Interview with Peter Akerley, President & CEO of Erdene Resource Development Corp.
Our previous interview: https://www.cruxinvestor.com/posts/erdene-resource-development-tsxerd-fulfills-first-gold-pour-in-mongolias-bayan-khundii-8096
Recording date: 12th January 2026
Erdene Resource Development achieved first gold production at its Bayan Khundii mine in southwestern Mongolia during Q3 2025, marking a significant milestone for the junior miner. The company completed the $115 million construction in 22 months, meeting both timeline and budget targets despite operating in what was previously considered a challenging infrastructure environment.
The plant has reached nameplate capacity of 1,950 tons per day, currently processing material at approximately 2 g/t. Erdene is systematically increasing feed grades toward the 3.8 g/t reserve grade, targeting commercial production declaration by April 2026. The company transitioned from bulk mining during commissioning to selective high-grade operations, though technical refinements continue around blasting optimization and material handling.
The operating subsidiary carries $123 million in debt, comprising a $50 million commercial loan and approximately $60 million in shareholder loans from partner Mongolian Mining Corporation. Despite debt service obligations, partners approved a $10 million exploration budget for 2026, reflecting confidence that operations have achieved self-sustaining status.
Erdene's growth pipeline includes the Dark Horse satellite deposit containing 48,000 ounces at 7 g/t, scheduled for year-three production. The company is evaluating plant expansion options including gravity circuit additions and heap leach processing for oxide material. Major development projects include the Altan Nar gold-copper project advancing toward feasibility over three years and the Zuun Mod molybdenum-copper system delivering a preliminary economic assessment by mid-2026.
The strategic context has improved significantly since project conception. Infrastructure constraints that historically challenged southwestern Mongolia are being resolved through Chinese border power connectivity and road construction. Gold prices above $2,600 versus the $1,860 reserve base definition create substantial margin expansion potential, while lower cutoff grades expand the economic envelope across multiple deposits. CEO Peter Akerley describes the strategy as building "a new minerals district in southwestern Mongolia that ultimately will be a multi-mine producer of multiple commodities."
View Erdene Resource Development's company profile: https://www.cruxinvestor.com/companies/erdene-resource-development
Sign up for Crux Investor: https://cruxinvestor.com
By Crux Investor4.8
3232 ratings
Interview with Peter Akerley, President & CEO of Erdene Resource Development Corp.
Our previous interview: https://www.cruxinvestor.com/posts/erdene-resource-development-tsxerd-fulfills-first-gold-pour-in-mongolias-bayan-khundii-8096
Recording date: 12th January 2026
Erdene Resource Development achieved first gold production at its Bayan Khundii mine in southwestern Mongolia during Q3 2025, marking a significant milestone for the junior miner. The company completed the $115 million construction in 22 months, meeting both timeline and budget targets despite operating in what was previously considered a challenging infrastructure environment.
The plant has reached nameplate capacity of 1,950 tons per day, currently processing material at approximately 2 g/t. Erdene is systematically increasing feed grades toward the 3.8 g/t reserve grade, targeting commercial production declaration by April 2026. The company transitioned from bulk mining during commissioning to selective high-grade operations, though technical refinements continue around blasting optimization and material handling.
The operating subsidiary carries $123 million in debt, comprising a $50 million commercial loan and approximately $60 million in shareholder loans from partner Mongolian Mining Corporation. Despite debt service obligations, partners approved a $10 million exploration budget for 2026, reflecting confidence that operations have achieved self-sustaining status.
Erdene's growth pipeline includes the Dark Horse satellite deposit containing 48,000 ounces at 7 g/t, scheduled for year-three production. The company is evaluating plant expansion options including gravity circuit additions and heap leach processing for oxide material. Major development projects include the Altan Nar gold-copper project advancing toward feasibility over three years and the Zuun Mod molybdenum-copper system delivering a preliminary economic assessment by mid-2026.
The strategic context has improved significantly since project conception. Infrastructure constraints that historically challenged southwestern Mongolia are being resolved through Chinese border power connectivity and road construction. Gold prices above $2,600 versus the $1,860 reserve base definition create substantial margin expansion potential, while lower cutoff grades expand the economic envelope across multiple deposits. CEO Peter Akerley describes the strategy as building "a new minerals district in southwestern Mongolia that ultimately will be a multi-mine producer of multiple commodities."
View Erdene Resource Development's company profile: https://www.cruxinvestor.com/companies/erdene-resource-development
Sign up for Crux Investor: https://cruxinvestor.com

3,070 Listeners

148 Listeners

142 Listeners

94 Listeners

358 Listeners

263 Listeners

22 Listeners

3 Listeners

1,346 Listeners

375 Listeners

72 Listeners

277 Listeners

416 Listeners

13 Listeners

160 Listeners