The South Deep gold mine west of Johannesburg, which is already benefits 50 MW of solar power commissioned last year, is poised to be boosted by another 50 MW to 80 MW of wind power going forward.
"We're busy with the wind study to put up those turbines. We're having very positive results on the tower that we put up," interim Gold Fields CEO Martin Preece told Mining Weekly during a media briefing following the company's release of quarter-three operational results.
Third-quarter production was 542 000 oz of gold at an all-in sustaining cost (AISC) of $1 381/oz and an all-in cost (AIC) of $1 622 oz. Third-quarter AISC of $1 381/oz was 30% higher year-on-year and 8% higher quarter-on-quarter.
The Johannesburg- and New York-listed company remains on track to meet the original production and cost guidance provided in February 2023, both at guided and forecast exchange rates. Attributable gold equivalent production is expected to be between 2.25-million ounces and 2.3-million ounces, compared with 2.32-million ounces in 2022. AIC is expected to be $1 480/oz to $1 520/oz.
Regarding South Deep's wind energy facility, a mast was erected to measure wind, bird life and bat life.
"We are currently busy with the environmental permitting for the wind facility. That should be close to completion in the second quarter of next year," said Preece.
At the same time, the renewable energy team working on where best to position the wind turbines along with their engineering design and final costing.
"We intend to make sensible arguments about advancing the wind project and taking it to the board for approval next year," Preece added.
Provision has been made in Gold Fields' long-term costing for the wind facility.
"We haven't arrived at the exact number of wind megawatts yet for South Deep but
we're most probably going to generate somewhere between 50 MW and 80 MW," Preece said in response to Mining Weekly during a media briefing following the company's release of quarter-three operational results.
In Australia, additional solar has been approved at Gold Fields' Granny Smith and Agnew mines, while a comprehensive study is being finalised to take the St Ives mine to 72% renewables.
The St Ives proposal will be presented to the board before year-end for the approval of a $200-million-plus investment, to be spent over a period of 2024 and 2025.
In Canada, a fully renewable hydropower electricity allocation has been allocated by Quebec Power for the Windfall project, where powerline construction to the mine is about 80% complete.
"Early next year, we should be able to switch Windfall on to a renewable source of electricity from hydroelectricity," said Preece.
Gold Fields is partnering Osisko Mining to develop Windfall, where third-quarter pre-construction has rep an expenditure of $25-million.
In Chile, an environmental impact assessment has been approved for solar power at the Salares Norte project, where more renewables study work is needed, "but I think it's more important right now that we get the mills turning and some gold coming out the backend at Salares rather than losing focus with solar panels".
COLLEAGUES FROM GHANA MOVING TO AUSTRALIA
On skills shortages in Australia and South Africa, Preece said the Western Australian government was reducing entry requirements and making it easier for Gold Fields to get expatriates into the country.
"The challenge in Western Australia is a little bit different to what we find at South Deep in that there's basically 97% employment in Western Australia and that 3% unemployment is not made up of people looking for jobs.
"It's made up of people who either can't work or don't need to work. The job market doesn't have surplus skills. You've got big infrastructure spend in the cities, which is attracting mining people because they know that they can go home every night.
"Then, you're also competing with the big bulk miners who so...