Are you more confident in working overtime than you should be? In this episode, Jason unpacks the truth about overtime based on a Construction Industry Cost Effectiveness Task Force report from November 1980. You'll learn why overtime disrupts the local economy and reduces productivity (60+ hours/week for 2+ months delays completion beyond what 40-hour weeks could achieve with same crew), the productivity decline timeline (starts immediately, recovers briefly, then steady decline, at week 6 working 60 hours you're at 75% capacity, week 12 at 62% capacity), why light work takes 3 hours to produce 2 additional hours of output and heavy work takes 2 hours to produce 1 hour, the auction atmosphere created when one project goes to overtime, and why the return on investment disappears after 6-9 weeks depending on hours worked.
What you'll learn in this episode:
Overtime extends projects: 60+ hours/week for 2+ months causes decreased productivity that delays completion beyond what could have been realized with same crew size on 40-hour week; disrupts economy, magnifies labor shortage, creates excessive inflation without benefit to schedule
Productivity decline is brutal: Light work, takes 3 hours to produce 2 additional hours output; Heavy work—takes 2 hours to produce 1 hour additional output; 8-hour day = 120 pieces/hour, 9-hour day = 100 pieces/hour
Timeline of decline: Productivity drops initially, recovers by end of week 1, holds 2-3 weeks, declines next 2-3 weeks, further drop at 5-6 weeks, hits low point at 9-12 weeks; Working 50 hours/week: Week 6 at 85% capacity, Week 12 at 72%; Working 60 hours/week: Week 6 at 75%, Week 12 at 62%
Auction atmosphere: When one project goes to overtime, other projects go to overtime to hold labor creating bidding process; local labor supply constant but additional capacity of transient workers offset by reduced productivity of all workers on overtime
Return on investment disappears: 60+ hours/week = no ROI after 6 weeks, 50-60 hours/week = 7.5 weeks, 40+ hours/week = 9 weeks; at 65 hours/week you pay twice as much per unit hour; all negative conditions still happen within those weeks
"The current condition is we throw money and manpower at things to try and fix them. All of the negative adverse conditions still happen. After 9 weeks there is no return on investment even from a productivity or completion standpoint. When we increase manpower and overtime, it increases costs, safety issues, fatigue, and in most cases we're extending the overall project duration."
If you like the Elevate Construction podcast, please subscribe for free, and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 😊).
Also, here are links to our YouTube Channels:
· Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg
· LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt
· LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured
· LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw
By Jason Schroeder4.9
139139 ratings
Are you more confident in working overtime than you should be? In this episode, Jason unpacks the truth about overtime based on a Construction Industry Cost Effectiveness Task Force report from November 1980. You'll learn why overtime disrupts the local economy and reduces productivity (60+ hours/week for 2+ months delays completion beyond what 40-hour weeks could achieve with same crew), the productivity decline timeline (starts immediately, recovers briefly, then steady decline, at week 6 working 60 hours you're at 75% capacity, week 12 at 62% capacity), why light work takes 3 hours to produce 2 additional hours of output and heavy work takes 2 hours to produce 1 hour, the auction atmosphere created when one project goes to overtime, and why the return on investment disappears after 6-9 weeks depending on hours worked.
What you'll learn in this episode:
Overtime extends projects: 60+ hours/week for 2+ months causes decreased productivity that delays completion beyond what could have been realized with same crew size on 40-hour week; disrupts economy, magnifies labor shortage, creates excessive inflation without benefit to schedule
Productivity decline is brutal: Light work, takes 3 hours to produce 2 additional hours output; Heavy work—takes 2 hours to produce 1 hour additional output; 8-hour day = 120 pieces/hour, 9-hour day = 100 pieces/hour
Timeline of decline: Productivity drops initially, recovers by end of week 1, holds 2-3 weeks, declines next 2-3 weeks, further drop at 5-6 weeks, hits low point at 9-12 weeks; Working 50 hours/week: Week 6 at 85% capacity, Week 12 at 72%; Working 60 hours/week: Week 6 at 75%, Week 12 at 62%
Auction atmosphere: When one project goes to overtime, other projects go to overtime to hold labor creating bidding process; local labor supply constant but additional capacity of transient workers offset by reduced productivity of all workers on overtime
Return on investment disappears: 60+ hours/week = no ROI after 6 weeks, 50-60 hours/week = 7.5 weeks, 40+ hours/week = 9 weeks; at 65 hours/week you pay twice as much per unit hour; all negative conditions still happen within those weeks
"The current condition is we throw money and manpower at things to try and fix them. All of the negative adverse conditions still happen. After 9 weeks there is no return on investment even from a productivity or completion standpoint. When we increase manpower and overtime, it increases costs, safety issues, fatigue, and in most cases we're extending the overall project duration."
If you like the Elevate Construction podcast, please subscribe for free, and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 😊).
Also, here are links to our YouTube Channels:
· Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg
· LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt
· LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured
· LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw

14,277 Listeners

4,388 Listeners

30,785 Listeners

32,784 Listeners

7,205 Listeners

12,147 Listeners

13,987 Listeners

1,135 Listeners

2,288 Listeners

2,593 Listeners

4,045 Listeners

2,209 Listeners

52 Listeners

380 Listeners

7 Listeners