two of which closed the period, highlighting the role of opportunistic corporate activity in performance. The firm emphasized that such events are beneficial but not a reliable foundation for long-term strategy.
The commodity landscape in H1 2026 was marked by a clear rotation. Lithium and oil emerged as the strongest performers, with oil remaining resilient despite price volatility and lithium rebounding after years of underinvestment. In contrast, gold, silver, and platinum group metals lagged after leading the previous year, undergoing what management described as a necessary consolidation phase.
Despite weak underlying commodity prices, Olive’s strongest gains came from precious metals equities. This divergence reflects the firm’s focus on company-specific catalysts—such as mergers and acquisitions, resource updates, and technical studies—rather than direct exposure to commodity price movements. Holdings like K92 Mining exemplify this strategy, with growth-driven revaluation potential independent of gold price trends.
Macroeconomic conditions remained broadly supportive, with strong global manufacturing activity and continued monetary stimulus, although reduced liquidity support from China is being monitored. Geopolitical tensions, including those involving Iran, influenced energy markets but were viewed as temporary disruptions with longer-term implications for supply chains and energy demand.
Heading into the second half of 2026, the firm is cautiously deploying elevated cash reserves into energy and uranium, driven by themes such as AI-related power demand, electrification, and favorable seasonal trends. It continues to avoid West African development projects due to rising jurisdictional risks, instead favoring opportunities in North and South America where regulatory conditions are more stable and investment visibility is stronger.
Sign up for Crux Investor: https://cruxinvestor.com
Interview with Stephen Gray, President & CEO of Fox Tungsten
Recording date: 11th July 2026
Fox Tungsten is advancing its high-grade Fox project in southern British Columbia, aiming to position it as a rare North American source of tungsten amid tightening global supply. The deposit averages roughly 1% tungsten, which management equates to about 20 grams per tonne gold or 25% copper at current prices, placing it among the higher-grade tungsten projects globally. However, its current resource of just over 1 million tonnes is considered too small to support economic development, prompting an aggressive 20,000-metre drilling campaign in 2026.
The ongoing program, supported by two active rigs, focuses primarily on infill drilling between three known zones to expand the resource toward a target of approximately 3 million tonnes—seen as the minimum scale required for a Preliminary Economic Assessment (PEA). A smaller portion of drilling will test deeper extensions of the deposit for potential underground development, marking the first step toward longer-term growth.
Metallurgical testing indicates a relatively simple processing route, with gravity separation achieving about 75% recovery into a high-grade tungsten concentrate exceeding 60%. The ore is also considered environmentally favorable, lacking harmful elements and unlikely to generate acid. Additional flotation testing is planned to potentially improve recovery further.
Infrastructure advantages strengthen the project’s outlook, including road access, proximity to regional services, and an existing power line. The company is well-funded, with approximately C$15 million in working capital following a recent financing, sufficient to complete drilling and advance toward a PEA expected in 2027.
Fox Tungsten’s strategy is supported by strong market dynamics. Tungsten prices have risen sharply due to both geopolitical pressures—particularly Chinese export constraints—and a broader structural supply deficit. With no active tungsten mines in North America, the Fox project could play a key role in diversifying supply if development progresses as planned.
Sign up for Crux Investor: https://cruxinvestor.com
Interview with Paul Lock, Chairman & MD of Flagship Minerals
Our previous interview: https://www.cruxinvestor.com/posts/flagship-minerals-asxflg-fast-tracks-isidora-project-to-21m-oz-gold-milestone-10307
Recording date: 9th July 2026
Flagship Minerals has repositioned itself as a focused gold and copper explorer, combining advancement of its flagship Isidora Gold Project in Chile with the acquisition of the Whipsaw Copper Project in British Columbia. The strategic shift is reinforced by the divestment of its RK Lithium Project for US$4 million, providing non-dilutive funding while simplifying the company’s commodity exposure.
At the core of Flagship’s portfolio is the 2.1 million ounce Isidora project, where recent metallurgical drilling and trenching have been completed. The company is now progressing infill and extension drilling aimed at upgrading and expanding the resource, with an updated estimate targeted for late 2026 or early 2027. Parallel workstreams—including metallurgical testing, environmental studies, and water solution assessments, are feeding into a prefeasibility study expected in early 2027. Management believes Isidora remains significantly undervalued compared to peers, attributing the gap primarily to investor concerns around potential equity dilution rather than asset quality.
