  • Ep.719 - Lean Onboarding Series - Bottlenecks

    Jason explains the concept of bottlenecks in construction, whether they show up as slow trades (like mechanical or specialty flooring), difficult zones (like high-bay formwork), or bottlenecks in information or material flow, and introduces a key production law: once one bottleneck is fixed, another will always emerge. Using the vivid image of a garden hose nozzle, he makes the point that adding pressure (pushing harder) never speeds up a bottleneck; only widening it does, meaning teams must constantly hunt for and optimize whatever is currently the slowest link rather than assuming the job is ever fully "solved."

    What you'll learn from this episode:

    • The difference between a bottleneck trade (like mechanical or flooring) and a bottleneck zone (like complex high-bay formwork)
    • The core law of bottlenecks: fixing one always reveals another, so the search for the current constraint never truly ends
    • Why adding pressure or pushing harder never speeds up a bottleneck, only widening the actual constraint does
    • Why bottlenecks aren't inherently bad, they can even be useful (like regulating flow), but they must be identified and managed
    • A practical mindset: constantly look for the slowest trade, zone, or process and optimize it before moving on to the next one

    Have you identified your project's current bottleneck, and are you widening it, or just pushing harder against it?

    If you like the Elevate Construction podcast, please subscribe for free, and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 😊).

    Also, here are links to our YouTube Channels:

    · Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg

    · LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt

    · LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured

    · LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw

    8 min
  • Ep.718 - Lean Onboarding Series - Variation

    Jason introduces the concept of variation as a core production law: the more a project deviates from its established plan, the longer it will take. He walks through a real ripple-effect example, a concrete crew's plan changing mid-task, to show how one small decision can trigger 15 or more downstream disruptions, from returning materials to rerouting crews to reordering supplies. His core message: variation itself is the enemy, alongside waste, and the job of foremen and superintendents is to protect day-level and week-level plans once they're set, holding the line against unnecessary changes so crews can actually execute what was planned.

    What you'll learn in this episode:

    • The production law of variation: the more a plan changes, the longer the overall project duration becomes
    • A real example showing how one small mid-task change can ripple into 15 or more downstream disruptions
    • Why day plans especially should be protected from variation once established, so crews can execute without disruption
    • Why variation (alongside waste) is framed as "the enemy" in construction production, not just an occasional inconvenience
    • The core response to variation: plan ahead, prepare the work, and hold the line on established day and week plans

    How much of your project's schedule slippage is really coming from waste, versus from variation, changes and disruptions to plans that were already set?

    If you like the Elevate Construction podcast, please subscribe for free, and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 😊).

    Also, here are links to our YouTube Channels:

    · Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg

    · LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt

    · LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured

    · LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw

    6 min
  • Ep.717 - Lean Onboarding Series - Finishing as You Go!

    Jason makes a forceful case for one of construction's most overlooked disciplines: finishing as you go instead of rushing through work and coming back to fix it later. He argues that "production" isn't about how fast you can move through a building, it's about how fast you can finish work completely so no one ever has to return to it, using a vivid concrete-crew example (formwork, honeycombing, spilled cement) to show how skipping small finishing steps in the moment creates two or three times the rework cost later. The real fix, he says, is committing to versatile, cross-trained crews and daily zone-by-zone inspection so trades genuinely leave each area ready for the next.

    What you'll learn in this episode:

    • Why "production" should mean finishing work completely, not just moving through space quickly
    • A real concrete-crew example showing how skipping small finishing steps (patching, cleaning, scraping) creates costly rework down the line
    • Why trades need more versatile, cross-trained crews so they can complete an entire phase in a zone instead of leaving partial work behind
    • Why daily zone-by-zone inspection is essential to confirm work is truly finished before crews move on
    • Why punch lists should take one or two weeks at most, not months, if finishing as you go is actually being practiced

    Is your crew finishing each zone completely before moving on, or leaving small things "for later" that will cost far more time and money down the road?

    If you like the Elevate Construction podcast, please subscribe for free, and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 😊).

