Jason records through allergy raspiness and shares a moment of clarity from a recent Takt simulation he ran with Spencer Easton in Indianapolis. After watching a team go from 16 minutes in round one, down to 9 to 11 minutes with Takt, and finally to 4 minutes 55 seconds with Takt control, he points to what actually made the difference: the huddles, pre install meetings, first run studies, and mockups. The line that came out of the room is the title of the episode: quality is not a quality system, it's a flow system.
What you'll learn in this episode:
The Takt simulation results: 16 minutes baseline, down to 4 minutes 55 seconds with full Takt control, a 66 percent reduction
Why huddles, mockups, pre install meetings, and first run studies are flow tools, not just quality tools
Why installing it right the first time is the fastest way to gain schedule, not the slowest
The two to twelve times multiplier of rework when quality is skipped
The reframe: when you need to hurry up, you add quality steps, you don't remove them
Quality control isn't a separate department to be managed. It's how the schedule actually flows.
If you like the Elevate Construction podcast, please subscribe for free, and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 😊).
Also, here are links to our YouTube Channels:
· Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg
· LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt
· LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured
· LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw
By Jason Schroeder4.9
139139 ratings
Jason records through allergy raspiness and shares a moment of clarity from a recent Takt simulation he ran with Spencer Easton in Indianapolis. After watching a team go from 16 minutes in round one, down to 9 to 11 minutes with Takt, and finally to 4 minutes 55 seconds with Takt control, he points to what actually made the difference: the huddles, pre install meetings, first run studies, and mockups. The line that came out of the room is the title of the episode: quality is not a quality system, it's a flow system.
What you'll learn in this episode:
The Takt simulation results: 16 minutes baseline, down to 4 minutes 55 seconds with full Takt control, a 66 percent reduction
Why huddles, mockups, pre install meetings, and first run studies are flow tools, not just quality tools
Why installing it right the first time is the fastest way to gain schedule, not the slowest
The two to twelve times multiplier of rework when quality is skipped
The reframe: when you need to hurry up, you add quality steps, you don't remove them
Quality control isn't a separate department to be managed. It's how the schedule actually flows.
If you like the Elevate Construction podcast, please subscribe for free, and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 😊).
Also, here are links to our YouTube Channels:
· Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg
· LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt
· LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured
· LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw

14,277 Listeners

4,388 Listeners

30,785 Listeners

32,784 Listeners

7,205 Listeners

12,147 Listeners

13,987 Listeners

1,135 Listeners

2,288 Listeners

2,593 Listeners

4,045 Listeners

2,209 Listeners

52 Listeners

380 Listeners

7 Listeners