A multi-phased development approach is being adopted at the Karo Platinum project in Zimbabwe, where a 17-year opencast mine is to be built with a timeline to deliver its first ore to mill in July 2024.
“In July 2024, we will put the first ore in mill,” Karo Mining Holdings MD Bernard Pryor told a project update presentation covered by Mining Weekly. (Also watch attached Creamer Media video.)
Land has been allocated for a 300 MW solar plant to serve the project, the 12-month design and construction period for which began on July 1.
The updated output is scheduled at 194 000 oz a year, which puts the project in line with Anglo American Platinum’s Unki mine, also on Zimbabwe’s Great Dyke.
Total cost to first ore in mill is estimated at $391-million, with $20-million spent to date and with Tharisa able to provide an extra escalation reserve of $26-million should it be needed in today’s volatile world of escalation and inflation.
Under the Zimbabwean government, the project, with a total value of $686-million, has a five-year tax holiday.
Its internal rate of return is just over 26% and return on investment capital is 30%.
The earthworks contracter began clearing the site this week for earthworks terracing to begin in December.
“The accelerator is flat to the floor,” was how Pryor described the project’s pace.
Orders for ball mills and flotations cells, the two long-lead items, have been placed. The ball mills are on the critical path that defines the 24-month construction period and the advanced flotation cells area expected to lift metal recovery to 82%.
Civils contracts will be awarded this month and final negotiations are under way with the selected mining contractor, a mix a South African mining contractor and a local Zimbabwean mining contractor, and “we should execute that in the next few weeks”.
In a country described by Pryor as having an exceptional level of education and challenged employment, there has been a nigh hundred-to-one response to the ten senior jobs advertised.
“My experience here in Zimbabwe is that the workforce is very capable, educated and has a greats work ethic, which will certainly help us to bring this project in on time and on budget,” Pryor said.
A first-phase resource of just under 10-million ounces has a six-element grade of 2.04 g/t.
Typically, the reef horizons are between two and three metres thick and Karo will be targeting anywhere between 3 m and 5 m in terms of its mining proposition, Tharisa CEO Phoevos Pouroulis stated.
Currently Tharisa plc owns 70% and Leto Settlement the remaining 30% of Karo Mining Holdings plc, which in turn owns Karo Zimbabwe Holdings in joint venture with Generation Minerals, which is the Republic of Zimbabwe’s carried interest in the Karo Platinum project.
Pryor described environmental social and governance (ESG) as one of the project’s most important targets, along with International Finance Corporation-compliant performance standards being applied to the mining and concentrator processing plant.
“We still have the water supply and the power supply to be approved by the Zimbabwean government. Those are in process, and we see no real issues with them.
“In terms of the tailings dam, clearly a subject that is important to all miners, this is a structurally safe dam, rock built not earth or dam built, and it has been independently designed and checked by our consultants,” said Pryor.
The community is seen as key, with the two towns within 30 minutes’ drive of the project site earmarked for employee recruitment.
“We will prioritise local recruitment so that we can benefit the local communities as much as possible,” Pryor promised.
A dedicated social and environmental team of 12 people will ensure that all ESG obligations are met, he added.
Government has allocated new land for 12 households to be relocated and the new houses will be built according to laid-down standards in the next six to nine months, with previously absent power and water supply laid on.
GREEN E...