    Also, here are links to our YouTube Channels:

    · Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg

    · LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt

    · LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured

    · LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw

    9 min
  • Ep.716 - Lean Onboarding Series - Leveling Work

    Jason breaks down leveling as one of the most critical (and misunderstood) levers for creating true flow on a construction project. Rather than making zones equal in size, he argues zones should be equal in work density, so a smaller, more complex zone and a larger, simpler zone can still take the same amount of time to complete. Using a memorable supermarket checkout analogy, where one shopper paying in loose change bottlenecks the entire line, he shows why leveling crew capacity within each trade matters just as much as leveling zone sizes, and how breaking up or combining crews keeps the whole "train of trades" moving at a consistent pace.

    What you'll learn in this episode:

    • Why zones should be leveled by work density, not by square footage or shape
    • How Little's Law and intentional zoning prevent overloading crews with more work than they can reasonably handle
    • The supermarket checkout analogy: why one slow, bottlenecked trade can stall an entire train of trades, just like a shopper paying in pennies
    • How to fix a bottleneck trade: either speed them up, split their crew into smaller parallel groups, or remove them from the critical path
    • The five key concepts for creating true flow: common direction, equal distance, equal speed, leveled work density per zone, and leveled crew capacity

    Is there a bottleneck trade on your project quietly slowing down everyone else in the sequence behind them?

    If you like the Elevate Construction podcast, please subscribe for free, and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 😊).

    Also, here are links to our YouTube Channels:

    · Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg

    · LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt

    · LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured

    · LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw

    9 min
  • Ep.715 - Lean Onboarding Series - Smaller Batch Areas

    Jason challenges a rule of thumb he was originally taught, using roughly 10,000 to 18,000 square foot zones, as mathematically wrong, and introduces Little's Law to explain why. He walks through the formula (wagons plus zones minus one, multiplied by Takt time) to show that increasing the number of zones on the same floor, while shrinking their size, consistently produces a shorter overall project duration. The real insight: trades often prefer large zones not because it makes them more productive, but because it makes them feel like the area ahead is fully "ready," when smaller, well-tracked zones can deliver that same confidence while moving the whole trade sequence through the building faster.

    What you'll learn in this episode:

    • Why the old rule of thumb of 10,000 to 18,000 square foot zones is mathematically the wrong way to size sequences
    • How Little's Law and the Takt duration formula show that more (smaller) zones shorten overall project duration
    • Why trades often prefer large zones out of a feeling of readiness, not because it actually increases productivity
    • How smaller, well-tracked zones let trades work closer together while still confirming the work ahead is ready
    • Why right-sizing zones, not defaulting to large batch areas, is a core lever for speeding up any Takt-planned project

    Is your project defaulting to large zone sizes out of habit or comfort, when smaller, well-tracked zones could actually finish the job faster?

    If you like the Elevate Construction podcast, please subscribe for free, and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 😊).

    Also, here are links to our YouTube Channels:

    · Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg

    · LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt

    · LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured

    · LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw

    7 min
  • Ep.714 - Lean Onboarding Series - The Last Planner System

    Jason gives a thorough overview of the Last Planner System as part of his onboarding series, walking through the full chain of schedule deliverables from the master schedule down to daily huddles. He explains how pull planning brings foremen and lead persons into refining the sequence, how the six-week make-ready look-ahead plan focuses on making activities truly ready (labor, materials, tools, equipment, information), and how the weekly work plan and daily huddles turn commitments into an executable plan tracked through percent plan complete. He closes by framing Last Planner not just as a set of tools, but as a culture shift, away from command-and-control leadership and toward genuinely listening to the people doing the work.

    What you'll learn in this episode:

    • The full chain of Last Planner deliverables: master schedule, pull plans/phase plans, the six-week make-ready look-ahead plan, weekly work plans, and daily huddles
    • Why the six-week look-ahead plan exists to make activities truly "ready" (labor, materials, tools, equipment, information) and surface roadblocks early
    • How percent plan complete (PPC) is tracked and scored differently depending on whether the master schedule is CPM (80-85% target) or Takt (100% target)
    • Why "last planners" refers to foremen and lead persons, the people closest to the actual work, not just superintendents
    • Why the Last Planner System is as much a cultural shift toward listening and collaboration as it is a set of scheduling tools

    Is your project actually using the full chain of Last Planner deliverables, or just borrowing the name without the real collaboration behind it?

