In today's short podcast, Bryan explores the differences between startup and commissioning.
Startups typically involve going in during the construction phase after the drywall has been sealed up. (Vents, ducts, and copper piping typically go in before the drywall.) A technician can then perform a startup. The startup includes testing the drain line, checking the charge, checking for leaks, and seeing if the equipment performs its most basic function. (Does the gas furnace make flame? Does the A/C unit blow cold air?)
The startup's goal is to get the equipment working. A startup does NOT focus on peak performance. A good startup will typically suffice for a cookie-cutter residential construction.
Conversely, the goal of commissioning is to optimize the equipment and test the advanced functions. Combustion analysis, airflow tests, and dehumidification tests all fall under the "commissioning" umbrella. Commissioning is where we use Manual S and Manual J to see if the equipment is appropriate for the home. Data collection, especially on sensible and latent capacities, is the core element of commissioning.
Commissioning also involves checking up on secondary functions, such as checking if heat strips activate during defrost. A custom construction plan will require commissioning to ensure that the equipment runs optimally in the uniquely designed space.
So, in short, equipment startup is about making sure the equipment works as it should on a basic level. On the other hand, commissioning uses data and specific instrumentation to make sure the equipment is running to its design and full potential.
Bryan also covers:
If you have an iPhone, subscribe to the podcast HERE, and if you have an Android phone, subscribe HERE.
By Bryan Orr4.9
10031,003 ratings
In today's short podcast, Bryan explores the differences between startup and commissioning.
Startups typically involve going in during the construction phase after the drywall has been sealed up. (Vents, ducts, and copper piping typically go in before the drywall.) A technician can then perform a startup. The startup includes testing the drain line, checking the charge, checking for leaks, and seeing if the equipment performs its most basic function. (Does the gas furnace make flame? Does the A/C unit blow cold air?)
The startup's goal is to get the equipment working. A startup does NOT focus on peak performance. A good startup will typically suffice for a cookie-cutter residential construction.
Conversely, the goal of commissioning is to optimize the equipment and test the advanced functions. Combustion analysis, airflow tests, and dehumidification tests all fall under the "commissioning" umbrella. Commissioning is where we use Manual S and Manual J to see if the equipment is appropriate for the home. Data collection, especially on sensible and latent capacities, is the core element of commissioning.
Commissioning also involves checking up on secondary functions, such as checking if heat strips activate during defrost. A custom construction plan will require commissioning to ensure that the equipment runs optimally in the uniquely designed space.
So, in short, equipment startup is about making sure the equipment works as it should on a basic level. On the other hand, commissioning uses data and specific instrumentation to make sure the equipment is running to its design and full potential.
Bryan also covers:
If you have an iPhone, subscribe to the podcast HERE, and if you have an Android phone, subscribe HERE.

229,195 Listeners

30,828 Listeners

151 Listeners

75 Listeners

210 Listeners

111 Listeners

725 Listeners

15 Listeners

45,718 Listeners

87 Listeners

85 Listeners

16 Listeners

16,993 Listeners

31 Listeners

6 Listeners