  • Ep.354 - The Takt Production System - Part 18

    Detailing a CPM schedule at schematic design is not only a waste of time. It is useless, distracting, and irresponsible. Submitting a CPM schedule says we had one person detail this plan without team input and are now asking you to trust this person guessed what you want perfectly. Submitting a Takt plan says our team sketched out the simplest plan possible and we can quickly collaborate with you to accomplish your needs. Takt planning in schematic design is fast, nimble, and real time. Designers and stakeholders can learn to adjust the Takt plan themselves. This saves countless days redoing CPM schedules. Your scheduling department has more capacity to delight the owner in preconstruction. More time for constructability reviews, coordination, integration, design pull planning, cost estimation, target value design.

    What you'll learn in this episode:

    • Why proposal with Takt shows wisdom: uses historical production rates and process analysis instead of guessing detailed logic without design
    • The design development workflow: finalize strategy, identify constraints, perform Takt analysis, develop roadblock system, begin at 50 percent DD
    • The three huddles: afternoon format for day planning, morning worker for entire site, crew preparation 15 to 25 minutes with pretask plans
    • The five sections of integrated production control: plan, environment, accountability, continuous improvement, presumes respect and stability for workers
    • What workers need to succeed: what building, how to install, where to put it, materials, equipment, clean environment, safe environment

    The Takt plan is one of your best referencing tools when managing a project.

    If you like the Elevate Construction podcast, please subscribe for free and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 馃槉).

    Also, here are links to our YouTube Channels:

    路 Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg

    路 LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt

    路 LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured

    路 LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw

    33 min
  • Ep.353 - The Takt Production System - Part 17
    div]:bg-bg-000/50 [&_pre>div]:border-0.5 [&_pre>div]:border-border-400 [&_.ignore-pre-bg>div]:bg-transparent [&_.standard-markdown_:is(p,blockquote,h1,h2,h3,h4,h5,h6)]:pl-2 [&_.standard-markdown_:is(p,blockquote,ul,ol,h1,h2,h3,h4,h5,h6)]:pr-8 [&_.progressive-markdown_:is(p,blockquote,h1,h2,h3,h4,h5,h6)]:pl-2 [&_.progressive-markdown_:is(p,blockquote,ul,ol,h1,h2,h3,h4,h5,h6)]:pr-8" style= "box-sizing: border-box; --tw-border-spacing-x: 0; --tw-border-spacing-y: 0; --tw-translate-x: 0; --tw-translate-y: 0; --tw-rotate: 0; --tw-skew-x: 0; --tw-skew-y: 0; --tw-scale-x: 1; --tw-scale-y: 1; --tw-scroll-snap-strictness: proximity; --tw-ring-offset-width: 0px; --tw-ring-offset-color: #fff; --tw-ring-color: hsl(213 68% 50% / 1); --tw-ring-offset-shadow: 0 0 #0000; --tw-ring-shadow: 0 0 #0000; --tw-shadow: 0 0 #0000; --tw-shadow-colored: 0 0 #0000; outline-color: #2977d6; scrollbar-width: thin; scrollbar-color: rgba(31, 31, 30, 0.35) rgba(0, 0, 0, 0); position: relative; line-height: 1.65rem; font-family: 'Anthropic Serif', Georgia, 'Arial Hebrew', 'Noto Sans Hebrew', 'Times New Roman', Times, 'Hiragino Sans', 'Yu Gothic', Meiryo, 'Noto Sans CJK JP', 'PingFang TC', 'Microsoft JhengHei', 'Noto Sans CJK TC', 'PingFang SC', 'Microsoft YaHei', 'Noto Sans CJK SC', 'Apple SD Gothic Neo', 'Malgun Gothic', 'Noto Sans CJK KR', serif; border: 0px solid #1f1f1e;">

    There is one real parameter when creating a Takt plan. Do not overburden the system. If more crews are needed, make sure the market has them. If materials are needed at expedited rate, make sure supply chain can accommodate. Research drawings before going to software. Builders who go straight to drawings are different from builders who go straight to software. The latter method puts things in the wrong order. Preliminary Takt zones in Phoenix for hospital space start at 10,000 square feet. Eventually they reduce to 3,000 to 7,000 square feet. Preliminary Takt time is usually 3, 5, 7, or 10 days. Five is most common because it represents one work week. Little's Law shows the power of smaller zones. Five floors with 5-day Takt equals 45 days total. Same project with 1-day Takt equals 29 days.