    If you like the Elevate Construction podcast, please subscribe for free, and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 😊).

    Also, here are links to our YouTube Channels:

    · Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg

    · LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt

    · LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured

    · LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw

    8 min
  • Ep.713 - Lean Onboarding Series - Holding Start Dates

    Jason explains why crews finishing early within their Takt zone should almost never rush into the next area, but instead use that leftover time as a buffer for preparation, quality checks, and continuous improvement. Drawing on military research showing troops can march up to twice as far with short, regular breaks, and a relatable analogy about a professor moving up a deadline just because a student finished early, he makes the case that holding start dates protects quality, safety, and morale far better than pushing ahead just because the work is technically done.

    What you'll learn in this episode:

    • Why finishing early in a Takt zone should trigger preparation and regrouping, not an immediate rush into the next area
    • The military research showing troops march up to 100% farther when given regular short breaks
    • What that buffer time should actually be used for: 5S-ing tools, pre-staging materials, refreshing layout, training, and reflecting as a team
    • Why pushing crews to move faster just because they finished early undermines quality, safety, and long-term production
    • The one exception: moving ahead is fine only when it's a mutual, unforced decision between trade partners, not the default expectation

    Are your crews using extra time within their zone to genuinely prepare for what's next, or are they being pushed to rush into the next area the moment they finish?

    If you like the Elevate Construction podcast, please subscribe for free, and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 😊).

    Also, here are links to our YouTube Channels:

    · Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg

    · LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt

    · LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured

    · LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw

    6 min
  • Ep.712 - Lean Onboarding Series - Zones, Takt Time, & Work Packages

    Continuing the onboarding series, Jason explains why every construction project should be broken into zones, each with its own planned, built, and finished scope of work before moving on, rather than assigning trades vague durations for an entire floor or building. He walks through the core discipline of "plan it, build it right, finish it" within each zone, and shares what he considers one of the most important habits in the entire series: superintendents checking in daily with foremen in each zone, punching out yesterday's fixes on the spot and walking tomorrow's area to clear roadblocks before they stop work.

    What you'll learn from this episode:

    • Why every project should be divided into zones (or sequences) with a specific duration for each, rather than one big duration for a whole floor or building
    • The discipline of "plan it, build it right, finish it" within each zone before moving crews to the next area
    • Why stopping and fixing quality issues immediately, rather than adding them to a list for later, saves far more time than it costs
    • The daily superintendent-foreman habit that Jason considers one of the most important in the entire series: reviewing yesterday's work and walking tomorrow's zone together
    • How isolating scope within zones sets up the conditions for true one-process flow

    Does your project break work into clear, planned zones with a defined duration, or are trades left with a vague "get it done somewhere in this floor" assignment?

    If you like the Elevate Construction podcast, please subscribe for free, and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 😊).

    Also, here are links to our YouTube Channels:

    · Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg

    · LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt

    · LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured

    · LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw

    5 min
  • Ep.711 - Lean Onboarding Series - Takt, Last Planner, Scrum, & CPM

    Continuing his onboarding series on flow and pull, Jason breaks down the four major scheduling systems used in construction and how each relates to creating true flow on a project: Takt planning (a visual, color-coded master schedule that keeps trades moving at the same speed and distance), the Last Planner System (a collaborative process where foremen, the true "last planners," help confirm sequence and build weekly work plans), Scrum (a to-do/doing/done board that keeps office staff focused on unblocking the field), and CPM (a computer-networked scheduling method useful only at a high summary level, never for detailed field planning). He closes with practical tips, working one process at a time, consistent crews, installing work right the first time, and finishing as you go, for anyone trying to actually maintain flow on site.