The newly acquired Whipsaw Copper Project introduces large-scale copper optionality in a Tier-1 jurisdiction. Located near an operating mine in British Columbia, Whipsaw hosts a substantial exploration target of up to 1.02 billion tonnes at 0.2–0.4% copper equivalent. Importantly, the deal is structured with deferred payments and no minimum exploration spend, allowing Flagship to manage capital efficiently. The company is evaluating whether to advance drilling or spin out the asset into a separate listed vehicle, offering flexibility in how value is realized.
Flagship’s broader strategy reflects a shift among junior miners toward multi-asset, multi-commodity portfolios that reduce reliance on a single project. With near-term catalysts at Isidora and strategic options at Whipsaw, the company aims to deliver growth, diversification, and a clearer pathway toward development without excessive shareholder dilution.
View Flagship Minerals' company profile: https://www.cruxinvestor.com/companies/flagship-minerals
Sign up for Crux Investor: https://cruxinvestor.com
Interview with Craig Hallworth, President & CEO of Gunnison Copper
Our previous interview: https://www.cruxinvestor.com/posts/gunnison-copper-tsxgcu-new-pea-with-18-24-month-pfs-timeline-9611
Recording date: 8th July 2026
Gunnison Copper is positioning itself as a rising U.S. copper producer under new CEO Craig Hallworth, who recently stepped up from CFO following a leadership transition. The company has rapidly advanced its operations, bringing the Johnson Camp mine in Arizona into production within 18 months and using that momentum to progress its much larger flagship Gunnison project, which could supply up to 10% of current U.S. refined copper demand.
A major priority has been financial restructuring. Gunnison successfully eliminated legacy secured debt in early 2026 and settled convertible debentures at a significant discount, strengthening its balance sheet and improving investor confidence. Institutional ownership has grown substantially, reflecting increased market credibility.
Operationally, Johnson Camp is already producing copper cathode using Rio Tinto’s Nuton leaching technology, with output sold domestically, including to Amazon Web Services. The project has also qualified for U.S. federal tax credits and may benefit from additional state-level incentives.
The flagship Gunnison project presents compelling economics, with an estimated after-tax value of nearly $2 billion and a 22.5% internal rate of return. Despite this, the company trades at a steep discount to peers. Management attributes this gap to its earlier-stage development status and sees significant upside as permitting, drilling, and feasibility work advance.
A key differentiator is Gunnison’s integrated acid plant strategy, designed to mitigate supply chain risks and reduce reliance on imported sulfuric acid. Combined with an already-permitted site and low litigation risk, this supports a streamlined development pathway.
With a large-scale drilling program underway and ongoing metallurgical testing, Gunnison aims to expand its resource base and attract a strategic partner ahead of a targeted construction decision by mid-2028, aligning with growing U.S. demand for domestically sourced critical minerals.
View Gunnison Copper's company profile: https://www.cruxinvestor.com/companies/gunnison-copper
Sign up for Crux Investor: https://cruxinvestor.com
Panel Interview with
Michael Hodgson, CEO of Serabi Gold PLC
Alan Carter, President & CEO of Cabral Gold Inc.
Thiago Diniz, VP Exploration of ValOre Metals
Recording date: 7th July 2026
Brazil is emerging as an increasingly attractive mining jurisdiction, according to executives from Serabi Gold, Cabral Gold, and ValOre Metals, who discussed the country’s regulatory environment, infrastructure, and investment climate. While Brazil’s federal mining framework is widely viewed as stable and predictable, challenges persist at the state level, particularly in newer mining regions such as Pará. There, under-resourced agencies often delay permitting, leading companies to rely on temporary “guia” licenses to maintain project timelines.
Despite these bottlenecks, investor sentiment toward Brazil has improved significantly. What was once considered a “Brazil discount” in mining valuations has, according to industry leaders, shifted to a “Brazil premium.” This change is driven by strong gold prices, increased participation from major global miners such as Vale, BHP, and Anglo American, and growing access to both institutional and retail capital. Brazil’s mining sector also plays a major economic role, contributing billions in revenue and exports.
