Jason continues recording from his hotel in Mexico and takes on the short interval scheduling responsibilities of foremen and assistant superintendents. He walks through the history from 1965 push CPM lookaheads, through the last planner system with weekly work plans and percent plan complete, all the way to today's gap where many new foremen and supers can't even create a three week schedule themselves. He lays out the good, better, and best progression and lands on Takt control as the highest expression of short interval execution, where standard work steps inside each Takt wagon get refined cycle after cycle.
What you'll learn in this episode:
Why every superintendent and foreman must be able to build a Gantt chart in Excel at minimum
The history of short interval planning from CPM lookaheads to last planner to Takt control
Good, better, best: super made lookaheads, last planner pull plans, then Takt control
Why Takt control targets 100 percent completion of work steps inside each Takt wagon, not just 80 percent PPC
How standard work sequences inside cycle times let foremen perfect a plan instead of inventing a new one each week
If every week is a fresh round of chaos, the system is broken. Standardize the cycle, control the Takt, and let the work get better every time around.
If you like the Elevate Construction podcast, please subscribe for free, and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 😊).
Also, here are links to our YouTube Channels:
· Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg
· LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt
· LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured
· LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw
By Jason Schroeder4.9
139139 ratings
Jason continues recording from his hotel in Mexico and takes on the short interval scheduling responsibilities of foremen and assistant superintendents. He walks through the history from 1965 push CPM lookaheads, through the last planner system with weekly work plans and percent plan complete, all the way to today's gap where many new foremen and supers can't even create a three week schedule themselves. He lays out the good, better, and best progression and lands on Takt control as the highest expression of short interval execution, where standard work steps inside each Takt wagon get refined cycle after cycle.
What you'll learn in this episode:
Why every superintendent and foreman must be able to build a Gantt chart in Excel at minimum
The history of short interval planning from CPM lookaheads to last planner to Takt control
Good, better, best: super made lookaheads, last planner pull plans, then Takt control
Why Takt control targets 100 percent completion of work steps inside each Takt wagon, not just 80 percent PPC
How standard work sequences inside cycle times let foremen perfect a plan instead of inventing a new one each week
If every week is a fresh round of chaos, the system is broken. Standardize the cycle, control the Takt, and let the work get better every time around.
If you like the Elevate Construction podcast, please subscribe for free, and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 😊).
Also, here are links to our YouTube Channels:
· Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg
· LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt
· LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured
· LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw

14,277 Listeners

4,388 Listeners

30,785 Listeners

32,784 Listeners

7,205 Listeners

12,147 Listeners

13,987 Listeners

1,135 Listeners

2,288 Listeners

2,593 Listeners

4,045 Listeners

2,209 Listeners

52 Listeners

380 Listeners

7 Listeners