    What you'll learn in this episode:

    • Why drawings come before software: builders visualize flow, see constraints, identify preliminary zones
    • Phoenix throughput rates: 10,000 square feet every 5 to 7 days, total process time 7.5 to 9 months
    • Little's Law optimization: 1-day Takt finishes in 53 percent of the time compared to 5-day Takt
    • The 15 Jason and Spencer rules: remove roadblocks daily is first priority, equal zones, deliveries on time or turned away, trades work weekends if not done
    • Why Takt handles changes better: stabilizes entire project so changes can be isolated and focused on with Last Planner or Scrum

    The difference with Takt is it is all downhill from here, whereas with CPM your nightmare is just beginning.

    If you like the Elevate Construction podcast, please subscribe for free and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 馃槉).

    Also, here are links to our YouTube Channels:

    路 Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg

    路 LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt

    路 LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured

    路 LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw

    1 hr 1 min
  • Ep.352 - The Takt Production System - Part 16

    There are three levels of Takt plan development. Macro level is the process analysis where you create the overall Takt plan and identify preliminary zones, time, and sequences. Norm level is harmonization where resource leveling occurs, buffers are integrated, and work steps are created for each work package. Micro level is crucial and cannot be omitted. This is where you detail work packages to make work ready, create quality deliverables and standard work, and begin Takt control meetings. There are three ways to implement Takt. Total Takt management is the preferred method because you achieve flow in all directions: workflow, logistical flow, and trade flow. Excel is viable and recommended for getting familiar. Tacting is free and forces proper planning. Timoti integrates with Last Planner. Be skeptical of applications that do not follow production laws.

    What you'll learn in this episode:

    • The three levels of Takt development: macro creates preliminary zones and sequences, norm adds work steps and buffers, micro details work packages and begins control meetings
    • Why total Takt management is preferred over integrated control: total management achieves flow in workflow, logistical flow, and trade flow simultaneously
    • The specific outputs at macro level: preliminary zones identified, preliminary time identified, sequences created by phase, phases networked with interdependence ties
    • Why Excel is recommended for initial plans: easy to manipulate, everyone has access, thoroughly tested, less friction when learning Takt
    • The warning about Last Planner applications: some tack on Takt as selling feature, applications must adapt to theory not the other way around

    Micro level planning is crucial and cannot be omitted from the system.

    If you like the Elevate Construction podcast, please subscribe for free and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 馃槉).

    Also, here are links to our YouTube Channels:

    路 Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg

    路 LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt

    路 LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured

    路 LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw

    11 min
  • Ep.351 - The Takt Production System - Part 15

    The current industry approach is chaos. Workers do not see the planning. Foremen try to follow an uncollaborative dictated schedule or they ignore it completely. The famous Office fire drill episode shows what this looks like. People run around in different directions with false urgency. Deadlines are unnecessary or too late. Teams throw workers, money, materials at the project. It is like putting out a fire with one hundred dollar bills. Last Planner and Scrum are better. They introduce phase planning with pull planning. Make ready schedules identify roadblocks. Workers receive 50 percent of planned information. The integrated production control system with Takt is best. Workers receive 75 percent of planned information. Information flows through multiple paths, not a single point of failure through the foreman.

    What you'll learn in this episode:

    • Why CPM creates chaos: look-ahead schedules are given to subs as directive without collaboration, workers do not see any planning
    • How Last Planner improves things: phase planning with pull planning, make ready schedules, weekly work plans, percent plan complete tracking
    • Why Takt with integrated production control is best: work packages and work steps planned early, roadblock removal is primary responsibility
    • The three huddles that get information to workers: afternoon format huddle 16 hours before work, morning worker huddle for entire site, crew preparation huddle with pretask plan
    • How information transfer improves from 50 percent with Last Planner to 75 percent with Takt because of multiple communication paths instead of single point of failure

    Workers see as much of the plan as possible and have input.

    If you like the Elevate Construction podcast, please subscribe for free and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 馃槉).

    Also, here are links to our YouTube Channels:

    路 Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg

    路 LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt

    路 LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured

    路 LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw

    23 min
  • Ep.350 - The Takt Production System - Part 14

    The parade of trades dice game reveals the power of flow. Red team rolls normal dice with numbers 1 to 6. Blue team rolls dice showing only 2, 3, and 4. Red team tries to move fast with 6s then hits painful 1s. Blue team maintains steady flow with no variation. Red team finishes in 26 weeks with 380 workers. Blue team finishes in 21 weeks with 280 workers. The cost difference is 8.8 million dollars. The factory example shows why. Four machines working at different speeds create inventory pileup between them. Workers stop running machines and start managing inventory. Throughput drops from 2 items per hour to 1.25 because of the waste. Movement does not equal production. Pushing creates variation and literally destroys projects.

