The North Star Rail line in Minnesota is being canceled after struggling with ridership, particularly following a devastating 98% drop during the pandemic. Though originally conceived as an 80-mile connection between Minneapolis and St. Cloud, budget constraints limited it to just 40 miles ending in Big Lake, setting the project up for challenges from the start.
• 40-mile commuter rail line with seven stations running from Minneapolis to Big Lake
• Pre-pandemic ridership approached 800,000 annually but collapsed to just 400 daily riders today
• Service reduction from six to four daily round trips further hampered recovery efforts
• Recent transit-oriented development along the route now threatened by line's cancellation
• Metropolitan Council replacing rail service with buses, reducing operating budget from $12M to $2M
• Original plan to extend to St. Cloud (population 70,000) never materialized
• Lack of stations in key areas like north Minneapolis likely limited potential ridership
• Political pressure accelerated the cancellation
Please like this video and leave a comment to help us out. Support the show directly through our Patreon, merch store, or by buying us a coffee.
Send us a text
Support the show
By Louis & Chris5
1515 ratings
The North Star Rail line in Minnesota is being canceled after struggling with ridership, particularly following a devastating 98% drop during the pandemic. Though originally conceived as an 80-mile connection between Minneapolis and St. Cloud, budget constraints limited it to just 40 miles ending in Big Lake, setting the project up for challenges from the start.
• 40-mile commuter rail line with seven stations running from Minneapolis to Big Lake
• Pre-pandemic ridership approached 800,000 annually but collapsed to just 400 daily riders today
• Service reduction from six to four daily round trips further hampered recovery efforts
• Recent transit-oriented development along the route now threatened by line's cancellation
• Metropolitan Council replacing rail service with buses, reducing operating budget from $12M to $2M
• Original plan to extend to St. Cloud (population 70,000) never materialized
• Lack of stations in key areas like north Minneapolis likely limited potential ridership
• Political pressure accelerated the cancellation
Please like this video and leave a comment to help us out. Support the show directly through our Patreon, merch store, or by buying us a coffee.
Send us a text
Support the show

8,764 Listeners

7,859 Listeners

10,745 Listeners

7,725 Listeners

426 Listeners

87,590 Listeners

112,758 Listeners

56,463 Listeners

10,271 Listeners

155 Listeners

916 Listeners

140 Listeners

5,475 Listeners

16,042 Listeners

2,289 Listeners