Infrastructure development has further strengthened the investment case. In the Tapajós region, new highways have reduced costs, connected mine sites, and improved community relations by generating local economic benefits. However, success in Brazil depends heavily on early and sustained engagement with state regulators and local stakeholders, as these relationships often determine permitting outcomes more than federal involvement.
Operationally, companies report a generally capable domestic workforce, though specialized skills and imported equipment can present constraints. Meanwhile, Brazil’s geological potential remains underexplored, with only about 30% of the country mapped in detail.
Looking ahead, Serabi aims to double gold production, Cabral is advancing toward first production in 2026 with active drilling, and ValOre is progressing toward a preliminary economic assessment while pursuing acquisitions. Overall, Brazil is increasingly viewed as a competitive and promising destination for mining investment.
Sign up for Crux Investor: https://cruxinvestor.com
Interview with Nicholas Holthouse, MD of Mont Royal Resources
Our previous interview: https://www.cruxinvestor.com/posts/mont-royal-resources-asxmrz-ashram-pea-nears-as-capex-slashed-50-and-fluorspar-upside-emerges-10160
Recording date: 8th July 2026
Mont Royal Resources Limited (ASX:MRZ, TSXV:MRZL) has used the past month to substantiate its case as a scale rare earths developer positioned to help address Western critical minerals supply gaps. The centrepiece is an updated Preliminary Economic Assessment for the company's 100%-owned Ashram Rare Earths and Fluorspar Project in Nunavik, Québec, released and followed by the formal NI 43-101 Technical Report required under Canadian disclosure rules.
The updated PEA confirms Ashram as a 30-year, large-scale development. On a post-tax basis, the project delivers an NPV8 of C$2.03 billion, an IRR of 22.0%, and payback of 3.9 years from the start of production; pre-tax figures are stronger, at C$3.44 billion NPV8 and 25.6% IRR. Life-of-mine revenue is forecast at C$24.6 billion, with EBITDA of C$15.5 billion (a 62.7% margin), driven by average annual production of approximately 17,466 tonnes of saleable rare earth oxide, including roughly 4,035 tonnes of NdPr oxide. Initial capital expenditure is estimated at C$1.23 billion, including a 30% contingency, with the Company also anticipating C$342 million in refundable Clean Technology Manufacturing tax credits.
The updated Mineral Resource Estimate totals 204.3Mt (73.2Mt Indicated at 1.89% TREO and 131.1Mt Inferred at 1.91% TREO), with the mine plan drawing on only around 25% of that base over its 30-year life leaving room for future expansion, including the currently excluded BD-Zone. NdPr, the primary magnet metal pairing, represents approximately 21% of the resource's total rare earth oxide content, a distribution that positions Ashram to supply the higher-value end of the rare earth basket into markets forecast to grow at 8-12% annually through 2050.
Beyond the economic study, Mont Royal is managing two other active workstreams. First, the company acknowledged an independent, Nation-led initiative from the Naskapi Nation of Kawawachikamach to evaluate potential regional access corridor options, a process Mont Royal says it respects but does not control, running in parallel to its own engagement with Inuit, Naskapi and Innu communities on Ashram-related infrastructure. Second, the company's 75%-owned Northern Lights Minerals project is undergoing a helicopter-supported gold till-sampling survey across the Chateaufort Property, targeting ground directly along strike from Benz Mining's 1,005,000oz Eastmain gold deposit, with preliminary data expected in August 2026 and a full report in Q3.
For investors, the key considerations are straightforward. On the positive side: a resource base and NdPr distribution that stack up well against global peers, PEA economics that clear the bar for progression to Pre-Feasibility Study, and access to Canadian government funding support, including the anticipated tax credit allocation. On the risk side: the PEA carries a ±50% accuracy range typical of scoping-level studies, no off-take agreements or committed financing are yet in place against the roughly C$1.23 billion initial capital requirement, and the assumed third-party access-road cost model has not yet been formalised into an infrastructure agreement. Permitting is expected to take several years given the project's location within federally and provincially regulated territory under the James Bay and Northern Québec Agreement.