    What you'll learn in this episode:

    • Why we level out bottlenecks by slowing faster trades: prevents stacking workers, burying scopes, installing too early, creating defects
    • How work in process destroys capacity: CPM pushes work to start early, team spends time managing overburden instead of removing roadblocks
    • The parade of trades math: 26 weeks times 380 workers equals 21.7 million versus 21 weeks times 280 workers equals 12.9 million
    • Why the factory throughput drops from 2 to 1.25 items per hour when machines run at different speeds and inventory piles up
    • How finish as you go and quality at the source require leveled work: you need capacity to focus on work in process and complete it right the first time

    Do not roll 6s and 1s when you can roll 3s.

    If you like the Elevate Construction podcast, please subscribe for free and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 馃槉).

    Also, here are links to our YouTube Channels:

    路 Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg

    路 LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt

    路 LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured

    路 LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw

    23 min
  • Ep.349 - The Takt Production System - Part 13

    CPM does not obey any of the four production laws. Little's Law says throughput time equals flow units times cycle time. CPM does not allow calculating optimal batch sizes. CPM does not help reduce work in process. CPM does not enable finishing as you go. The Bottleneck Law says every system has at least one constraint. CPM cannot see bottlenecks because you cannot see trade flow. The Law of Variation says as variation increases, duration increases. CPM is so chaotic it takes all management capacity just to update the schedule. Kingman's Formula calculates waiting time. CPM has no buffer strategy. Takt obeys all four production laws. Weak leaders and non-accountable trades will not like Takt because it requires holding the line and keeping rhythm.

    What you'll learn in this episode:

    • How Little's Law in Takt translates to: number of takt wagons plus number of takt areas minus one, multiplied by takt time equals duration
    • The FOCCCCUS bottleneck strategy: Find, Optimize, Coordinate, Collaborate, Curate, Upgrade, Start again
    • Why Takt takes one-twelfth the time to manage, freeing 55 percent of time from schedule management to roadblock removal
    • How to level trades using throughput times: if electrician takes 100 days and others take 50, add a second crew to match the rhythm
    • Why we focus on throughput and collective efficiency for all trades, not individual contractor efficiency

    We want everyone to succeed together as a group and optimize the project, not just individual companies.

    If you like the Elevate Construction podcast, please subscribe for free and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 馃槉).

    Also, here are links to our YouTube Channels:

    路 Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg

    路 LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt

    路 LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured

    路 LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw

    28 min
  • Ep.348 - The Takt Production System - Part 12

    Takt has been used successfully in Europe for over a century. The Empire State Building used it. The Pentagon renovation used it. Yet CPM continues to dominate in the United States. Do not build boats when you can build trains and railways. Rivers cannot be controlled. Railways let you control your destiny. Takt is a collaborative system where you predict what should take place and prepare for success instead of hoping for the best in the moment. Rhythm is smooth and smooth is fast. The decision is not between going fast and finishing early versus going slow and finishing late. The decision is between going fast and failing versus going at the right rhythm and finishing at the soonest possible moment.

    What you'll learn in this episode:

    • Why Takt shows what SHOULD be done and CPM guesses what WILL be done, which is why Takt brings problems to the surface faster
    • The four things needed to see a problem: know the target, see the deviation, see what it affects, see it within 5 to 48 hours (only Takt does all four)
    • How Takt takes one-twelfth the time to manage compared to CPM because teams focus on making work ready instead of managing the schedule
    • Why non-Takt meetings focus on when things should happen but Takt meetings already know when and focus on removing roadblocks
    • The four considerations for flow: rhythm, capacity, consistency, and continuity

    In non-Takt systems, teams spend most time managing the schedule instead of making work ready.

    If you like the Elevate Construction podcast, please subscribe for free and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 馃槉).

    Also, here are links to our YouTube Channels:

    路 Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg

    路 LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt

    路 LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured

    路 LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw

    24 min
  • Ep.347 - The Takt Production System - Part 11

    Flow is the single most important condition to strive for in construction. It is the most value-added effort on the journey to increase safety, customer delight, profits, employee satisfaction, and reduce production durations. Overproduction and excess inventory are the mother and father of all wastes. When we overproduce, we have excess inventory which needs to be transported and causes excess motion. The distraction of moving inventory creates defects or allows us to ignore them. Defects need to be fixed which causes overprocessing and that creates waiting. Workers are the heroes who make the money. We do not lose money while crews are working. We lose money when the flow of work or the crews are interrupted. Jason realizes there is no other system than Takt that implements the 14 principles of the Toyota Way.

