Jason argues there is no such thing as a critical path on well-planned projects. If a project has a critical path with zero float it already is set up for failure with no buffers or contingencies. CPM schedules hide whose fault delays are which benefits owners and GCs but hurts trade partners. In Europe owners have more contractual risk so they use Takt, in the United States everyone contracts out risk so CPM prefers to hide problems in chaos.
What you'll learn in this episode:
Projects should have at least 3 percent buffers not 100 percent efficiency, focus on flow of the entire system not critical path.
If you like the Elevate Construction podcast, please subscribe for free and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 😊).
Also, here are links to our YouTube Channels:
· Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg
· LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt
· LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured
· LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw
By Jason Schroeder4.9
139139 ratings
Jason argues there is no such thing as a critical path on well-planned projects. If a project has a critical path with zero float it already is set up for failure with no buffers or contingencies. CPM schedules hide whose fault delays are which benefits owners and GCs but hurts trade partners. In Europe owners have more contractual risk so they use Takt, in the United States everyone contracts out risk so CPM prefers to hide problems in chaos.
What you'll learn in this episode:
Projects should have at least 3 percent buffers not 100 percent efficiency, focus on flow of the entire system not critical path.
If you like the Elevate Construction podcast, please subscribe for free and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 😊).
Also, here are links to our YouTube Channels:
· Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg
· LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt
· LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured
· LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw

14,277 Listeners

4,388 Listeners

30,785 Listeners

32,784 Listeners

7,205 Listeners

12,147 Listeners

13,987 Listeners

1,135 Listeners

2,288 Listeners

2,593 Listeners

4,045 Listeners

2,209 Listeners

52 Listeners

380 Listeners

7 Listeners