The Company has targeted the second half of 2026 for the start of Pre-Feasibility Study work, alongside continued permitting, environmental baseline studies, and strategic partnership discussions as the next set of milestones to track.
View Mont Royal Resources' company profile: https://www.cruxinvestor.com/companies/mont-royal-resources
Sign up for Crux Investor: https://cruxinvestor.com
Interview with Nolan Peterson, CEO of Atlas Salt
Our previous interview: https://www.cruxinvestor.com/posts/atlas-salt-tsxvsalt-no-competitors-lowest-cost-producer-a-mining-story-built-for-certainty-10812
Recording date: 8th July 2026
Atlas Salt has advanced its Great Atlantic Salt Project in Newfoundland from pre-development into active construction, marking a key milestone for the company. Since construction began in February, work has shifted to feasibility-study-funded capital expenditures, meaning current activities are part of the permanent mine infrastructure rather than preparatory steps. Backed by recent financing, the company has maintained steady progress through the 2026 construction season.
Early-stage work has focused on site clearing, overburden removal and storage, subgrade preparation, and initial road and drainage infrastructure. These efforts are designed as long-term assets for the project. The next major milestone, excavation of the box cut and development of a 1.5-kilometre underground drift, is still several months away and will be critical in determining the project’s technical performance.
Initial geotechnical observations have been encouraging, with ground conditions appearing drier and more stable than expected. If confirmed, these conditions could reduce both construction time and capital costs, though further testing during drift development will be necessary to validate these early findings.
On the regulatory side, Atlas Salt has secured permits covering over $150 million in early works. In addition, local authorities have shifted to a streamlined permitting approach aligned with provincial approvals, reducing administrative complexity and signaling strong regional support.
The project aims to produce 4 million tonnes of de-icing road salt annually, targeting undersupplied markets in the northeastern United States, eastern Canada, and Atlantic Canada. Execution is supported by an experienced in-house team and engineering partner Hatch, with a phased staffing strategy intended to reduce risk during peak construction.
Overall, Atlas Salt’s transition into active construction, combined with favorable early conditions and improved permitting, positions the project for continued advancement toward full-scale production.
View Atlas Salt's company profile: https://www.cruxinvestor.com/companies/atlas-salt
Sign up for Crux Investor: https://cruxinvestor.com
Interview with Darren Bowden, CEO of Metals Exploration PLC
Our previous interview: https://www.cruxinvestor.com/posts/metals-exploration-lsemtl-doubling-gold-output-as-build-on-track-on-budget-9180
Recording date: 8th July 2026
Metals Exploration (LSE:MTL) presents a self-funded gold development story entering its most consequential phase, with a newly acquired copper optionality layered on top. The company's flagship growth asset, La India in Nicaragua, is roughly 50% built and remains on schedule for first gold production in December 2026. CEO Darren Bowden confirmed that a previously flagged risk, the power transmission to the construction site, has now been substantially resolved through a revised delivery arrangement with the Nicaraguan government, under which the state handles design and the company handles construction.
Construction progress is tangible: front-end processing infrastructure is complete, the CIL tanks are half-erected, and both mills are currently being installed. Some equipment deliveries such as an elution circuit from Australia and high-voltage cabling have slipped by a few weeks, but management maintains that the December 2026 target is intact, aided by a stockpiling strategy designed to bank four to five months of processing feed ahead of commissioning.
The build is being funded entirely from Runruno's operating cashflow. The Philippines-based mine delivered record FY2025 results - $208.4 million in revenue and $115.3 million in free cashflow - leaving the company debt-free. FY2026 Runruno guidance of 40,000-48,000oz represents a step down from FY2025's 65,287oz, reflecting the mine's advancing age rather than any operational issue, as La India is designed to take over as the group's primary cashflow generator from late 2026.
La India's underlying economics remain strong: a pre-tax NPV6 of $882 million at $2,500/oz gold (rising to $1,378 million at $4,000/oz), targeting 145,000oz of annual production over a mine life of 12-plus years, at an initial capital intensity of $1,138/oz - the lowest among the development-stage peer group Crux tracks for comparison.