    What you'll learn in this episode:

    • The four pillars of lean in construction: respect for people and resources, stable environments with flow, total participation with visual systems, continuous improvement
    • Why overproduction and inventory are the mother and father of all wastes and how they cascade into all other wastes
    • The stop, call, and wait principle: discover abnormality, stop the process, fix immediate problem, investigate root cause
    • How 3S (sort, straighten, sweep) creates the ability to find and see problems so they can be fixed
    • The 14 principles of the Toyota Way and why Takt is the only system that implements them (level workload, create continuous flow, use pull systems, stop to fix problems)

    We do not lose money while crews are working. We lose money when the flow of work or the crews are interrupted.

    If you like the Elevate Construction podcast, please subscribe for free and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 馃槉).

    Also, here are links to our YouTube Channels:

    路 Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg

    路 LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt

    路 LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured

    路 LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw

    25 min
  • Ep.346 - The Takt Production System - Part 10

    Takt planning is a one-page, one-process flow schedule that focuses on throughput, bottlenecks, and creating flow. The water vortex demonstrates why this works. Forcing water through the opening as fast as possible creates turbulence and takes 11 seconds. Creating a coordinated spiral flow with space in the center for air to rise takes 5 seconds. CPM pushes activities through as fast as possible and creates turbulence. Takt coordinates all parts to work together while giving space for roadblocks to rise and be removed. You can take the best basketball players in the world and encourage them to make slam dunks after placing the hoops 25 feet in the air, but they will fail. CPM puts Scrum and Last Planner into an impossible game with unrealistic dates and non-rhythmic milestones. Takt brings a game where we can win.

    What you'll learn in this episode:

    • Why Takt must show time and space and how they relate to workflow, trade flow, and logistical flow
    • The three main considerations in Takt planning: continuity (flow without interruption), rhythm (repetition at same rate), consistency (leveled materials and worker counts)
    • The difference between roadblocks (temporary, can be removed) and constraints (permanent, must work within them)
    • How flow enables long supply chains by holding consistent dates and reduces material inventory by bringing materials just in time
    • Why Scrum and Last Planner cannot maintain flow when based on CPM milestones because they are not receiving materials on time in the chaotic system

    When CPM puts Scrum and Last Planner into a game with unrealistic end dates, we are setting our hoops 25 feet in the air.

    If you like the Elevate Construction podcast, please subscribe for free and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 馃槉).

    Also, here are links to our YouTube Channels:

    路 Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg

    路 LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt

    路 LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured

    路 LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw

    20 min
  • Ep.345 - The Takt Production System - Part 9

    Takt is a holding system, not a push system. Holding means flow. When you flow you go fast, much like the Navy SEAL saying slow is smooth and smooth is fast. With lean, holding is smooth and smooth is fast. When the assistant super kept pushing the schedule instead of holding the Takt start dates, it caused friction with trade foremen. After three weeks of coaching, they transferred him to a different project. Within two weeks the entire site was in sync. Six weeks after implementing Takt, Jeff sees an entirely new job site. Clean bathrooms, air-conditioned lunch area, less workers on site due to flow efficiency, clean areas that crews control, foremen spending time with workers instead of tracking down procurement. Early pilot projects are seeing 20 percent time savings. Here is where we leave the characters behind and you become the main character of the book.

    What you'll learn in this episode:

    • Why foremen have been distracted making weekly work plans from scratch, tracking misaligned procurement, and orienting influx of different workers every week
    • How Takt enables safety by giving foremen the environment and capacity to control the site and protect their workers
    • Why one assistant super was transferred off the project for pushing instead of holding (Takt is a holding system not a push system)
    • The transformation Jeff sees six weeks later: clean, organized, fewer workers, stable procurement, workers who are happy
    • How Olivia scales Takt across all Evergreen projects with standardized systems: fresh eyes meetings, lean contracts, prefabrication as default, worker conditions, orientations

    When you can get flow, you can get safety.

    If you like the Elevate Construction podcast, please subscribe for free and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 馃槉).

    Also, here are links to our YouTube Channels:

    路 Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg

    路 LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt

    路 LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured

    路 LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw

    20 min