    What you'll learn in this episode:

    • What Takt planning is and how it visually keeps trades moving at the same speed and distance across a project
    • Why the Last Planner System exists to bring foremen's real-world wisdom into the schedule instead of a top-down, forced plan
    • How Scrum boards help office teams prioritize the tasks that create flow for the field
    • Why CPM schedules work only as high-level summaries and become dangerous when used for detailed trade sequencing
    • Practical habits that maintain flow: one process at a time, consistent crews, quality installation the first time, and finishing as you go

    Do you know how to read your project's schedule, whether it's Takt, Last Planner, Scrum, or CPM, well enough to spot a roadblock before it stops your work?

    If you like the Elevate Construction podcast, please subscribe for free, and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 😊).

    Also, here are links to our YouTube Channels:

    · Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg

    · LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt

    · LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured

    · LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw

    9 min
  • Ep.710 - Lean Onboarding Series - Flow and Pull

    Jason introduces a foundational Lean distinction: the difference between flow and pull. Pull means each trade or process moves at the pace set by whoever's ahead of them, speeding up or slowing down to match, and materials get delivered just in time to the point of work rather than staged in advance. Flow, by contrast, regulates both the speed and the distance between trades, so everyone moves at a consistent, steady pace through the building rather than adjusting to whoever's setting the pace. Using Eli Goldratt's hiking-line story from The Goal and a real anecdote about a failing Tucson project turned around by putting trades back into rhythm, Jason makes the case that flow is the ideal, pull is the acceptable fallback, and pushing everyone around chaotically is never acceptable.

    What you'll learn in this episode:

    • The core difference between pull (matching the pace of whoever's ahead of you) and flow (a regulated, consistent speed and distance for everyone)
    • Why pull means producing based on customer demand and delivering materials just in time to the point of work
    • The hiking-line story from The Goal, and why putting the "slow kids" in front creates rhythm instead of chaotic starts and stops
    • A real story about a failing Tucson project turned around by sending everyone home, building a real plan, and bringing trades back into a consistent rhythm
    • Why flow is the ideal goal, pull is an acceptable fallback, but pushing crews around with no regard for pace or distance is never acceptable

    Is your own project actually flowing at a consistent pace and distance, or is it just barely surviving on scattered, chaotic pushing?

    If you like the Elevate Construction podcast, please subscribe for free, and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 😊).

    Also, here are links to our YouTube Channels:

    · Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg

    · LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt

    · LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured

    · LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw

    10 min

About Elevate Construction

From the publisher's feed

Elevating construction with interviews, training, and techniques that will make the build environment better for workers, our customers, companies, and the industry as a whole.

More shows like Elevate Construction

The Art of Manliness by The Art of Manliness

The Art of Manliness

14,287 Listeners

EntreLeadership by Ramsey Network

EntreLeadership

4,374 Listeners

Jocko Podcast by Jocko DEFCOR Network

Jocko Podcast

30,725 Listeners

REAL AF with Andy Frisella by Andy Frisella

REAL AF with Andy Frisella

32,768 Listeners

The Human Upgrade: Biohacking for Longevity & Performance by Dave Asprey

The Human Upgrade: Biohacking for Longevity & Performance

7,181 Listeners

Mind Pump: Raw Fitness Truth by Sal Di Stefano, Adam Schafer, Justin Andrews, Doug Egge

Mind Pump: Raw Fitness Truth

12,100 Listeners

THE ED MYLETT SHOW by Ed Mylett

THE ED MYLETT SHOW

13,962 Listeners

Modern Craftsman by Modern Craftsman

Modern Craftsman

1,141 Listeners

Bedros Keuilian Podcast Show by Bedros Keuilian

Bedros Keuilian Podcast Show

2,293 Listeners

Front Row Seat with Ken Coleman by Ramsey Network

Front Row Seat with Ken Coleman

2,581 Listeners

Modern Wisdom by Chris Williamson

Modern Wisdom

4,096 Listeners

A Bit of Optimism by Simon Sinek

A Bit of Optimism

2,212 Listeners

Contractor Evolution by Breakthrough Academy

Contractor Evolution

54 Listeners

The Build Show Podcast by Matt Risinger

The Build Show Podcast

381 Listeners

Takt Construction by Jason Schroeder & Kevin Rice

Takt Construction

7 Listeners