Layered on top of this near-term gold catalyst is a newly signed set of agreements over the Batong Buhay copper-gold porphyry project in the Philippines, announced 15 June 2026. The 440-hectare licence hosts two historically drill-tested porphyry systems and a high-sulphidation gold vein system, with a historical (non-JORC) resource at the Dickson porphyry of 86.9 million tonnes at 0.60% copper and 0.25 g/t gold. Crucially, the licence sits with the state-owned Philippine Mining Development Corporation, which satisfies local ownership requirements automatically and gives the project government backing that makes it a very different prospect. Initial exploration is underway, with a drill programme targeted for H2 2026.
For investors, the near-term case rests on execution through La India's remaining construction and commissioning phases - watch particularly for confirmation of the final capital figure, which has moved slightly across recent company materials - alongside early drill results from Batong Buhay and the company's existing Abra and Cacao exploration targets, both expected in H2 2026.
View Metals Exploration's company profile: https://www.cruxinvestor.com/companies/metals-exploration-plc
Sign up for Crux Investor: https://cruxinvestor.com
Interview with Blaine Monaghan, President & CEO of Pacific Ridge Exploration Ltd.
Our previous interview: https://www.cruxinvestor.com/posts/pacific-ridge-exploration-tsxvpex-2026-drilling-campaign-eyes-500-mt-resource-expansion-9972
Recording date: 8th July 2026
Pacific Ridge Exploration Ltd. (TSXV:PEX) closed the final tranche of an C$8.5 million financing and in doing so secured its largest corporate strategic shareholder: Peruvian mining group Minsur S.A., which through its subsidiary Cumbres del Sur now holds approximately 13.8% of the company. For a junior explorer that has spent recent years working to close a persistent valuation gap with peers, this is a meaningful development heading into the 2026 field season.
The financing directly funds Pacific Ridge's 2026 exploration programme: approximately 2,500 metres of drilling each at the flagship Kliyul copper-gold project and the RDP copper-gold project, both located in British Columbia's Toodoggone district. Mobilisation is underway, with drilling expected to begin by late July and a second rig arriving mid-August to accelerate the Kliyul programme.
At Kliyul, Pacific Ridge already holds a maiden resource of 334 million tonnes at 0.33% copper equivalent - roughly 2.42 billion pounds of copper equivalent, or 5.7 million ounces of gold equivalent. Rather than simply expanding this resource, management is directing drilling toward three untested porphyry targets along a 6-kilometre mineralised trend, starting with the M39 target in the property's southeast corner. Only three of the roughly 36 holes drilled at Kliyul to date have tested ground outside the existing main zone, leaving significant untested potential. Management's rationale is straightforward: nearby discoveries at Amarc Resources' Freeport-backed JOY district and Kingfisher Metals' HWY 37 project in the Golden Triangle have both driven multi-fold share price re-ratings, and a fresh discovery is seen as more likely to move Pacific Ridge's valuation than incremental tonnage growth.
At RDP, the 2026 programme is concentrated on testing an interpreted porphyry centre nestled between two known mineralised magnetic lobes, the same zone that Minsur specifically negotiated technical access rights to as part of its investment. CEO Blaine Monaghan has described RDP's grades as among the highest-grade porphyry copper-gold mineralisation seen in the province, distinguishing it from the larger but lower-grade Kliyul resource.
Minsur's investment carries structural significance beyond the capital itself. The company has been granted an investor rights agreement covering participation and top-up rights in future financings, along with a nine-month right of first refusal to acquire the RDP project and an agreement to negotiate a potential strategic transaction in good faith. This creates a defined, time-bound window in which Minsur can act on this season's drilling results - a specific catalyst investors can track rather than an open-ended thesis.
With more than C$9 million now in treasury and a share count that has grown from roughly 63 million to approximately 97 million following the raise, management argues the company's dilution overhang is largely behind it, pointing to roughly 160 million shares traded since September 2025 as evidence that legacy sellers have been substantially absorbed. Separately, Pacific Ridge's Yukon gold properties, Mariposa and Eureka Dome, remain under a non-dilutive option to Labrador Gold Corp, adding optionality without competing for Pacific Ridge's own exploration capital this season.