Snowy Hydro 2.0 was meant to be a nation building project, supposed to begin delivering green power to the grid by next year.
But the pumped hydro project in the Snowy Mountains of NSW has been up-ended by a single tunnelling machine called Florence that got bogged underground.
The mega project was once estimated to cost $2 billion, but is now four years behind schedule and forecast to cost much more.
Today, Four Corners reporter Angus Grigg on the mistakes that were made and the billions of taxpayer dollars they’ve cost.
Featured:
Angus Grigg, Four Corners reporter
4.5
5151 ratings
Snowy Hydro 2.0 was meant to be a nation building project, supposed to begin delivering green power to the grid by next year.
But the pumped hydro project in the Snowy Mountains of NSW has been up-ended by a single tunnelling machine called Florence that got bogged underground.
The mega project was once estimated to cost $2 billion, but is now four years behind schedule and forecast to cost much more.
Today, Four Corners reporter Angus Grigg on the mistakes that were made and the billions of taxpayer dollars they’ve cost.
Featured:
Angus Grigg, Four Corners reporter
73 Listeners
55 Listeners
855 Listeners
15 Listeners
17 Listeners
73 Listeners
14 Listeners
11 Listeners
7 Listeners
8 Listeners
2 Listeners
17 Listeners
104 Listeners
64 Listeners
6 Listeners
10 Listeners
13 Listeners
313 Listeners
7 Listeners
85 Listeners
149 Listeners
179 Listeners
249 Listeners
5 Listeners
64 Listeners
2 Listeners
2 Listeners